METHOD STATEMENT Revision No. 0


Page No. 1 of 3

METHOD STATEMENT FOR


Installation of LAD Partners Acknowledgement Wall Signage

Name of Company Axon Business System LLC

MS No. 06/03

Revision No. 00

DESCRIPTION TITLE SIGNATURE DATE

Prepared By Faisal Babu 06 Jul. 23

Reviewed By Anish P 06 Jul. 23

Approved By Vigil Powell 06 Jul. 23

This template is for guidance purposes only specifying the recommended contents of a method statement to be submitted to LAD as
part of the Permit to Work process. Titles and/or the extent of the content is dependent upon the scope of the works.
Document No PRO-TEC-HSE-1.0-0.0-T01

METHOD STATEMENT Revision No. 0


Page No. 2 of 3

1.0 PURPOSE

This method statement explains the sequential steps for removing the existing
Acknowledgment Wall Sign and installing the new sign at the same location.

2.0 SCOPE

This method statement provides the controlled sequence of Acknowledgment Wall Sign

REFERENCES

 Attached Artwork of the proposed sign

3.0 RESPONSIBILITIES

This job can be carried out by the operatives without much supervision. The supervisor
responsibilities are mainly to ensure that the signage are installed in the correct
sequence as per the key plan. The HSE officer’s role is to ensure that the area is
cleaned once the signs are installed.

4.0 RESOURCES & COMPETENCY

 Resources
o Signage Installers (Operatives)
o Ladder
o Measuring Tape
o Signage Components
o Cordless handheld Drill(Small) with adapter chuck - 24v cordless
o Combination spanners - 10, 13, 17, 19mm 12” adjustable up to 34mm
o Screwdrivers - flat, positive, Phillips (various sizes), terminal
o Spirit Level.
o PPE.
o Permit to Work
o Approved drawings
 Competency
o The operatives should be experienced in installation of signage.
o No certifications are applicable.

5.0 SEQUENCE OF ACTIVITIES


5.1 Locate the location of the existing signage.
5.2 Remove the existing signage panel from the bracket.
5.3 Remove existing bracket.

This template is for guidance purposes only specifying the recommended contents of a method statement to be submitted to LAD as
part of the Permit to Work process. Titles and/or the extent of the content is dependent upon the scope of the works.
Document No PRO-TEC-HSE-1.0-0.0-T01

METHOD STATEMENT Revision No. 0


Page No. 3 of 3

5.4 Locate and confirm that the new will be of exactly same dimensions as of
the removed signage.
5.5 Align the bracket and drill holes on to walls for installation of the bracket.
5.6 Install the brackets using appropriate screws, check for alignment.
5.7 Install the signage panel onto the brackets using concealed screws on
the side.
5.8 Check for alignment and quality of application.
6.0 LIST OF SIGNIFICANT HAZARDS

No Significant Hazard applicable – The maximum height of installation will be 2.2


meters and only portable small battery operated drill machines will be used.

7.0 LIST OF TOOLS & EQUIPMENT


7.1 Signage Installers (Operatives)
7.2 Ladder
7.3 Measuring Tape
7.4 Signage Components
7.5 Cordless handheld Drill(Small) with adapter chuck - 24v cordless
7.6 Combination spanners - 10, 13, 17, 19mm 12” adjustable up to 34mm
7.7 Screwdrivers - flat, positive, Phillips (various sizes), terminal
7.8 Spirit Level.
8.0 EMERGENCY PROCEDURES
8.1 Not Applicable

.ATTACHMENTS

A) Risk Assessment for the given Scope of Works


B) Workmen compensation policy and third party liability policy 
C) Approved Artwork

This template is for guidance purposes only specifying the recommended contents of a method statement to be submitted to LAD as
part of the Permit to Work process. Titles and/or the extent of the content is dependent upon the scope of the works.