Check
Weekly Check Check Check
Weekly Monthly Quarterly
Date:
Visually inspect the pads • Check bleed-off rate and • Drain and disinfect the
Initials:
for bowing, sagging or dry adjust if necessary. entire water distribution
Notes: streaks. system.
Inspect the sump, remove • Check water flow rate and
any debris and make sure the adjust if necessary.
water level is correct.
Check the water distribution • Check pumps and clean Bleed Off
system for leaks and clogged any debris from the inlet. • Bleed off water continuously to
Check water distributor holes. prevent the concentration of
Monthly minerals.
Date:
Scale Control • Start with 1 gallon/hour (GPH)
for each linear foot of cooling
• Maintain a pH between 7 and 9 in the sump and 6 and 9 for make-up water supply.
Initials: system and adjust as needed
• Make sure the flow of water is even from one end of the distributor pipe to the
Notes: other. • The following formula and table
• Water flow should be 0.75 gpm per linear foot for a 6” pad. is to help in calculating your
• Use plenty of Bleed Off. bleed off rate.