You are on page 1of 1

Toronto Transit Commission

Engineering, Construction and Expansion

Request for Information (RFI) Form RFI No. Rev. Total pages
Step 1 (General Contractor to complete): Contract & Information Requested
Contract Number Contract Name

Subject:
Date Requested Request Response by
(Allow reasonable timeframe for TTC to review and respond)
Reference Documents (relevant portions attached)
Contract Drawing #:
Shop Drawing #:
Specification Section / Clause:
Description of RFI See attached (if required)

Proposed Resolution (If any) Information not shown on Contract Documents


Clarification / Interpretation of Contract Documents
Conflict in Contract Documents / Requirements
Site Conditions
Other:
Requested by (Name & Position) Company Name

Step 2 (TTC to complete)


Response to RFI See attached (if required)

Replied by (Name & Position) Date Replied Unjustified


Incomplete

Request for Information, Form 81-01-001, Apr. 2015, Rev. 01