You are on page 1of 2

PLAN DRILLING DAN BLASTING JULI 2023

A. SPO Bulan Juli 2023 AMM site BCP :

SPO JULI 2023 Volume Satuan


Overburden Removal 3,058,956 bcm
-Top Soil 327,526 bcm
-Mud Original 0 bcm
-Overburden 2,731,430 bcm

B. Dasar Perhitungan AMM site BCP :

No. KETERANGAN NILAI SATUAN


1 TARGET VOLUME BLASTING SPO 2,731,430 bcm
2 INVENTORY SISA 180,000 bcm
3 REMAIN VOLUME 2,551,430 bcm
4 PERSIAPAN VOLUME BULAN SELANJUTNYA 140,321 bcm
5 TARGET VOLUME BLASTING 2,691,751 bcm
6 PERSENTASE TERHADAP OB 88 %

C. Plan Blasting AMM site BCP :

No. TARGET NILAI SATUAN


1 TARGET VOLUME OB REMOVAL 3,058,956 bcm
2 TARGET VOLUME BLASTING 2,691,751 bcm
3 TARGET VOLUME BLASTING/HARI 86,831 bcm
4 TARGET HOLE PRODUKSI 151 hole/day
5 TARGET PF 0.24 kg/bcm

No. GEOMETRI PELEDAKAN NILAI SATUAN


1 BURDEN 8 m
2 SPACING 9 m
3 STEMMING 4.3 m
4 POWDER CHARGE 3.7 m
5 KEDALAMAN LUBANG 8.5 m
6 SUB DRILL 0.5 m
7 POWDER FACTOR (PF) 0.24 kg/bcm
8 DIAMETER DRILL BIT 7.88 inch
D. Kebutuhan Handak dan Perlengkapan AMM site BCP :

No. KEBUTUHAN HANDAK & PERLENGKAPAN NILAI SATUAN


1 HANDAK HOLE PRODUKSI 646,020 kg
2 HANDAK HOLE TRIM 8,383 kg
3 ELDETO/LIL 14 pcs
4 IHD 500 ms 12 meter 4,878 pcs
5 SFD 17 ms 12 meter - pcs
6 SFD 25 ms 12 meter 1,707 pcs
7 SFD 42 ms 12 meter 1,707 pcs
8 SFD 67 ms 12 meter 488 pcs
9 SFD 175 ms 12 meter 976 pcs
10 BOOSTER (0.4 kg/Pcs) 4,878 pcs
11 BALLDECK - pcs
12 DRILL BIT 7 7/8 5 pcs

E. Plan Drilling AMM site BCP BP3 , CP4 & CP7 :

No. TARGET NILAI SATUAN


1 TARGET VOLUME OB REMOVAL 3,058,956 bcm
2 TARGET OB BLAST 2,691,751 bcm
3 KEDALAMAN 8.5 m
4 BURDEN 8 m
5 SPASI 9 m
6 DRILL METER HOLE PRODUKSI 37,385 m
7 DRILL METER HOLE TRIM 1,636 m
8 DRILL METER TOTAL 39,021 m
9 PRODUCTIVITY 65 m/jam
10 KEBUTUHAN DRILLING 2 unit
11 WH 669.60 jam
12 UA 56% / drilling

Bengalon, 30 Juni 2023

Dibuat Oleh: Diperiksa Oleh:

(________________) (_________________) (_________________) (_________________)


Drill Blast Engineer Mine Plan Engineer S.H. Engineering S.H. Operation