Thai Binh Thermal Power Plant Project - Contract No.

261213/TB-EVN-MC Minutes of Kick-off Meeting (Boiler)

Date: 14-16 April 2014


Location: EVN’s Twin Towers, No. 11, Cua Bac Street, Ba Dinh District, Hanoi
Participants:

No Name Position Company Signature

1. NGUYEN VAN CUONG BOILER ENGINEER TBPMB

2. LESLIE LEACH BOILER ENGINEER FICHTNER (Consultant)

3. TRAN QUANG MINH BOILER ENGINEER PECC1 (Consultant)

4. S. RENGARAJAN PROJECT ENGINEER MARUBENI

5. ERIC LEASCHNER PROJECT ENGINEER MANAGER FOSTER WHEELER

6. KEVIN MILLER PROJECT DIRECTOR FOSTER WHEELER

7. MECH. LI PROJECT MANAGER FOSTER WHEELER

8. JOHNSON WANG PROJECT ENGINEER MANAGER FOSTER WHEELER

9. VUONG PHAN COUNTRY MANAGER FOSTER WHEELER

736140905.doc 1/4
Thai Binh Thermal Power Plant Project - Contract No. 261213/TB-EVN-MC Minutes of Kick-off Meeting (Boiler)

TBPMB/Consultant and MC’ s


No Item Reference Conclusion
thoughts

List of Shop Inspection and Test GC 23; PC The Employer's witness inspection 1. MC(FW) to re-issue ITP as per
23 point and number of inspectors shall be bidding documents
Workshop and Site Inspection Plan
determined during the Kick Off 2. MC(FW) to amend/correct packages
Volume 2
(Boiler) Meeting after the Contract signing.
3. MC(FW) to submit witness point list
with place + date of tests as per
0161-TB-
contract
MCP(FW)
4. MC(FW) to indicate in ITP which
documents will not be included in final
1
documents (internal only FW+vendor)

5. MC(FW) to submit required hydro


test procedure before any inspection (1
month as per Contract). Procedure for
tests for information only, not for
approval.

The revised ITP should be submitted


officially by MC before 24 April 2014.

Site ITP (Boiler) (include Hold and Witness Will be submitted by MC later
2 Points)

736140905.doc 2/4
Thai Binh Thermal Power Plant Project - Contract No. 261213/TB-EVN-MC Minutes of Kick-off Meeting (Boiler)

TBPMB/Consultant and MC’ s


No Item Reference Conclusion
thoughts

List of concerned issued in Nghi Son 1


Q
TPP

3 Coal pulverizer: Coal stuck in bunker Coal get stuck in the bunker when it is MC(FW) are aware of the problem at
provided to the pulverizer at Nghi Son Nghi Son. MC(FW) followed the
bidding document/contract to supply
stainless steel liners for NS and TB.

MC(FW) noted the coal at NS1 has


often been out of spec. Specifically it
has been too wet and too hard.
MC(FW) believes that improved coal
yard management could help alleviate
the issue.

MC(FW) provided air cannons on NS1


and is providing air cannons on TB to
help alleviate blocking as required by
the contract, however these are not
guaranteed to prevent blocking.

MC(FW) also believes a “Tyvar” liner


in the bunker (instead of the Stainless
Steel liner as defined in the contract)
might minimize the potential for

736140905.doc 3/4
Thai Binh Thermal Power Plant Project - Contract No. 261213/TB-EVN-MC Minutes of Kick-off Meeting (Boiler)

TBPMB/Consultant and MC’ s


No Item Reference Conclusion
thoughts

blocking.

MC(FW) will supply a hammer plate


welded to the bunker at no additional
cost.