Professional Documents
Culture Documents
Mobile Substations
Incorporating HV GIS
WG B3.41
Members
Copyright © 2023
“All rights to this Technical Brochure are retained by CIGRE. It is strictly prohibited to reproduce or provide this publication in any
form or by any means to any third party. Only CIGRE Collective Members companies are allowed to store their copy on their
internal intranet or other company network provided access is restricted to their own employees. No part of this publication may
be reproduced or utilized without permission from CIGRE”.
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any responsibility, as to the
accuracy or exhaustiveness of the information. All implied warranties and conditions are excluded to the maximum extent permitted
by law”.
WG XX.XXpany network provided access is restricted to their own employees. No part of this publication may be
reproduced or utilized without permission from CIGRE”.
Disclaimer notice
ISBN : 978-2-85873-612-6
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any
responsibility, as to the accuracy or exhaustiveness of the information. All implied warranties and
TB 907 - Mobile substations incorporating HV GIS
Executive Summary
In recent years several utilities have reported on the use of ‘mobile’ substations employing a high level
of off-site construction (e.g. B3-102, 2012 [B1]). A number of specific objectives have been described,
such as the ability to quickly substitute a failed transformer in an emergency; however, the underlying
aim is the ability to provide new, extended or replacement substation facilities either at short notice
and/or with a reduced site construction period compared with traditional solutions. There is a growing
interest in such ‘build off-site’ solutions as transmission and distribution owners come under pressure
to respond rapidly to changing user demands. The ability to respond to these demands is one element
in delivering smarter grids for the 21st Century.
Mobile substations generally, although not exclusively, utilise GIS technology with many designs
based on compact switchgear assemblies with the addition of integrated protection and control
facilities. Thus, in addition to individual standards covering the design and testing of the functional
components of the substation, the following existing standards are partly relevant to mobile
substations:
IEC 62271 High-voltage switchgear and controlgear - Part 202: High voltage/low voltage
prefabricated substation [B2]
IEC 62271 High-voltage switchgear and controlgear - Part 205: Compact switchgear
assemblies for rated voltages above 52 kV [B3]
These standards, however, do not necessarily consider the specific requirements for design,
construction and testing of mobile substations and it was identified that recommendations were
required on this issue.
In some circumstances, depending on the application, it may not be appropriate for mobile substations
to fully comply with conventional standards regarding, for example, foundations, environmental
conditions or testing requirements. This Technical Brochure aims to give recommendations on how to
consider these topics.
A number of developments over recent decades have enabled the growth of mobile substation
technology; for example the continuous size reduction seen in GIS equipment and also the evolution
of IEC 61850 [7] and digital communications which has considerably reduced the size and weight of
Protection & Control equipment.
The early adopters of mobile substation technology have now gained valuable experience regarding
the design, testing, implementation and use of mobile substations and CIGRE Study Committee B3
decided that it would be valuable to capture this experience. Working Group B3.41 was established to
undertake this task and this Technical Brochure presents the conclusions of the work.
The Technical Brochure discusses the range of mobile substation applications, which extend from
those intended for rapid deployment in an emergency through re-locatable designs to prefabricated or
‘build off-site’ solutions. Three types of mobile substation are defined:
Type A mobile substation: “Short Term Emergency type unit”
Type B mobile substation: “Intermediate type unit”
Type C mobile substation: “Semi-stationary type unit”
The key benefits of each type of mobile substation are discussed and a number of case studies are
presented on recent projects from around the world.
Working Group B3.41 has reviewed existing IEC standards for their applicability to mobile substations,
with a particular focus on the IEC 62271 Series, which governs the performance and testing of
substations, and on IEC 61936 [B6], which governs the design of electrical power installations. The
working group has concluded that no changes are required to the standards as there is already an
allowance for reduced site testing of pre-assembled substations and the standards are considered
adequate. There are a number of examples where this philosophy of reduced on-site testing has
already been applied for many years very successfully, for example in the off-shore wind industry. A
representative example of how the off-shore wind industry has benefited from mobile pre-assembled
substations is shown in Appendix P. It is worth noting that there have been some isolated cases
identified through the work of this Working Group where user experience has been less positive,
leading to users returning to requirements for full IEC testing. More details can be seen in Section 7
(User Experience). Opinion on the required amount of testing across users is not consistent and
therefore it is concluded that it would not be possible to develop a new standard that adequately
3
TB 907 - Mobile substations incorporating HV GIS
supports all users. This Technical Brochure therefore provides guidance on how the standards should
be read and what should be considered in their implementation, but allows flexibility for the user.
The Working Group has made recommendations for how to consider the design, construction and
testing of mobile substations and how the approach should vary depending on the specific application.
Further topics such as transport, storage, dis-assembly, relocation and the ability to cater for differing
connection arrangements are considered as well.
It is important to note that mobile substation installations and the level of acceptable risk vary widely
between individual users and their specific applications. The Working Group therefore does not
recommend a one size fits all approach, and instead that each user should, in accordance with the
guidance given in this Technical Brochure, carefully consider the particular application and their
position on risk. Providing that the guidance is followed, Working Group B3.41 considers that mobile
substations are able to provide a flexible and cost-effective solution to current and future electricity
network requirements.
4
TB 907 - Mobile substations incorporating HV GIS
Contents
1. Introduction.............................................................................................................. 10
1.1 Scope of Working Group ........................................................................................................................ 10
1.2 What is a mobile substation? ................................................................................................................. 10
1.3 Types of mobile substations .................................................................................................................. 11
1.3.1 Type A mobile substation: “short term emergency type unit” ............................................................ 11
1.3.2 Type B mobile substation: “intermediate type unit” ........................................................................... 12
1.3.3 Type C mobile substations: “semi-stationary type unit”..................................................................... 13
1.3.4 Summary of types of mobile substation ............................................................................................. 14
1.4 Development of technologies to enable wider use of mobile substations ......................................... 14
1.4.1 IEC 61850 .......................................................................................................................................... 14
1.4.2 Compact gas-insulated switchgear (GIS)........................................................................................... 14
1.5 Drivers and benefits for deployment of mobile substations ............................................................... 15
1.5.1 Emergency replacement of failed equipment ..................................................................................... 15
1.5.2 Duplicating substation functionality to facilitate outages .................................................................... 15
1.5.3 Requirement for temporary additional capacity .................................................................................. 16
1.5.4 Early grid connections........................................................................................................................ 16
1.5.5 Shorten site works (Manage site access restrictions/reduce project lead time) ................................. 16
1.5.6 Advantage in case local installation/commissioning resources are not available ............................... 17
1.5.7 Economic advantages of mobile substations ..................................................................................... 18
1.5.8 Summary of drivers for deployment of mobile substations ................................................................. 18
5
TB 907 - Mobile substations incorporating HV GIS
7. Conclusion ............................................................................................................... 42
6
TB 907 - Mobile substations incorporating HV GIS
7
TB 907 - Mobile substations incorporating HV GIS
8
TB 907 - Mobile substations incorporating HV GIS
Tables
Table 1: Summary of Types of Mobile Substation ................................................................................................. 14
Table 2: Overview of Drivers in relation to Types of Mobile Substation ................................................................. 18
Table 3: Summary of drivers and related benefits of mobile substation including link to relevant case studies in
appendices ............................................................................................................................................................ 19
Table 4: Overview of on-site test requirements ..................................................................................................... 31
Table 5: Storage Risks and Mitigations ................................................................................................................. 33
Table 6: Summary of Recommended Maintenance of Mobile Substations ........................................................... 35
Table 7: Summary Table of Case Studies in Appendices ...................................................................................... 38
Table 8: Comparison of deployment times between mobile and conventional substations ................................. 101
9
TB 907 - Mobile substations incorporating HV GIS
1. Introduction
1.1 Scope of Working Group
CIGRE Working Group B3.41 was tasked with an investigation and assessment of mobile,
prefabricated and build-off-site substations for the following scope:
Drivers for deployment of mobile substations
Benefits of using mobile substations.
Experience of implementation and operation, including relevant case studies
Applicability of existing standards
Guidelines for specification and design
In recent years several utilities have reported on the use of ‘mobile’ substations employing a high level
of off-site construction (e.g. B3-102, 2012 [B1]). A number of specific objectives have been described,
such as the ability to quickly substitute a failed transformer in an emergency; however, the underlying
aim is the ability to provide new, extended or replacement substation facilities either at short notice
and/or with a reduced site construction period compared with traditional solutions. There is a growing
interest in such ‘build off-site’ solutions as transmission and distribution owners come under pressure
to respond rapidly to changing user demands. The ability to respond to these demands is one element
in delivering smarter grids for the 21st Century.
Mobile substations generally, although not exclusively, utilise GIS technology with many designs
based on compact switchgear assemblies with the addition of integrated protection and control
facilities. Thus, in addition to individual standards covering the design and testing of the functional
components of the substation, the following existing standards are partly relevant to mobile
substations:
IEC 62271 High-voltage switchgear and controlgear - Part 202: High voltage/low voltage
prefabricated substation [B2]
IEC 62271 High-voltage switchgear and controlgear - Part 205: Compact switchgear
assemblies for rated voltages above 52 kV Erreur ! Source du renvoi introuvable.
These standards, however, do not necessarily consider the specific requirements for design,
construction and testing of mobile substations and it was identified that recommendations were
required on this issue.
In some circumstances, depending on the application, it may not be appropriate for mobile substations
to fully comply with conventional standards regarding, for example, foundations, environmental
conditions or testing requirements. This Technical Brochure aims to give recommendations on how to
consider these topics.
A number of developments over recent decades have enabled the growth of mobile substation
technology; for example the continuous size reduction seen in GIS equipment and also the evolution
of IEC 61850 [B7] and digital communications which has considerably reduced the size and weight of
Protection & Control equipment.
The early adopters of mobile substation technology have now gained valuable experience regarding
the design, testing, implementation and use of mobile substations and CIGRE Study Committee B3
decided that it would be valuable to capture this experience. Working Group B3.41 was established to
undertake this task and this Technical Brochure presents the conclusions of the work.
The main focus of this Technical Brochure is on the incorporation of GIS technology into mobile
substations. The WG does not aim to give guidance on specific design and testing requirements for
other types of equipment such as transformers or Protection & Control (P&C).
10
TB 907 - Mobile substations incorporating HV GIS
11
TB 907 - Mobile substations incorporating HV GIS
12
TB 907 - Mobile substations incorporating HV GIS
13
TB 907 - Mobile substations incorporating HV GIS
14
TB 907 - Mobile substations incorporating HV GIS
15
TB 907 - Mobile substations incorporating HV GIS
16
TB 907 - Mobile substations incorporating HV GIS
1
It is unlikely that Type A installations mounted on road trailers will practically achieve a 50 year life, however the authors are
aware of Type B installations that are expected to do so.
17
TB 907 - Mobile substations incorporating HV GIS
Key:
Very likly to be suitable/ Possible Solution Unlikely to be suitable
first choice solution
Table 3 below shows an overview of the drivers presented in Sections 1.5.1 to 0, highlighting key
benefits and characteristics and linking to the real examples in the Case Study section at the end of
18
TB 907 - Mobile substations incorporating HV GIS
this Technical Brochure. Where the benefit is considered as a secondary benefits in the respective
case study the link is shown in brackets: e.g. [Appendix X].
Table 3: Summary of drivers and related benefits of mobile substation including link to relevant case
studies in appendices
19
TB 907 - Mobile substations incorporating HV GIS
20
TB 907 - Mobile substations incorporating HV GIS
deployment, since arrangements must be made for reducing gas pressure prior to movement by public
road and restoring the gas to normal operating pressure at the deployment site.
Where the transport vehicle forms an integral part of the substation (as is generally the case with Type
A Units) then consideration must be given to local regulations relating to design and the periodic
inspection and testing of road vehicles.
21
TB 907 - Mobile substations incorporating HV GIS
special packing, such as temporary bracing, for transport. The use of shock recorders during
transport is recommended as these can be used to confirm that design loading conditions have not
been exceeded. Where special packing is required for transport then clear instructions should be
provided in the operating manual for the mobile substation and any temporary bracing or fixings
should be included in the scope of supply. The operating manual should also identify the
recommended position for installation of shock recorders during transport and the acceptable limits on
these loads.
It is important that the Purchaser of a mobile substation clearly identifies to the Supplier the transport
conditions that the substation may experience. In some cases, where the area of deployment has a
well-developed road infrastructure, the transport loads may not be difficult to accommodate. In other
cases, it may be necessary to move a mobile substation long distances over poorly
constructed/maintained roads, thus imposing much higher loads. If the requirements can be defined,
the designer can take them into account when preparing the structural design of the substation and
selecting components.
It is recognised that there are a number of test procedures that could be used to ensure that a mobile
substation is designed to withstand transport loads:
The vehicle manufacturing industry uses a variety of test tracks and ‘proving grounds’ to test
road vehicles under conditions that allow assessment of durability under extreme conditions.
In some cases mobile substations have been tested using these facilities, which has allowed
vulnerabilities to be identified and designs modified.
Such testing has the disadvantage that it is not possible to accurately measure and quantify
the test conditions, therefore it is impossible to define clear acceptance criteria and cannot be
used as a ‘type test’. Nevertheless, this can be considered a useful tool for engineering
development of mobile substations.
It is recommended that cameras / sensors are fitted to the mobile substation during testing so
that the dynamic behaviours of the equipment can be observed and subsequently analysed.
Some of the vibrational loads experienced by mobile substations during transport can be
considered as having similarities to seismic loadings. Whilst the Working Group has not
identified any cases where this has been used as an acceptance criteria, it is noted that IEC
62271-207 [B5] defines test criteria for GIS that is to be applied in environments where there
is a risk of seismic activity.
Whilst the Working Group has seen no requirement to make any recommendations in this
regard, the objectives of seismic testing (which is to ensure that electrical equipment should
be able to survive a severe seismic event suffering no or only negligible structural damages
and without any effect on its electrical functionality) are clearly closely aligned with the
requirements for a mobile substation.
22
TB 907 - Mobile substations incorporating HV GIS
Where safe operational access cannot be assured, this should be clearly identified in the substation
operating instructions and measures should be taken to prevent access to danger areas, for example
by locking access doors or through the use of temporary barriers to restrict access.
2.3.2 Oil containment
Where a mobile substation includes a transformer, the risk of oil leakage must be considered and,
where necessary, measures taken to mitigate the possible environmental impact.
In some cases local regulations may require the provision of oil containment measures, even where
the deployment is short-term.
For Type C installations it would generally be appropriate to provide permanent oil containment
facilities (bunds, catch-pits etc.), however for Type A/B mobile substations a temporary bund may be
more appropriate and would allow for rapid deployment by minimising the requirement for permanent
civil works.
2.3.3 Fire protection
Where transformers are installed in close proximity to critical substation facilities then the risk of fire
must be considered. Since the installation of fire barriers or fire suppression systems can probably not
be justified for short-term deployments, the preferred option would be to allow sufficient spacing from
vulnerable equipment where this is possible.
If fire risk cannot be managed by spacing, it may be possible to accept the risk providing the
deployment is of relatively short duration.
2.3.4 Internal Arc Performance
Consideration should be given to risks related to internal arc failures of the GIS switchgear and
consequemt operation of pressure relief devices. Where necessary, arrangements should be made to
vent the mobile substation to atmosphere, whilst ensuring that the vents are arranged so as to
mimimise the risk to workers.
2.3.5 Earthing
The mobile substation should be designed such that all exposed conductive parts are equipotentially
bonded and that appropriate paths are provided to safely conduct fault currents. Designated points
should be provided for connecting the mobile substation to an external earth electrode system.
If the mobile substation is placed in an existing substation, an interconnection with the existing earth
grid should be provided. The interconnection arrangements should be dimensioned to carry the
maximum fault point current and should preferably provide a minimum of two independent current
paths.
If the mobile substation is placed close to an existing substation, then a new earthing grid should be
provided, as necessary, to achieve permissible touch/step potentials at the deployment site and this
should be connected to the existing substation earth electrode system. It should be noted that the
connection of both grids can be expected to reduce the total earthing resistance (and thus the
maximum rise of potential under fault conditions), but may extend the area around the substation that
is affected by that rise of potential.
If the mobile substation is not near an existing earthing grid, then methods of providing safe step and
touch voltages for operating personnel must be considered.
A copper loop around the mobile substation at the soil surface fixed by earth rods can be effective, but
in some cases a portable ground mat installed on the soil surface of the areas where personnel need
to access may be necessary.
2.3.6 Labelling
Identification and labelling of equipment is an essential requirement to avoid operating errors and
accidents. All important parts of a substation should be clearly, legibly and durably labelled to allow
identification of equipment and safety warnings, for example warning notices, safety instruction notices
and informative notices shall be provided at suitable points in the installation.
When a mobile substation is relocated, it is critical that any labelling which identifies the designation of
the equipment within the network is changed to suit the new deployment. It may be appropriate to
provide a mobile installation with a unique designation that is independent of the deployment site to
reduce the requirement to make changes to labelling.
23
TB 907 - Mobile substations incorporating HV GIS
2.3.7 Fencing
It is generally required that all electric supply substations are provided with fences, screens, partitions,
or walls to form an enclosure to reduce the possibility of entrance of unauthorized persons or
interference with equipment inside.
In some circumstances local regulations might allow waiver of certain rules for emergency or
temporary installations.
2.4 Deployment
Detailed planning of the installation can be essential to the successful deployment of a mobile
substation. Different considerations apply to emergency or short-term installations (Type A) and
longer-term applications (Type B / Type C).
2.4.1 Type A
Although Type A substations are designed for rapid deployment, there are benefits in planning their
installation. This can either be through a fast-track design procedure where an emergency
deployment is unforeseen and must be implemented at short notice, or mobile substation sites can be
selected for suitability prior to emergency situations (or a planned temporary deployment) to facilitate
proper assessment through normal procedures.
Some of the benefits of advanced planning are as follows:
To ensure that the required materials, tools, construction equipment and workers are identified
before starting work and can thus be made available at an appropriate point in the deployment
programme. This allows efficient use of resources and will assist in minimising delays waiting
for critical resources to be mobilised.
To allow work activities to be reviewed to ensure that risks (including health and safety risks)
are identified and, where possible, eliminated. Where elimination is not reasonably
practicable then appropriate mitigation measures can be identified and implemented.
Checks, inspections and tests can be built into the deployment programme, allowing errors to
be corrected before they can have a significant impact.
To avoid design errors. These can often occur as a result of design decisions being
‘improvised’ on site without check or review.
To ensure that any organisations or individuals impacted by the works or the completed
installation are identified and consulted.
The site for a ‘Type A’ mobile substation will generally be selected on the basis of proximity to existing
infrastructure, such as transmission and distribution lines. Selection should also consider the
availability of adequate space considering the physical size of the equipment, the required electrical
clearances and the availability of suitable access for both the substation transportable assemblies and
any related equipment, such as oil tankers, cranes and service or test equipment.
Type A substations generally do not require foundations, however a level of site preparation is
required.
2.4.2 Type B / Type C
For Type B & C installations it is expected that site selection and preparation will follow local
procedures for conventional substations. This is in recognition of the expectation that this equipment
will remain in the same location for a significant part of its operating life and operation/maintenance
will be undertaken in accordance with normal practice. (Note: for Type B mobile substations, some
maintenance may be carried out at an intermediate storage location).
The foundation requirements for a pre-assembled substation are likely to be different from those of a
more conventional substation, with slab foundations or prefabricated/temporary blocks replacing
distributed supports for individual plant items. If ground conditions are poor (inadequate bearing
pressure, such as marsh/swamp where piling is required) then the cost estimates should be adjusted
to reflect this.
If the transportable units are large then consideration may have to be given to the available site
access and, in particular, to any requirements to upgrade the off-site access infrastructure. This will
increase costs and should be included as part of the economic evaluation during site selection.
24
TB 907 - Mobile substations incorporating HV GIS
During the site selection process consideration should be given to any requirement for final assembly
and/or testing of the mobile substation before final deployment to site and it must be ensured that a
suitable area is available and accessible.
2.4.3 All installations (type A / B / C)
A deployment within an existing substation will often be favoured and can be planned based on a
review of the existing substation drawings, supported by limited field investigations to confirm the
specific site conditions.
Where a deployment site lies outside an existing high voltage compound (i.e. a closed electrical
operating area) then more detailed investigations are likely to be required. These may include, but are
not limited to:
Topographical surveys
Environmental surveys
Drainage surveys
Laser surveys of existing assets
Ground Penetrating Radar (GPR) surveys to identify buried services
Intrusive Ground Investigations (trial pits/bore holes).
Soil resistivity testing (to inform earthing design)
Thermal resistivity testing (to inform buried cable system rating assessments)
Tests for soil contaminants.
Transport surveys.
The proposed access route for the mobile substation should be reviewed to ensure that physical
clearance requirements can be met and that any weight restrictions imposed by local codes or
infrastructure are satisfied. Any need for licenses, permits or other third party consents should be
identified.
Design considerations to accommodate safe installation of mobile equipment include:
Space for delivery and installation; taking into consideration the need to use lifting equipment
(such as mobile cranes or vehicle-mounted loader cranes) and the minimum clearances to
adjacent live equipment defined by local regulations or procedures.
Requirement for outages of operational equipment (for connection of the mobile substation
and proximity outages during delivery/installation).
Access space around the mobile substation to allow other planned work to take place; e.g.
replacement of failed equipment or construction works to extend an existing substation.
Means of isolation from existing HV/LV systems during installation of the mobile substation.
Installation of foundation to provide level location for mobile equipment.
Means to connect mobile equipment to ground grid.
Emergency escape requirements from containerised equipment rooms and fenced
compounds.
Where GIS equipment is located in confined spaces, consideration must be given to
arrangements for venting following the operation of a rupture disc. In general, if access to
containerised GIS is not restricted then arrangements should be made to reduce the risks of
harm.
25
TB 907 - Mobile substations incorporating HV GIS
FACTORIES SITE
Switchgear Delivery to
site
In Service
Transformer Substation
Protection &
Control
FAT SAT
26
TB 907 - Mobile substations incorporating HV GIS
monitoring during transport has not picked up any problems; then they are more able and likely to
choose to reduce the amount of testing.
FACTORIES ASSEMBLY
LOCATION
Delivery to
Switchgear assembly
location
Delivery
Mobile to site Mobile In Service
Transformer Substation Substation
(assembled) Monitoring? (installed)
Protection &
Control
FAT Testing? Testing?
27
TB 907 - Mobile substations incorporating HV GIS
Additionally the user’s confidence in the equipment will have an impact on the decision about the level
of testing to carry out. Where a user has previously deployed the mobile substation multiple times with
no issues, or where the transport is straightforward, for example a short distance on a smooth road
surface, then the user may decide that full site acceptance testing is not necessary.
A graphical representation of this balance between the amount of testing and the user’s confidence
level and risk appetite is depicted in Figure 15 below. Here risk is considered as the product of the
likelihood or probability of something happening, and of the impact or consequence of the event
happening. Risk appetite is then the level of risk that a user is willing to accept.
Reducing the number or complexity of site tests carried out will enable the user to reduce the cost and
time required for deployment of the solution. A user must decide on how confident they are in the
solution, for example based on previous experience, and on their level of risk appetite, for example if
the solution if going to be in service for a long period of time then they may have a lower apetite to
take on risk. Carrying out full site testing in accordance with existing IEC standards will serve a user
with a very low risk appetite and/or low confidence in the equipment. Carrying out no/minimum site
testing will better serve a user with a very high confidence level in the equipment and/or high risk
appetite. A graphical representation of this concept of the trade-off between risk appetite/confidence
level and the amount of site testing is illustrated below in Figure 16.
Increased level
of testing
No site
Full IEC
testing
testing
Reduced time/cost
28
TB 907 - Mobile substations incorporating HV GIS
There are a number of considerations that a user should take into account when making a decision on
their risk appetite and the amount of on-site testing required. The consequences or impact of varying
the amount of testing can be categorised as follows:
Safety: for example the proximity of the mobile substation to members of the public/personnel
when deployed, risk to personnel during testing (e.g. due to an adverse environment)
System: the impact of failure on the existing transmission/distribution system
Cost: impact of carrying out testing or of having a failure (including time and resource)
Reputation: impact of delaying deployment for testing as well of having in-service failure
Environment:, gas or oil leakages
The following factors may affect the likelihood or consequence, and thus risk, of a failure:
Operating voltage of equipment
Complexity of GIS
Whether bushings or GIS components need to be disassembled for transport
Road/transport conditions
Ability to monitor during transport, e.g. using shock indicators or shock recorders
Confidence in the design of the transportation solution (e.g type testing of vehicle)
Previous experience in deploying the same/similar mobile substations
Service history
Length of time that mobile substation will be in service
Installation environment
Note that this may not be an exhaustive list and a user should carefully consider their specific
application.
3.3.3 Design and testing of transport vehicles
Additional type testing of mobile substations and/or their transportation vehicles can give more
confidence in the equipment withstanding different road and transport conditions. Environmetal
conditions during transport can be specified by reference to IEC 60721-3-2 [B8], however the Working
Group did not identify any cases where this Standard had been used.
Some manufacturers carry out extensive road testing of hundreds or thousands of kilometres in order
to prove that the integrity of the mobile substation and transport vehicle will be maintained during
future relocations. In this case it is recommended that the type of road surface during testing should
be considered, for example gravel or pot-holed road surfaces may have more impact on equipment
than smooth tarmac.
An alternative option to road testing is to simulate the transport conditions in a laboratory environment
for example through seismic / shaker-table testing. The vehicle, with the mobile substation mounted
onto it, can be placed onto a platform that can be subjected to vibrations and shocks.
For larger applications it may be impractical to carry out physical testing, and computer modelling may
be considered instead.
3.3.4 Monitoring during transport
It is recommended that monitoring during transport is considered, especially where it is planned to
reduce the amount of site testing to be carried out. Monitoring allows a user to check that nothing
adverse has occurred during the transportation, such as a collision or unexpected vibration from road
surface conditions. A number of options are available to monitor equipment during transport including
the use of vibration monitoring, shock recorders or video equipment.
3.3.5 Recommendations for on-site testing
Many of the drivers for deployment of mobile substations rely on realising the benefit of reduced
deployment and commissioning times, reduced requirement for skilled labour or reduced costs such
as from hiring expensive test equipment. In order to achieve these benefits a user should consider the
reduction of on-site testing. A risk-based approach should be taken.
The IEC standards broadly specify the following tests to be carried out on GIS equipment:
Dielectric tests on auxiliary circuits
Measurement of the resistance of the main circuit
29
TB 907 - Mobile substations incorporating HV GIS
Back-
10kV DC HV Test at energise
Resistance
Gas insulation System through VT Full HV
No testing Test of Main
Tightness resistance Voltage Testing
Circuits at/above
test (soak test)
rated voltage
Figure 17: Risk Appetite and On-Site Testing Options (Note: Tests are cumulative, Left to Right)
An HV test set may take many weeks to arrive on site and in some situations the benefits of deploying
the mobile substation more quickly will outweigh the risks of not carrying out HV testing. A good
example of this would be in an emergency situation (Type A) following a failure and or loss of power,
where restoration of the system is of paramount importance. HV testing may also be difficult or
prohibitively expensive due to space or skilled resource constraints at the final location, for example
on an offshore platform or in an area which is sparsely populated and has no local labour supply.
Where the deployment of the mobile substation is planned, such as to support maintenance or
network replacement, then a user may consider carrying out more tests to mitigate any risk of failure.
30
TB 907 - Mobile substations incorporating HV GIS
Where a mobile substation workshop (intermediate site) is used then consideration should be made of
carrying out as much testing as possible here, for example where there are multiple modules these
can be brought together and functional tests carried out before arrival at the final site. If HV testing will
not be carried out at the final site, then consideration could be made to also do these tests at the
mobile substation workshop.
The use of a power VT, which can provide a high voltage source for testing, can provide a good
compromise between risk mitigation and cost and should be considered in the user’s specification.
Currently this option is known to be available at least up until 245 kV.
It is anticipated that, as a user or manufacturer gains experience in deploying a particular mobile
substation solution multiple times without any test failures, then they will gain confidence and be able
to further reduce the number of tests carried out.
The following sections give further guidance and examples specific to the type of mobile substation to
be deployed.
3.3.5.1 Type A:
Emergency – Deployment usually unplanned. As a HV test set can take many weeks to
arrive on site, it is common that no testing is carried out on-site. Fast response is the driver.
3.3.5.2 Type B:
Planned deployment, but HV test expensive, and time to commission important in some
cases.
The use of the HV test will therefore depend on user’s risk appetite balanced against
time/cost/resource – see examples of different approaches in case studies in the
appendices.
3.3.5.3 Type C:
Access difficult, so may not be possible to perform test on site e.g. windfarms, war zones,
etc.
Skilled resource constraints:
o offshore platform
o area that is sparsely populated and has no local labour supply available (for example
Middle East/Africa)
Wind farm platforms/off-shore substations – often utilise an assembly location close to or at
the port
31
TB 907 - Mobile substations incorporating HV GIS
32
TB 907 - Mobile substations incorporating HV GIS
4. Asset management
This section defines general principles/good practice in regards to asset management of a mobile
substation. In determining an asset management policy, it is recommended that Users should
additionally pay specific attention to manufacturers recommendations and any conditions of the
warranty.
4.1 Storage
Long time periods of storage are often part of mobile substations’ life cycle; and operational availability
at any time is the purpose of these substations.
Therefore, particular care should be taken with the equipment during these periods of time in order to
keep it operational, and to avoid any bad surprise when the mobile substation has to be mobilised.
Storage conditions should be properly defined and implemented to avoid:
- Any risk of accident during storage (risk to employees)
- Any risk of theft and act of vandalism
- Excessive exposure to aggressive environmental agents
- Malfunction or accelerated ageing of the electrical equipment
Some risks which could occur during these storage periods are listed below in Table 5 with some
relevant mitigation measures.
Table 5: Storage Risks and Mitigations
# Risk Mitigation
1 Condensation and potential corrosion The mobile substation shall be stored preferably in an
in the containers airy place, with limited short-term temperature
variations.
2 Condensation and corrosion in the Anti-condensation heaters should be energised to
cabinets (leading to the loss of control ensure a positive air temperature difference between
and protection functions) the inside and the outside of the cabinets.
33
TB 907 - Mobile substations incorporating HV GIS
# Risk Mitigation
6 Ageing of tyres Protection of tyres against solar radiation is
recommended in the case of long storage periods (for
example with a tarpaulin).
34
TB 907 - Mobile substations incorporating HV GIS
4.2 Maintenance
There are two different requirements for a mobile substation to be maintained.
- Maintenance according to the existing equipment maintenance plan.
- Maintenance due to the specific circumstances the mobile substation is used for.
4.2.1 Maintenance according to the existing equipment maintenance plan
Here the maintenance requirements stay unchanged, e.g. the inspection of circuit-breakers,
disconnectors and earthing switches.
4.2.2 Maintenance due to the specific circumstances the mobile substation is used
for
Aspects such as operating area of the mobile substation, road conditions, and more transport
influences may especially mechanically stress a mobile substation more than a regular GIS
substation. In order to have the mobile substation in proper condition for the next use it is
recommended to inspect the mobile substation when it is returned from use in a substation.
A final inspection should be applied at the new location when transport and installation works are
completed.
It is recommended that user and OEM agree on the maintenance content that may be related to the
specific use of the mobile substation. This would also allow alignment in relation to the warranty
position.
The following table gives a summary of recommended maintenance at different periods during the life
of a mobile substation.
35
TB 907 - Mobile substations incorporating HV GIS
the expectation is that the life of Type A substations will be lower than that of conventionally installed
substation equipment.
Type B substations may be subject to a range of different operating environments. In some cases
relocation will be undertaken relatively frequently, in other cases relocation may only be required in the
event that the network requirements change. In the latter case it is anticipated that the substation will
be subject to a conventional maintenance regime and that the asset life will be similar to that of a
conventional substation. Where multiple relocations are required, then a shorter life can be expected.
Considering Type C substations, these are generally constructed off site for logistical reasons and
once deployed are expected to be subject to a similar operating regime to a conventional installation,
therefore they will achieve a similar life.
36
TB 907 - Mobile substations incorporating HV GIS
All loose parts should be suitably packed for transport/storage. The standard of packing
required will depend on the vulnerability of the parts and the environment which they may
experience
Special care must be taken when transporting porcelain-clad bushings as they are vulnerable
to mechanical damage. Special packing may be required and consideration could be given to
the use of shock indicators to indicate improper handling
Preparation for transport may include reduction of gas pressures to comply with local
regulations and/or draining of fluids
Storage
If the mobile substation is not to be immediately redeployed, then it will need to be put into storage.
For storage recommendation see Section 4.1.
Redeployment
Before mobilising the substation it is essential to confirm that suitable access is available. In
particular, the following should be considered:
o Survey to determine status of access roads (width, surfacing, permitted axle loading,
swept path limitations).
o Height limit imposed by any overbridges
o Bridge weight limitations
Confirm that there is adequate working area at site for erection of the mobile substation.
Schedule deployment activities. Ensure that adequate resources are available and that
special equipment (e.g. cranes, access platforms) is scheduled
Where damage to internally pressurised parts is suspected (e.g. due to operation of a shock
indicator) then suitable precautions should be taken before refilling with insulating gas
The supplier’s instructions for unpacking and assembly should be followed. If no supplier
instructions are provided, then it is recommended that the user should develop a step-by-step
procedure to define the method of deployment.
Any parts fitted for protection of the substation in transit/storage (covers, support struts, etc.)
should be removed and carefully stored for future use
During reassembly, loose parts should be checked against the equipment schedule. Any
parts not required for the specific deployment should be carefully stored. Replacements may
have to be sourced for any parts that are lost or damaged.
Consideration may have to be given to holding spares for loose parts that are vulnerable to
loss or damage
Once the equipment is in its final position, and all major components have been fitted then gas
pressures (where they have been reduced for transport) must be restored and fluid levels
checked and replenished as required
The equipment can then be functionally checked prior to recommissioning
37
TB 907 - Mobile substations incorporating HV GIS
380 kV
Air bushing connection
138 kV
Cable connection
110 kV
Air bushing connection
400/132 kV
Air bushing & cable connection
110 KV
Air bushing connection
123 kV
Cable connection
38
TB 907 - Mobile substations incorporating HV GIS
220 kV
Cable connection
70 kV AC/3 kV DC
Cable connection
220 kV
Cable connection
63 kV
Cable connection
155/33 kV
Cable connection
77/6.9 kV
Cable connection
39
TB 907 - Mobile substations incorporating HV GIS
phenomena engendered by vibrations. Finally, the repetition of the routine tests, such as HV
tests and tightness tests leads to the validation of the design.
Dynamic mechanical calculation is another way to validate the design. A model of the
complete mobile substation is submitted to an acceleration spectrum reflecting road
conditions, it is then checked that the HV equipment of the mobile substation is not submitted
to excessive mechanical stress.
Lastly, a combination of road tests and dynamic mechanical calculations allows the designer to
enhance the mechanical models used in the dynamic calculation, and to improve the suitability of the
calculation for the validation of the design.
The experience shows that when these transport impacts are properly addressed, and provided that
the HV tests have been previously carried out at the manufacturer’s premises on the complete mobile
substation, HV tests at site can be avoided without affecting the confidence in the integrity of the
equipment.
5.2.2 Deployment
The key benefit offered by mobile substations is the commissioning lead time, which constitutes their
main use value. This short commissioning lead time relies on prerequisites which must be carefully
fulfilled, without which this benefit is lost.
First of all, and obviously, the mobile substation should be fully pretested at the manufacturer’s
premises. This includes above all the complete functional tests. Furthermore, when the substation is
made of several mobile modules to be connected at site, these functional tests should be carried out
with respect to site conditions, that is by connecting the modules to each other.
Instructions and conditions for site installation must be properly defined by the manufacturer and
scrupulously respected by the operator. The experience shows that neglect at this stage can have
consequences impacting the commissioning lead time substantially.
These instructions and conditions shall cover:
the installation layout,
the civil work specification,
the specification for the grounding connection, the description of the interfaces,
and last but not least the access conditions to the final position.
Finally and obviously, a fast deployment requires serviceable equipment. Therefore appropriate
storage conditions before deployment are essential. The manufacturer’s instructions must be fully
fulfilled by the operator, and the maintenance shall not be neglected.
5.2.3 Knowledge of use values by operators
The benefits of mobile substations are many and varied; some of them are not well understood by
operators. Many calls for tenders refer indeed to a conventional substation where a mobile substation
could be more appropriate.
If the usefulness of mobile substations for restoring operating conditions after a failure of a disaster is
well known, their benefits regarding the shortening of the lead time is less known: i.e. the shortening of
lead time of site activities, but also and in particular, the shortening of the lead time of a complete
project (from ordering to commissioning).
Other benefits worth remembering are the simplification of civil work, and the simplification of site
activities.
40
TB 907 - Mobile substations incorporating HV GIS
The applicability of IEC 61936 [B6] has also been considered and the basic design rules found to be
applicable.
No changes to standards needed as standards currently include flexibility for a user to make
decisions on the amount of testing required for pre-assembled substations.
Users should review the guidance in this Technical Brochure and make an informed decision
on what testing they require to be done based on their risk position.
In some circumstances, depending on the application, it may not be appropriate for mobile substations
to fully comply with conventional standards regarding, for example, foundations, environmental
conditions or testing requirements. This Technical Brochure aims to give recommendations on how to
consider these topics.
A number of developments over recent decades have enabled the growth of mobile substation
technology; for example the continuous size reduction seen in GIS equipment and also the evolution
of IEC 61850 [B7] and digital communications which has considerably reduced the size and weight of
protection & control equipment.
41
TB 907 - Mobile substations incorporating HV GIS
7. Conclusion
Mobile substations are becoming an established solution and international use is growing. The
technology is now considered proven.
The working group has identified many cases where mobile substations have been effectively
deployed to meet user requirements across a wide range of applications.
Various drivers and benefits have been reported, such as
- Emergency replacement of failed equipment
- Duplicating substation functionality to limit the impact of outages
- Providing temporary additional capacity
- Early grid connections
- Shortening site works
- Avoiding stranded assets
These scenarios can be confirmed by the numerous case studies described in this brochure spanning
the range from mobile substations used for emergencies, intermediate type units, and semi-stationary
type units. These case studies demonstrate mainly positive experiences for users, manufacturers, and
engineering companies.
Mobile substations are very adaptable to cover different requirements for different applications that
users may have. To benefit from this flexibility to use a mobile substation according to the specific
need in a required time frame, it is not recommended to target common solutions.
This flexibility is also related to the risks experienced when transporting, installing, and testing mobile
substations on site. This risk situation needs to be understood before energising the mobile
substation. An increased risk appetite can be acceptable in emergency situations where power must
be restored quickly and time for intensive on-site testing is not available. Previous deployments,
known road conditions, shock indicator readings will influence a certain confidence level that must be
considered for the risk evaluation.
Next to the risk evaluation it is important to determine the objective of the use of the mobile substation.
A clear understanding about the expected outcome operating the mobile substation will streamline
preparation and mobilisation aspects such as choosing the correct mobile substation type, transport
options, installation, safety, risks, and on-site testing considerations. Fencing, access, and related
safety items are taken into consideration when operating the mobile substation. A clear objective and
good planning will allow the maximum benefits of using a mobile substation to be obtained.
Existing technical standards are fit for purpose. There is no recommendation for adjusting or
upgrading these standards for the use of mobile substations.
42
TB 907 - Mobile substations incorporating HV GIS
43
TB 907 - Mobile substations incorporating HV GIS
B.4. Solution
The solution is a fully equipped bay based on standard GIS components which can be easily adapted
to the requested situations. The bay consists of a circuit-breaker fitted with a current transformer, and
on each side of the circuit breaker with a voltage transformer, a disconnector and two earthing
switches. This bay is installed in a 40 foot container of 3.5 m width. The terminations are removable
for transportation and must be installed on site before commissioning.
The control cabinet and all secondary equipment (e.g. protection relays) are installed in a separate 20
foot container of 2.9 m width.
The use of these containerised solutions, with secondary equipment ready for use, reduces the
installation works and time, which mainly consist of installing and grounding the containers, setting up
the bushings and connecting them to the HV grid conductors.
B.5. Execution
The main contractor for the container is the supplier of the GIS; construction, manufacturing and FAT
are within his scope of work.
The substations where the solution described above is intended to be used are in general designed in
order to allow connections on both sides of the busbar system. In the example below, the transformer
bay, highlighted with a red frame, is to be refurbished. To this end, the containerised solution is set-up
in the area highlighted in green.
44
TB 907 - Mobile substations incorporating HV GIS
Figure 18: Schematic visualisation of a typical AIS sub-station (red: OHL bays; blue: transformer bays;
orange: coupling bay)
Figure 19 shows the layout of a switchyard bay to be replaced. The necessary steps for the
replacement of this bay are sketched in the sequence from Figure 20 to Figure 23. In this example,
the connection of the temporary bay to the transformer is done using existing OHLs within the
substation. Depending on the local situation, this connection could be done with cables.
The advantage of the use of a containerised switch bay solution is the reduction of service
interruptions to a minimum of time. The transformer can stay online for almost the entire time and
service interruptions are only necessary when switching from the fixed installation to the temporary
one and back, after all work is finished.
45
TB 907 - Mobile substations incorporating HV GIS
Figure 20: Setup of the mobile and containerised solution (green) while the old bay stays in service.
Figure 21: Taking the old bay (red) out of service. The full functionality is taken over by the mobile
solution.
Figure 22: Disassembling and reconstruction of the new bay without further service interruptions
Figure 23: After renewal, the new bay goes back into service. No interruptions of service needed for
disassembling of the temporary solution
To ease the process of refurbishing/renewing a switchyard bay, the containerised solution consists of
the switchgear container and a local control container. The renewal often includes the secondary
control and protection systems, and having all necessary control and protection instruments
preinstalled in the local control container allows for a fast integration at site. As a consequence, the
whole protection and control equipment can be renewed at the same time.
B.6. Conclusion
The use of a self-contained and containerised bay is an effective solution to conduct refurbishment
works with a limited impact on the service continuity.
The full-featured bay allows for use as a coupling bay (voltage transformer before circuit breaker), as a
transformer bay and as a line bay for overhead line or cable. The symmetrical setup makes the mobile
switchgear quite versatile and allows for further connections using cables or overhead lines on both
sides as well.
46
TB 907 - Mobile substations incorporating HV GIS
C.4. Solution
A GIS bay with cable end box interface, including circuit-breaker, current transformer, voltage
transformer with test capability and partial discharge sensors. In addition a set of test
equipment was included to allow verification that no deterioration has occurred before each
use of the substation in a new location.
C.5. Execution
The project was executed with the assembly of GIS followed by tests at the GIS
manufacturer’s premises using a conventional test transformer followed by the use of its own
in-built voltage transformer together with theordered test equipment.
The trailer was designed and constructed in Portugal, and all equipment assembled together
in the EPC premises in Madrid (Spain)
Once completely assembled into the trailer, the GIS was tested again with its own voltage
transformer to verify that no damage has occurred during transportation and installation.
Function tests and measuring of protection system were also carried out at this stage.
Trailer was transported from Spain to US, where a GIS supervisor has been to site to perform
for the 3rd-4th time the power-frequency test using its own voltage transformer and the
oredered test equipment.
A second trailer was supplied with improved lessons learned from the first trailer, such as
design of height of the trailer and provision of a secondary LV box with direct access for
testing, without needing to access the voltage transformer low voltage box.
C.6. Conclusion
The customer has expressed satisfaction with the 2 mobile substations, which have been in
service and functioned satisfactorily.
47
TB 907 - Mobile substations incorporating HV GIS
Figure 24: Representatives from the EPC Team (Switzerland, USA and Spain) and the customer
48
TB 907 - Mobile substations incorporating HV GIS
49
TB 907 - Mobile substations incorporating HV GIS
50
TB 907 - Mobile substations incorporating HV GIS
D.4. Solution
The solution was made of a standard 110 kV GIS bay comprising the circuit breaker, a disconnector
and an earthing switch on both sides, the instrument transformers (CT / VT), the cable connection and
GIS-to-air bushings mounted inside a 20 foot ISO container.
51
TB 907 - Mobile substations incorporating HV GIS
D.5. Execution
The main contractor for the container was the supplier of the GIS: engineering, manufacturing and
FAT was within the scope of work.
Initially, the containerised solution was deployed in two different locations:
Two containers were used in a first location for two and a half years
Three other containers were used in another location for four years
Placing the container solution into service takes about 3 to 4 weeks, mainly due to the necessary full
integration into the protection and control system of the substation. After each relocation a standard
procedure to place a switchyard bay into service was followed. This included a high-voltage test
(minimum 24 hours at U0) and a SAT of the protection and control system.
The equipment is fully overhauled in a workshop before each relocation, allowing for a reduced high
voltage test at site.
The service experience has been very good. At the first location the container was used for the
connection of a cable to an AIS substation during retrofitting of the substation. At the second location it
was used as a compensation reactor switch with at least one switching operation per day.
In case of maintenance or failures, the usage of standard GIS is seen as a big advantage, as spare
parts are kept in stock for this type of equipment.
D.6. Conclusion
The mobile 110 kV GIS bay, mounted within a single standard container has proven to be a flexible
solution for planned retrofitting and maintenance. The easy relocation by standard means of
transportation and the standard procedure to put the bay into operation allow for a good integration
into the established processes.
52
TB 907 - Mobile substations incorporating HV GIS
Height
3.8m
Length 12m
width
2.5m
E.4. Solution
The mobile substation has been designed with two units, a “mobile transformer with GIS” and a
“mobile control house with distribution switchgear”. These can be connected together quickly and can
be operated without removing main components from the transport vehicles.
Additionally, the two units can be deployed independently. For replacement of a transformer, the
“mobile transformer with GIS” unit can be connected to existing 6.9 kV switchgear and existing
control/operating system.
A schematic diagram of the design solution adopted is illustrated in Figure 32.
53
TB 907 - Mobile substations incorporating HV GIS
E.5. Execution
To minimise the site activities:
The main components of the mobile substation units remain on the vehicles during
deployment.
Plug-in cables are used to provide HV and control connections between the two units.
By using VCBs (vacuum circuit-breakers) installed in the GIS directly connected to the
transformers, the mobile substation can be designed for operation at a SF 6 working pressure
of only 0.07 MPa (gauge pressure). This allows the substation to be transported under full
working pressure, avoiding the need to re-pressurise the equipment on site.
The high voltage test at site is omitted
To allow for transportation stresses:
When the mobile substations are moved, dynamic loads are exerted on equipment. Therefore,
these loads must be evaluated and consideration given to possible metallic fatigue.
For analysis of transportation loads, an evaluation of key parts is performed using finite element
analysis. A typical output of this analysis is shown in Erreur ! Source du renvoi introuvable.
54
TB 907 - Mobile substations incorporating HV GIS
E.6. Conclusion
This solution minimises the site works required to deploy a temporary substation.
Only the HV power cables and control cables have to be connected to deploy the temporary
substation.
The substation is easy to move because all equipment is mounted on the vehicles and no
special permissions are required.
This solution is becoming one of the standard mobile substation designs in Japan.
55
TB 907 - Mobile substations incorporating HV GIS
F.4. Solution
The 380 kV 500 MVA substations consist of six trailers and two interface material containers:
One 380 kV GIS trailer equipped with one circuit-breaker.
Three single-phase 380/132-115-110 kV/15 kV auto transformers trailers of 168 MVA each
representing together a total 500 MVA rating.
One 132 kV GIS trailer comprising four bays: one incoming transformer bay and three
outgoing cable line feeders.
One auxiliary power trailer equipped with auxiliary power transformer, battery, battery
chargers and AC & DC distribution boards.
The substation can be moved by road transportation with standard tractors, set up and connected to
the HV grid without any need for specialists from the manufacturer.
Once mobilised on site, the set-up time to become ready for commissioning can be as little as one
week.
The multiple-ratio auto transformers provide the flexibility to connect to the four voltage levels used in
the kingdom: 380, 132, 115 and 110 kV.
56
TB 907 - Mobile substations incorporating HV GIS
57
TB 907 - Mobile substations incorporating HV GIS
58
TB 907 - Mobile substations incorporating HV GIS
Availability despite long storage period is also an important consideration and therefore a connection
plug for supply of battery chargers is available for keeping battery banks in charge while being stored
in the warehouse.
Agility also means the ability to be transported easily across long distances, which calls for maximum
mobility.
Mobility
The trailers on which the equipment is installed are designed to be pulled by standard prime movers.
Dimensions and weights have been optimised to simplify transport on most of the kingdom’s roads.
502 MVA auto transformers had to be designed in three 186 MVA single-phase units in order to be
compatible with road-type trailers.
This challenge was made possible thanks to thorough design optimisation seeking maximum
compactness.
59
TB 907 - Mobile substations incorporating HV GIS
As the 380 kV / 502 MVA mobile substation is an exceptionally high rating configuration, reaching
dimensions compatible for road transportation was a technological challenge:
380 kV dielectric clearance are not compatible with standard road transportation limitations.
Rotating bushings on the GIS and power transformer side was the solution to reach a
compact transport configuration while minimising the amount of installation work on-site.
Power transformer oil conservators are flat shaped to reduce height as the transformer is
designed to be transported with all accessories installed.
Protection and control system dimensions were minimised thanks to the use of multi-function
protection relays.
60
TB 907 - Mobile substations incorporating HV GIS
Robustness
Environment resistance:
The operating environment is tough in the kingdom combining:
o Intense solar radiation
o High temperatures
o Dust and sand winds
o Salty atmosphere in areas close to the seashores
Substation trailers are therefore protected by high resistance paint, equipped with high-rating air-
conditioning systems, and reinforced tightness against dust.
Mechanical stress:
Trailers are subject to mechanical stress from road and ocean transportation: torsion and flexing
efforts coming from the road are partially absorbed by the trailer hydraulic shock absorber systems. A
fraction of these efforts can however be transferred to the equipment on the trailer platform. The main
risk is located on the gas insulated switchgear which is made of pressurised vessels filled with gastight
sealing.
F.5. Execution
The design of each GIS trailer was conducted in close cooperation with the GIS manufacturer and the
trailer supplier. This way of working allowed the engineering team of the EPC Contractor in charge of
the project to guarantee the reliability of the complete solution, and to make sure that the deflection
induced by the transport would never engender overstress on the GIS.
The GIS trailers (380 kV and 132 kV) were manufactured in a dedicated workshop in France where
complete HV tests were carried out after assembly. The auto transformer trailers were manufactured
in a adjoining yard of the shipping port. After completion of assembly, the trailers composing a
substation are brought together at the yard for final functional tests.
F.6. Conclusion
The company faced a triple challenge of maximum mobility, fast deployment and versatility to connect
to any of the four high-voltage sub-areas of the kingdom.
The challenge was met by the use of a mobile substation incorporating several optimisations of
primary and secondary equipment such as multiple-ratio single phase power transformers, rotating
380 kV air bushings, multiple-function relays, giving compactness, quick and autonomous deployment,
and compatibility with several grid voltage levels.
61
TB 907 - Mobile substations incorporating HV GIS
Figure 42: Failure in circuit-breaker on the line bay in a windfarm hub 110 kV substation
G.4. Solution
The mobile bay had been in use recently, connected to the system in another location, but it was now
available for this work. As such, the mobile bay was proposed as the most appropriate and cost
efficient solution for reconnection in place of the failed circuit breaker in the substation.
G.5. Execution
The mobile bay (which is trailer-mounted and has no transport restrictions) was transported by road
from its storage location to site, a distance of 250 km, and over a poorly surfaced mountain climb for
the last 5 km.
The faulty bay was disconnected and isolated from the system.
62
TB 907 - Mobile substations incorporating HV GIS
The site location was such that minimal ground work was required. There was ground available
outside the existingsub station and directly under the outgoing line. The substation fence was
extended to incorporate the mobile bay. As this mobilebay is GIS with air bushings, all connections are
by conductor to overhead lines.
The mobilebBay was located underneath the outgoing line. A temporary pole set was erected at the
opposite end of the substation and a temporary line strung across the substation. Connections were
made from this to the busbar and to the mobile bay. The line side of the mobile bay was connected to
the outgoing line.
The mobile bay has both 48 V and 24 v battery systems for control and signals and alarms, as well as
protection relays, CTs, VTs and surge arrestors.
The mobile bay was then positioned, the trailer waslevelled and set up in the following steps:
1. Poles moved from transport position to operation position and pinned.
2. Drives fitted for the circuit-breaker and disconnectors.
3. Circuit-breaker filled to pressure with SF6
4. Cables run from bay to control room
5. Control panel mounted in control room
63
TB 907 - Mobile substations incorporating HV GIS
The remote circuit-breaker was closed, energising as far as the open mobile bay circuit-
breaker, and so on until the procedure wascomplete.
G.6. Conclusion
This case shows the mobile bay to be a success and an ideal solution for such an emergency. Its
compact nature and ease of transport made it a flexible option. The short set-up time contributed to
considerable cost savings in penalties due to loss of access to the system. Further engagement with
wind farms and external customers would highlight this as an option for such emergencies and avoid
any undue delay in decision making by the customer for reconnection.
64
TB 907 - Mobile substations incorporating HV GIS
65
TB 907 - Mobile substations incorporating HV GIS
Preference was given to standard material from existing framework agreements and following
existing company standards in order to avoid delays in installation, in the case of emergency
use, due to a lack of knowledge by maintenance crews.
H.4. Solution
The custom solution designed by the manufacturer consisted of:
A 5 bay 123kV GIS mobile substation fitted in a 40 foot container (12 m x 2.5 m x 2.5 m).
A power voltage transformer on the busbar in order to perform a 3-phase high voltage
dielectric test after transportation.
The container can be unloaded from a trailer via hydraulic jacks and connected to the
substation via isolated HV cables.
The mobile substation is self-contained including protection, control and auxiliary power
systems including:
o Digital protection relays (IEDs) and remote terminal units communicating through
IEC61850. protection relays include different protections (multi-protecting) to limit the
use of additional equipment for the same functions.
ACDC cubicles, telecom cabinets and- interface and metering cubicles.
Various protection options for different grid topologies. There are variants to allow for
transformer bays, trunk bays, incoming bays, line and cable bays.
Outward communication (Network operations and opposite side of the line) is provided for
over fiber optic (Single Mode and/or Multi Mode) cables, telephone pairs, Access and
IEC101/104 protocols.
66
TB 907 - Mobile substations incorporating HV GIS
Even though the mobile substation is an industrial compromise and not a full substation, an
attempt was made to create a state-of-the-art design with an ergonomic approach. Attention
was paid to details such as desk shelves with Ethernet and telephone jacks, emergency
lighting, pictograms, emergency exits and equipment accessibility through removable panels.
The heavy weight of the container (approximately 30 tonnes) was also a structural challenge.
Like in all prefabricated GIS substations, it has been essential to carefully analyse the
structural behaviour of the complete system [GIS + container] under transportation and
unloading conditions, and to make sure the stress and deformation would not exceed
acceptable tolerance.
H.5. Execution
The manufacturing of the mobile substation was done in a dedicated factory of the manufacturer
where all different routine tested parts from the different sub-manufacturers (GIS, protection cubicles,
communication cubicles,...) were assembled in the container. The manufacturing took approximately
12 months. After completion of the manufacturing process, the following additional factory acceptance
tests were carried out at the main manufacturer site:
Ergonomic accessibility tests
Functional test of the connection of the HV-cable on the mobile substation
High voltage test with the busbar power voltage transformer. During the high voltage test, a
partial discharge (PD) test was carried out in order to have a fingerprint for comparing with
later PD test measurements.
Functional test of loading and unloading of the container with the hydraulic jack system on a
trailer.
67
TB 907 - Mobile substations incorporating HV GIS
Figure 47 - Functional test of loading and unloading of the container during FAT
After these successful tests, the mobile substation was transported to a substation were the analysis
of the shock recorders (one on the GIS, one of the container frame) was done to check if any
problems occurred during the 1000 km road trip.
On site the manufacturer led the first installation and connection of the mobile substation together with
the TSO’s maintenance crew in order to be able to perform this autonomously in the future:
The container was bolted on a specially made concrete floor in order to avoid displacement in
case of a simultaneous shutdown of the 5 circuit-breakers of the substation.
The temporary high voltage cables were placed in u-shaped concrete gutter filled with sand
and topped with a small amount of concrete.
68
TB 907 - Mobile substations incorporating HV GIS
H.6. Conclusion
Since its delivery in 2014, the 123kV mobile substation was successfully used to refurbish a complete
70 kV substation in Belgium without having to acquire additional land. It avoideda complex shutdown
scenario of a bay-by-bay refurbishment that would have impacted the service continuity, and required
a sophisticated OH&S management plan. As a whole, the quality of the refurbished substation proved
to be much better: the substation can be entirely dismantled and re built from scratch using latest
greenfield design standards.
The compact design of the mobile substation proved to be extremely useful: transportation on a
regular truck and unloading without the need of a crane maximises the agility in narrow substation
sites. Special attention must be given to temperature control during operation.
In 2017, the company decided to acquire one more identical 123 kV mobile substation to replace an
outdated existing substation at risk. The grid function of this outdated substation will not be necessary
anymore after 2023. In order to reduce the actual risk of this substation in the grid and avoid
unnecessary CAPEX investment costs for a limited time, the mobile substation will take over the
function of the outdated station for a couple of years until the substation is no longer required by the
grid. Later on, it can then be re-used for other objectives in the grid refurbishment strategy.
Having these mobile substations will give the company a powerful tool to deal with the future
challenges on substation renewal and emergency situations.
Note: Further details of this use case can be found in the following CIGRE papers:
“The Use of Mobile Substations to Facilitate Substation Renewal”, P. De Bisschop, L. Hoebanx, A. Goyvaerts,
CIGRE Belgium Conference March 2014
69
TB 907 - Mobile substations incorporating HV GIS
“Prefabricated substations as a leverage for increased availability and agile expansion of high voltage grids”,
F.Mauban, D.Signing Tsamo, S M. Al-Otaibi, A.Goyvaerts, CIGRE Conference Paris 2018
70
TB 907 - Mobile substations incorporating HV GIS
I.1. Motivation
Type B 400/132 kV mobile substation to temporarily substitute normal transformer capacity during
maintenance and replacement works.
I.4. Solution
The mobile substation bay is a self-contained, easily transportable and modular design to enable fast
installation. The concept drawing is below:
71
TB 907 - Mobile substations incorporating HV GIS
3 single-phase 80 MVA 400/132 kV autotransformers. To reduce the risk of fire, ester fluid is
used instead of conventional transformer mineral oil. Transformers will stand in a temporary
bund (like a paddling pool) or on a pre-constructed metal grille, avoiding the need for
permanent civil works. The transformer will utilise a compact Oil-Directed Air-Forced (ODAF)
cooling system.
Dry-type polymeric transformer bushings will be used, with “plug-in” terminations on the LV
side. A 400 kV plug-in option is under development.
420 kV and 132 kV GIS modules: self-deploying for fast deployment. Dry-type rotating
bushings for rapid deployment.
Figure 51: Left: Compact transformer, Centre: Metal grille transformer bund, Right: Typical GIS module
Fully digital solution using IEC 61850 protocol. Options developed for integration with mesh
and double busbar substations.The dDesign uses isolated busbar sections to avoid interfering
with existing busbar protection and will connect to the feeder side of the disconnector. The
mobile substation will have a dedicated stand-alone SCADA system.
3 single phase 132 kV XLPE cables with aluminium laminated sheath (lightweight for manual
handling). Cables will use “click-fit” technology for easy installation. Cable drums will be
motorised for fast deployment and a number of lengths provided to minimise excess cable on
site (proposed lengths are: 30 m, 150 m and 250 m). There are some outstanding questions
on reusability of cables and requirements for making up terminations on site (to allow testing).
Cables will be surface laid with a bespoke GRP cable tray designed to hold the cables: cables
will be restrained within with ratchet straps.
Figure 52: Left: Factory-prepared Click-Fit cable end, Centre: Motorised cable drum, Right: GRP tray for
surface laid cables
There are two possible configurations of the modular design as shown in Figure 53 and Figure 54.
The option shown in Figure 53 is simpler and quicker to deploy as it does not require any interference
with the site busbar protection, however subject to the exact maintenance task or space available on
the substation site this is not always possible. Figure 54 shows a configuration whereby the full bay is
bypassed.
72
TB 907 - Mobile substations incorporating HV GIS
Reserve
Main
132kV busbars
400kV or 275kV
Mesh corner
Bay Bypass avoids
interference with busbar
protection
HV CB module
CB, CTs, connections, LV CB Module
LV cable LV CB, Busbars,
P&C module etc LV cable to connect
located close to cable, duct, cable
remote LV CB module sealing ends etc.
busbars Mobile Transformer module
Transformers, CTs, metering
to SGT module. P&C module
Secondary system, protection,
control, slip over CTs
Figure 53: Configuration of modules to avoid interference with site busbar protection
Reserve
Main
132kV busbars
400kV or 275kV
Mesh corner
New Bay enables
Bypass of whole SGT
bay
HV CB module LV CB Module
Mobile Transformer module LV cable
CB, CTs, connections, LV CB, Busbars,
Transformers, CTs, metering LV cable to connect
P&C module etc cable, duct, cable
Secondary system, protection, remote LV CB module
located close to control, slip over CTs
sealing ends etc.
to SGT module.
busbars P&C module
I.5. Execution
The designed solution has not yet been implemented, however consideration has been made of a
number of factors that relate to how the solution would be deployed on site:
Testing: Full factory testing in accordance with IEC requirements would be required. It is
proposed to carry out a test deployment at the utility’s own test facility with full commissioning
tests carried out to build confidence in procedures and the equipment. The next deployment
would be on a live site to support planned work and it is proposed again that full
commissioning tests including HV testing would be carried out. Following this second
deployment, providing everything has been successful, it is intended to look to remove the
requirement for HV testing for subsequent deployments especially where a short re-
deployment time is required.
Physical layout on site: Due to the physical size of equipment and the varying layouts of the
utility’s sites, it will be difficult to maintain access to the permanent substation equipment while
the mobile substation is installed. During the design phase some examples were developed of
real substation sites with layouts where the mobile substation could be installed to
demonstrate it would physically fit, that access routes were maintained and that all safety and
environmental impacts on adjacent equipment had been considered. An example of a layout
drawing of the mobile substation on a substation site is shown in Figure 55.
Environmental and fire risks: A key consideration of the project was to minimise any additional
risks that the mobile substation would introduce to the permanent substation. Ester insulating
fluidand temporary bunds are used to mitigate against fire risk and oil leaks.
73
TB 907 - Mobile substations incorporating HV GIS
I.6. Conclusion
This project has brought out a number of challenges in development of such a large mobile substation.
The key challenges encountered were around the integration with the existing sites, both in terms of
physically fitting the mobile substation on the site and then the integration with existing systems such
as busbar protection.
At the time of writing, the utility was still assessing the following risks prior to making an investment
decision:
Site procedure for interfacing with busbar protection
Final development of testing regime and commissioning programme for each deployment
Challenge of access restrictions from surface laid cables in existing substations
Ongoing asset management including storage and maintenance
Impact on asset lifetime of equipment due to frequent relocation – especially reuse of cables
and terminations
A 3D printed model of the solution has been produced, as shown below:
74
TB 907 - Mobile substations incorporating HV GIS
J.1. Motivation
To maintain power supply during partial refurbishment and substation extension works (lack of
physical space).
J.4. Solution
The custom solution provided the following possibilities:
The container can be unloaded from a trailer via hydraulic jacks and can be connected to the
substation via isolated HV cables.
The mobile substation is self-contained including protection, control and auxiliary power
systems.
Various protection options are possible for different grid topologies. There are variants of
transformer bays, trunk bays, incoming bays, line and cable bays.
Outward communication (dispatching and opposite side of the line) is possible via fiber optic
(Single Mode and/or Multi Mode) cable, telephone pairs, Access and IEC101/104 protocols.
75
TB 907 - Mobile substations incorporating HV GIS
The heavy load of the container (29.5tonnes) was also structurally considered.
J.5. Execution
The project single line diagram is shown below:
76
TB 907 - Mobile substations incorporating HV GIS
Figure 61: Photograph of the substation during refurbishment with Mobile Substation
J.6. Conclusion
Since its delivery in 2012, the 220 kV mobile substation was successfully used to refurbish a
complete 220 kV substation without having to acquire additional land.
The compact design proved to be very beneficial.
The substation can be entirely dismantled and rebuilt from scratch using latest greenfield
design standards
This mobile substation was considered to have a positive impact on footprint, SF 6 emissions
and environment through replacement of first-generation GIS with modern equipment
77
TB 907 - Mobile substations incorporating HV GIS
K.4. Solution
In order to meet these requirements, a highly modular substation with modules was engineered that
can be easily transported according to Belgian road regulations and installed on site in a few days
(down to a weekend for a sectioning post as the first emergency energisation proved).
The following modules were supplied for this contract:
8 x Power Transformer modules: 6.9 MVA each. Vector group Yy0d11 with a secondary
voltage of always 2 times 1280 V
o 2 with primary voltage 10/11/15 kV
o 4 with primary voltage 30/36 kV
o 2 with primary voltage 70 kV
o All can withstand an overload of 150 % for 2 hours and 300 % for 5 minutes
o Dielectric fluid: Ester oil
4 x 3 kV DC modules able to connect the 2 mobile rectifier modules. It can be configured to
control the whole substation independently of the chosen configuration/SLD
o 8 outgoing 3 kV feeders
o One 3 kV incomer
o Human-Machine Interface (HMI)
o T-switchboard
o Control of up to 32 T-switches on the overhead lines
o Central fire protection system
o Central access control system
o Central telecommunication cabinet
o Batteries, charger and AC and DC-panel
4 x Rectifier Modules:
o Rectifier
o 3 kV connection to 3 kV-module
o
o Connection of negative conductor
o Battery charger, batteries, AC-panel and DC-panel
1 x MV Module used for voltages ranging from 10 to 3 6kV
o MV GIS Switchgear (2 incomers, 4 outgoing feeders, 2 bus couplers, 1 feeder for
auxiliary transformer)
o 2 auxiliary transformers 630 kVA
o 1 primary voltage 10,11 or 15 kV
78
TB 907 - Mobile substations incorporating HV GIS
o 1 primary voltage 30 or 36 kV
o Only one used at the same time, depending on the voltage on site
o Central AC-distribution panel (for all modules)
o Gateway cabinet to make remote-control possible
o Batteries, Charger and DC-distribution panel
o Small office
1 x HV Module used for voltages from 30 to 70 kV
o GIS installation (1 incoming feeder,2 outgoing feeders,1 feeder for the auxiliary
transformer)
o 1 auxiliary transformer 630 kVA
o Central AC-distribution panel (for all modules)
o Gateway cabinet to make remote-control possible
o Batteries, Charger and DC-distribution panel Power transformer unit
Each module can be used separately.
Each module (except the transformer module) has its own emergency DC-supply (batteries
and charger).
Each module has an AC and DC-distribution panel.
Only the 3 kV-module contains a central HMI-system. To use the other modules with a fixed
substation, plugs with all the necessary signals can be connected to the inputs of the HMI of
this fixed substation.
The modules can be used in different configurations.
When a larger substation is needed, this can be created by adding additional modules (upto 4
rectifiers and two 3 kV-modules for 1 MV-module).
The 3 kV-module can be used as sectioning post.
2 complete traction substations and 2 sectioning posts can be composed with these modules
and transformers.
Two of various possible configurations are as follows:
K.5. Execution
All modules were manufactured in Belgium within the contractual delivery time. All electrical
equipment was purchased, factory tested, installed and commissioned.
79
TB 907 - Mobile substations incorporating HV GIS
All modules are designed to allow for road transport on flat bed trailers without dismantling the
main elements as to minimise site activities.
Transformers are fixed to a frame finished which at the same time serves as an oil pit with
removable sound-insulating walls. All can be lifted as one unit to allow rapid
interchangeability.
Interconnection between modules is simplified using sockets and pre-finished cables as well
as dismountable sealing solutions where applicable.
All modules are self-supported and provided with leveling landing gears.
All modules were factory tested both individually and as a complete system
K.6. Conclusion
The advantage of a mobile substation compared with a traditional traction substation is the reduced
implementation time and the cost saving as the civil works are very limited in complexity and size.
Furthermore, it presents the following advantages:
Flexibility:
It can be used everywhere in the network.
All modules can work independently.
The modules can be used in conventional substations in case of breakdown or maintenance
to by-pass a part thereof.
Fast deployment:
It can be installed on a very short term (a few days when the terrain is prepared).
It does not require building permits.
Compact:
It can be used when the available space is limited.
Functionality: it can be adapted according to circumstances on installation site.
Environmental friendly:
The substation incorporate environmental measurements to control oil spill and noise.
Safety:
The compact design does not compromise personnel or equipment safety; accessibility to
components is assured as to enable normal maintenance.
80
TB 907 - Mobile substations incorporating HV GIS
81
TB 907 - Mobile substations incorporating HV GIS
L.5. Execution
Commissioning of the GIS was done onshore after installation of the substation. During the
commissioning three disruptive discharges occurred.
L.6. Conclusion
The disruptive discharges during the commissioning led to the decision that further projects will require
a BIL test in addition to the AC withstand test during commissioning onshore.
Offshore, when the platform is at its final location, an additional AC withstand test is to be done. This
additional test reduces the risk due to transportation of the platform to its location. For the AC
withstand test power voltage transformers (PVTs) are used. The implementation of PVTs into the
relocatable substation allows for an easy but also economical way to do an AC withstand test on
demand (e.g. after maintenance or after a ship collision with the platform).
82
TB 907 - Mobile substations incorporating HV GIS
83
TB 907 - Mobile substations incorporating HV GIS
Existing
Substation
Extension
M.4. Solution
These project constraints led to a proposed solution based on the use of GIS preassembled inside a
prefabricated building including:
Gas Insulated Switchgear
Control panels
Auxiliary building services (air conditioning, lightning, fire detection, …)
Connection to the existing substation busbar is ensured with an isolated 63 kV cable, and connection
to the line and the transformer are also ensured through HV cables.
The prefabricated building substation design has been customised to meet the compactness
requirement of the road transportation and at the same time be compliant with the minimum
requirements for operability and maintainability by the end-user. A thorough collaborative assessment
was carried out at design stage with transmission operator staff to find the best compromise meeting
the two objectives.
M.5. Execution
The complete installation was designed by the EPC department of the GIS manufacturer company;
thus the substation design experts could work in close cooperation with the equipment experts. This
collaboration aimed at optimising the layout and at taking into consideration the mechanical stress
induced by the transport, the lifting and the handling.
The mechanical calculation was conducted as follows:
84
TB 907 - Mobile substations incorporating HV GIS
Through the use of the specialised workshop, a large number of time-consuming site activities have
been transferred to the workshop:
GIS assembly
Dielectric tests
Connection of control panels
LV point to point tests
Functional tests
Test of building services
As a consequence, on-site civil works were significantly simplified as a concrete building construction
was not needed. Only a basement, simple foundations and 63 kV cable trenches were needed.
Furthermore, civil works were carried out in parallel with the equipment assembly in the workshop,
while a conventional approach would have required sequential tasks: civil work followed by in-situ
assembly.
85
TB 907 - Mobile substations incorporating HV GIS
Likewise, construction site activities were reduced to just the assembly of the prefabricated building on
the foundations and the connection of the HV cables. The building prefabrication, including building
services and cabling of control panels, has significantly reduced the amount of on-site interface
management, hence a subsequent reduction of risks arising from unexpected on-site correction work
requirements.
As a result, site works could be reduced to 3 weeks for the complete installation, the connection to the
existing substation and the commissioning. Site tests were reduced to just the functional tests.
In addition to the simplification of site activity, this approach has led to a substantial reduction of the
complete lead time of the project (20 %), as shown in the diagram below.
86
TB 907 - Mobile substations incorporating HV GIS
M.6. Conclusion
This solution has demonstrated its suitability for the extension of existing substations in an urban
environment:
No need for structural modification of the existing building
Compact dimensions simplifying the construction permit process
Simplification of interface management during site construction
Simplified site work, reducing extent and duration of disturbance to existing live substation and
neighbourhood
Reduction of project lead time
This solution is now being evaluated to become one of the standard solutions for the extension of
French substations in challenging sites.
87
TB 907 - Mobile substations incorporating HV GIS
N.4. Solution
In order to match as far as possible the customer requirement, the 63 kV substation supplier proposed
a solution using a unique and large prefabricated module (24 m x 6 m), and to limit road transport by
assembling this module in a workshop situated near a river port (this choice was of course consistent
with the location of the site which was close to a port of unloading).
All HV connections to the substation were made by HV plug-in cables entering the switch room
through cable glands beneath the shelter, cable ladders were provided and fixed at site on the shelter.
The switch room was fitted with relevant equipment (crane, doors and removable platform) so as to
allow further maintenance and extension works. All external devices, such as cable trays, stairs, door
caps, outside lighting and HVAC were removable for transport.
88
TB 907 - Mobile substations incorporating HV GIS
N.5. Execution
The complete switch room was designed by an EPC department according to the customer
specification and with the support of two main partners:
The GIS factory for the design of the GIS layout, the manufacturing and the routine test of the
GIS bays according to the relevant standard (i.e. IEC 62271-203 [B3])
A subcontractor for the design and the manufacture of the shelter, and for the incorporation of
the equipment in the shelter to build the switch room
The GIS and the complete switch room were fully assembled in the factory of the subcontractor. All
the standard tests of a substation which are normally carried out on site were performed in the
workshop and witnessed by the customer. These tests consisted of:
Individual tests of HV apparatus according to their relevant standards
Secondary and primary injection of instrument transformers
89
TB 907 - Mobile substations incorporating HV GIS
Functional tests of apparatus including interlock from local panel, Distributed Control System
(DCS) panel and external information through telecom cabinet
Test of protection system
Test of interfaces between local panel, protection panel, DCS panel, and telecommunications
panel
HV tests according to routine test protocol
100 % of power frequency withstand voltage – minimum gas pressure
After testing and before shipment the SF6 pressure was reduced to 0.03 MPa, the coupling busbar
devices were dismantled, together with all external devices (stairs, platform…).
In this way, site works were limited to the installation of the switch room on the steel support structure,
the reassembly of the coupling bus bar devices, the reassembly of the external devices, the
connection of HV plug-in cables and the gas filling.
Site tests consisted in checking the bus bar resistance, performing the HV test and testing the
interface between the dispatching of the customer and the DCS of the switch room.
N.6. Conclusion
Thanks to the use of a prefabricated and pretested modular substation, erection and commissioning of
the HV substation were completed in six weeks, whereas a standard solution with a building would
have required nine months.
This solution has therefore proven its suitability for erecting and commissioning substations in remote
areas, where the transport of material to site is expensive, and the availability of skilled manpower
critical.
90
TB 907 - Mobile substations incorporating HV GIS
91
TB 907 - Mobile substations incorporating HV GIS
Partner C:
Auxiliary systems
Transport and off-shore installation of the OSS.
O.4. Solution
Since the windfarm is located approximately 140 km from the mainland, the cost of all activities that
have to be performed at the final location is extremely high. Therefore the OSS was designed and built
in such a way that it could be assembled and tested in a workshop on-shore.
In essence, an off-shore substation is equipped with the same systems as a regular on-shore
substation:
A “building” that contains all the equipment.
HV/MV equipment: transformers, reactors, switchgear and cables.
Auxiliary equipment: e.g. HVAC, firefighting, lighting.
92
TB 907 - Mobile substations incorporating HV GIS
However, there are a number of design challenges due to fact that it is an off-shore substation:
The complete platform is a steel construction that needs to be transportable.
The extent of onshore installation, testing and commissioning should be maximised, in order
to minimise the off-shore activities.
Special measures need to be taken so that everything that is not installed in a climate-
controlled room, can withstand the aggressive salty, wet and cold North Sea conditions. The
quality of the painting process is therefore extremely important and must be controlled
meticulously.
The dimensions of the platform have to be reduced to a minimum. Consequently the
dimensions and layout of every component forming part of the OSS needs to be optimised:
the largest custom-made electrical items are the two power transformers and the high voltage
switchgear.
The transformers consist of a transformer part and a separate cooler bank. The transformer
part is positioned in a non-climate-controlled air-ventilated room while the cooler banks are
placed outdoors. The coolers are equipped with fans that only need to be in operation when
the second transformer is switched off. This philosophy makes it possible to minimise the size
of the transformers whilst providing a high level of redundancy to ensure the wind park’s
power output can be maintained during outages.
The HV GIS has an non-standard configuration in the sense that it is quite high so that the
total ground surface could be limited to a minimum. The primary function of the GIS is to
transfer the power coming from one or two transformers to one or both export cables. This
flexibility was created by the H-configuration of the switchgear, consisting of 2 cable bays, 2
transformer bays and a coupler.
93
TB 907 - Mobile substations incorporating HV GIS
O.5. Execution
The components of the steel structure were manufactured in sections and partially painted at one
construction yard, after which they were transported to a second yard. After arrival at this second
location, the sections were welded together to form the final structure of the substation. Finalisation of
the painting and installation of the access ways was completed before the start of the works of the
other JV-partners.
Bringing the equipment into the substation is a lot more complex for an off-shore substation than it is
for a conventional on-shore installation. Some challenges are, for example:
Dimensions of the doors are limited due to off-shore regulations and rooms are dimensioned
to optimise the footprint of the OSS. Consequently the equipment has to be engineered,
taking into account these constraints.
The 2 main transformers (240 MW ONAN/340 MW ONAF, 195 tonnes each without cooler
banks), have to be hoisted into the OSS structure through the roof.
The main transformers were transported to the erection yard by barge.
Figure 85: Power transformer being moved from barge to quay at the yard
94
TB 907 - Mobile substations incorporating HV GIS
Figure 86: Power transformer being hoisted into the OSS structure
All equipment had to be completely installed, wired, tested and pre-commissioned on-shore. Due to
the short construction programme, and the fact that a lot of activities involving different JV partners
were linked to each other, it was a challenge to complete this project within the contractual deadlines.
Since the costs for every week the windfarm was not able to supply power to the onshore grid was
high, the liquidated damages that were applicable in many stages of the project made it imperative to
achieve the contractual milestones.
All components were assembled in the platform and tested, as is typically required following assembly.
After interconnection of all components with HV cables, the complete system was subjected to a soak
test. After transport to the deployment site, the complete installation was again subjected to a soak
test. For the transport of the finalised platform of 2400 tonnes, a number of specialized techniques
where needed. Within the yard, eight-off ten-axle Self-Propelled Modular Transporters (SPMTs) were
positioned under the platform. They were able to drive the platform onto the barge used for transport
to the deployment site.
95
TB 907 - Mobile substations incorporating HV GIS
96
TB 907 - Mobile substations incorporating HV GIS
O.6. Conclusion
The prefabrication and preassembly of off-shore substations is a logical response to the constraints
imposed by the off shore location and environment. A number of benefits were realised with this
project:
Early grid connection
Reduced site works
Lower costs.
97
TB 907 - Mobile substations incorporating HV GIS
77 kV
Transformer car
Cubicle car
Residual CT
98
TB 907 - Mobile substations incorporating HV GIS
P.4. Solution
In the first step, the utility defined the scope of the new mobile substation to include transformer
capacity and LV output signal commuication.
The utility specified their own standard of mobile substation which can be connected or installed to all
distribution substations in their network.
The network has a standard distribution substation design, although some communication and
protection relay generations vary.
Specifiying the LV connection cable detail was critical to reduce the installation time, because the time
for connection and checking of LV cables, including signal and power supply, take a significant
portion of time.
The developed specification of the mobile substation has the following key characteristics:
Mobile substation composed of two “cars” (Transformer car and Cubicle car) which covers half
of a general distribution substation.
Size and weight of each car capable of meeting the transportation regulations in Japan
To connect with latest second-generation communication system.
Applying a special connector joint for control cables
P.5. Execution
Special cable connector arrangement for LV cables:
Even though the connections for each cable is clearly specified, it is still necessary to perform a check
each time that the correct connection has been made. In the mobile substation, to avoid incorrect
connections, different kinds of cable connection are used. This solution makes it easier to connect the
cables correctly, and makes it more easy to check connections after installation.
99
TB 907 - Mobile substations incorporating HV GIS
Site Testing:
In order to minimise on-site testing time the utility decided to omit the high voltage test. Instead a
dielectric test at operating voltage for ten minutes is carried out.
Training:
To minimise installation time such as main circuit connection, regular training is very effective.
P.6. Conclusion
The mobile substation achieves half of the installation time in comparison to the conventional type, as
shown in Table 8 below.
100
TB 907 - Mobile substations incorporating HV GIS
・Two trucks (Transformer car, Cubicle car) ・Four trucks plus one truck for accessories
plus one truck for accessories
Transportati ・Sometimes need for permission of road
on ・No need for permission of road administrator
administrator as within Japanese
regulations.
101
TB 907 - Mobile substations incorporating HV GIS
Q.1. Motivation
The main motivation for installation of a mobile substation is “Fast deployment of substation”.
For example, Japan has suffered many earthquakes in the past and in such cases mobile substations
contributed to rapid recovery of the power supply.
Q.3. Requirements
The main uses of mobile substations are:
To support maintenance and refurbishment
For emergency deployment in case of a fault or failure
The substations are therefore required to support rapid deployment (Type A mobile substation).
Utilities perform reasonable and minimum maintenance for mobile substations.
The policy at one utility is to omit time-based maintenance, carrying out checking and maintenance
before use.
The limitation of installation duration
For maintenance or refurbishment: 10 - 20 days
For emergency: 24 hours
The frequency of maintenance
2 utilities: less than 3 years
1 utility: every time before using (not time-based)
1 utility: according to supplier manual
Q.4. Conclusion
Mobile substations are very useful for recovery of emergency outages caused by equipment failure.
This was demonstrated following the Great East Japan Earthquake.
Power utilities also effectively use mobile substations to maintain temporary supplies during
maintenance of normal substations.
102
ISBN : 978-2-85873-612-6
TECHNICAL BROCHURES
©2023 - CIGRE
Reference 907 - June 2023