Minutes of Construction Quality Meeting #003

Venue: Block-07, New Project office, KPO


Date & Time: 10-03-2014 & 02.30pm

Members Present: (44/53)


As per enclosed List

S.No. Points Discussed Action by Date by


Previous MOMs has been reviewed and action points
1 CB
complied.
Mr. Singh suggested that, maximum 3 remainders
will be issued to Agency regarding compliance of
2 Info
pending NCRs. After that certain action will be taken
by concerned authority.
Roster to be prepared & submitted to CB/MK by all
3 CB/MK Immediate
Individual teams.
Construction material test data is to be recorded in
4 some authorized format. Format of data sheet is to be BP/SC Immediate
finalized. All data will be stored in a central place.
Bricks/ Brick work of all agencies/zones will be
inspected as a campaign on 11th March 14 and report
5 BP/SC 11.03.14
to be submitted after conducting all tests in addition
to other inspection.
Mr. Singh advised that each report should have at
11.03.14
6 least 5 Nos. observations/Non-compliance, if CB
onwards
possible.
Mr. Singh suggested that Daily summary report 11.03.14
7 MK
should show discipline wise detail. onwards
Revised format of daily CQC report has been shown
8 Info
and explained to all by Mr. CB.
Once again explained to CQC team regarding
9 MK Done
Uniform file/report numbering system.
Meeting has been conducted with different agency’s
10 responsible representatives to emphasize the quality CB Done
& their action for improvement.
11 Batching plant No:6 of L&T shall be calibrated. SC/SA Immediate