PROPOSED COMMISSIONING SCHEDULE

Project : Big Blue Project - C05 Steam Boiler Works


Client : Dutch Lady Milk Industries Berhad

Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
BOILER -

1 HT preparation & Internal HT

2 Official HT with JKKP (

PRE-COMMISSIONING

4 Follow all installation as PID

5 Check electrical termination as drawing

6 Do functional test for motor,instrument and etc

Do functional test for mechanical part (open and close


7
valve)

8 Check all equipment and tigthen all bolt & nut

9 Check as per electrical check list

10 Follow as commissioning process

11 Power up panel

12 Check and power up instrument

COMMISSIONING

13 Power up Burner

14 Check interlock for all system applied

15 Slow firing and chemical boil out (client scope)

16 Setting on Instrument

17 Raise pressure and Safety Valve testing

18 Steam Test With JKKP

THINGS REQUIRED FROM CLIENT

1)GAS SUPPLY Prepared by:

2)WATER SUPPLY Sureyaprekgas, 22/6/23

3)ELECTRIC SUPPLY

4) COMPRESSED AIR SUPPLY