Professional Documents
Culture Documents
Lecture No. 8-1
Lecture No. 8-1
Engr. M. Nouman,
Lecturer, CED, SUIT.
Email: mnouman.civil@suit.edu.pk
• A network is a graphic representation of a project plan.
• A project schedule network diagram is an output type of the
process ‘sequencing activities’ according to PMI’s Guide to
the Project Management Body of Knowledge.
• The activities that make up the project and the logical
relationships that exist between these activities are
represented by a group of arrows and nodes.
Activity name
i j
Construction Management (Engr. M. Nouman) - Fall 2022 7
Activity name
i j
1. Arrow Diagramming Method (ADM):
§ Recommendations on building Activity on
arrow:-
• Draw arrows from left to right.
• j must be greater than i (j>i).
• Each activity must have an unique i-j number.
• Always number the nodes after the diagram is
completed.
X
yA
ty
cti
i
vit
iv
y
t
Ac
i k
Construction Management (Engr. M. Nouman) - Fall 2022 Activity Y 10
§ Example 1 (ADM):
Activities Predecessor D
A -
B
B A A
C A
C
D B E
E B, C
F
F C
Construction Management (Engr. M. Nouman) - Fall 2022
§ Example 1 (ADM):
D
Activities Predecessor 3
A - B
A E
B A 1 2 5 6
C A C
D B 4
F
E B, C
F C
A - A
B - B E 5
1 3
C -
D A C
F
4
E A, B
F A, B, C
Construction activities
B D
A F
C E
Logical relationships
Construction Management (Engr. M. Nouman) - Fall 2022 14
B
B B
A
A A
C C
C
Construction Management (Engr. M. Nouman) - Fall 2022 15
A C
B B C
D
B A A
A
B
Start B E Finish
C F
Construction Predecessor
Activities Activities B
A -
B A
A D
C A
D B, C C
Construction Predecessor
Activities Activities
A - B D
B A
A E
C A
D B
C
E C, D
Construction Predecessor
Activities Activities
A - B D
B A
A PF
C A
D B
C E
E B, C
Construction Predecessor
Activities Activities A D
A -
B - PS B PF
C -
D A, B C E
E B, C