1 BURDEN 8 m 2 SPACING 9 m 3 STEMMING 4.3 m 4 POWDER CHARGE 3.7 m 5 KEDALAMAN LUBANG 8.5 m 6 SUB DRILL 0.5 m 7 POWDER FACTOR (PF) 0.24 kg/bcm 8 DIAMETER DRILL BIT 7.88 inch D. Kebutuhan Handak dan Perlengkapan AMM site BCP :
No. KEBUTUHAN HANDAK & PERLENGKAPAN NILAI SATUAN
1 HANDAK HOLE PRODUKSI 646,020 kg 2 HANDAK HOLE TRIM 8,383 kg 3 ELDETO/LIL 14 pcs 4 IHD 500 ms 12 meter 4,878 pcs 5 SFD 17 ms 12 meter - pcs 6 SFD 25 ms 12 meter 1,707 pcs 7 SFD 42 ms 12 meter 1,707 pcs 8 SFD 67 ms 12 meter 488 pcs 9 SFD 175 ms 12 meter 976 pcs 10 BOOSTER (0.4 kg/Pcs) 4,878 pcs 11 BALLDECK - pcs 12 DRILL BIT 7 7/8 5 pcs
E. Plan Drilling AMM site BCP BP3 , CP4 & CP7 :
No. TARGET NILAI SATUAN
1 TARGET VOLUME OB REMOVAL 3,058,956 bcm 2 TARGET OB BLAST 2,691,751 bcm 3 KEDALAMAN 8.5 m 4 BURDEN 8 m 5 SPASI 9 m 6 DRILL METER HOLE PRODUKSI 37,385 m 7 DRILL METER HOLE TRIM 1,636 m 8 DRILL METER TOTAL 39,021 m 9 PRODUCTIVITY 65 m/jam 10 KEBUTUHAN DRILLING 2 unit 11 WH 669.60 jam 12 UA 56% / drilling