CONSTRUCTION METHODOLOGY

PROJECT TITLE : INSTALLATION OF FM200 FIRE SUPPRESSION SYSTEM


CLIENT : NAKATOMI ELECTRO MECHANICAL SERVICES
ACTIVITY DESCRIPTION : SUPPLY AND INSTALLATION OF FM200 FIRE SUPPRESSION SYSTEM

I. GENERAL REQUIREMENTS
1. Submit all requirements needed to the project for approval.

II. SCOPE OF WORKS


FABRICATION & INSTALLATION OF FM200 FIRE SUPPRESSION SYSTEM

1. PREPARATION WORKS
1.1 Prepare and lay-out works

2. MOBILIZATION / DELIVERY
2.1 Check and inspect needed tools, equipment, and materials properly.
2.2 Inspect area where work will take place
2.3 Secure work permits (Hot work, hygiene, electrical-mechanical, etc.)

3. LAY-OUT OF PIPES AND SUPPORTS


3.1 Prepare needed tools and equipment
3.2 Ladder preparation
3.3 Ascending / descending at the ladder
3.4 Measurement of pipes and supports

4. FABRICATION WORKS
4.1 Fabrication of support, brackets and cylinder frame.
a. Cutting of angle bar
b. Assembling of support, brackets and cylinder frame
c. Welding and jointing of support, bracket and cylinder frame
d. Grinding of sharp edges of support, bracket and cylinder frame
4.2 Fabrication of pipes
a. Cutting of pipes
b. Threading of pipes

CONSTRUCTION METHODOLOGY

5. INSTALLATION WORKS A
5.1 Installation of supports, pipes & cylinder frame
a. Prepare tools, equipment and materials needed
b. Hauling of tools, equipment and materials to job site
c. Ladder preparation

d. Ascending / descending at the ladder


e. Drilling works
f. Install support, pipes and cylinder frame

5.2 Installation of Control panel, smoke detector, MPS, abort, Bell and Horn / Strobe
a. Prepare tools, equipment and materials needed
b. Hauling of tools, equipment and materials to job site
c. Ladder preparation
d. Ascending / descending at the ladder
e. Drilling works
f. Install control panel and field devices

5.3 Wiring and Termination of Control panel and field devices.


a. Cable pulling
b. Termination of control panel and field devices

6. INSTALLATION WORKS B (TO BE PERFORM ON PLANT SHUTDOWN)


6.1 Installation of supports and pipes
a. Prepare tools, equipment and materials needed
b. Hauling of tools, equipment and materials to job site
c. Ladder preparation
d. Ascending / descending at the ladder
e. Drilling works
f. Install support and pipes

6.2 Installation of Control panel, HSSD Sampling points


a. Prepare tools, equipment and materials needed
b. Hauling of tools, equipment and materials to job site
c. Ladder preparation
d. Ascending / descending at the ladder
e. Drilling works
f. Install control panel and HSSD sampling points

6.3 Wiring and Termination of Control panel.


a. Cable pulling
b. Termination of control panel

7. PAINTING WORKS
7.1 Painting of pipes, supports and cylinder frame

8. HOUSEKEEPING
8.1 Clean the area before/during/after the activity
8.2 Segregate waste materials per activity

9. DEMOBILIZATION
8.1 Back loading of tools and equipment for pull out, lifting and loading.

Prepared by:

Jaypee Ramos
Project Engineer