Subject: 4-laning of Ambala-Kala Amb section of NH-72 (Part of New NH-344 from
Ambala Ring Road (Design Chainage (-) 0+800) to Shahzadpur and Part of
New NH-7 from Shahzadpur to Kala Amb (HR/HP Border) (Design Chainage
33+015)) in the state of Haryana and Punjab (Design Length 33.815 Km) on
Hybrid Annuity Mode under NH(O).
Reference: - Your quotation dated 01.08.2023.
Dear Sir,
As per your quotation dated 18.02.2023, we are pleased to place a work
order for the above-mentioned project: -
Sr. Description Rate
No.
1. To collect the sample of various construction Rates as per Enclosed
materials from the site of work/yard, for testing as Annexure-A on the
per relevant IS Code/MoRT&H specifications and mutually agreed terms &
conveying the result for the work cited as subject. conditions.
Term and Conditions: -
1. The work will be immediately started after the confirmation through this work
order/letter.
2. Income Tax (TDS) as applicable will be deducted.
3. GST will be paid extra as applicable.
4. You will fully indemnify, hold harmless and defend the DCC Infra Projects limited
from and against any and all losses, damages, costs charges and/ or claims with
respect to the death of or injury to any person, loss of or damage to any property
that may arise during the Construction process.
5. Courts of Kaithal shall have Jurisdiction to settle any dispute or claim arising out
of this sub-contract/work.
6. Bills shall be considered for payment if it is approved and signed by all the
members of committee comprising of Project Manager, Q.S and one Authorized
Q.C Engineer.
7. Payment shall be done as per submitted bills, which are only subjected to TDS
deduction if applicable.

Please sign one copy of this work order as token of your unconditional acceptance.
No payment will be made without acceptance of this work order.

Yours Faithfully, Accepted By


For DCC Infra Projects Ltd The Bombay Textile Research Association

Auth. Signatory Auth. Signatory


ANNEXURE-1
Sr. No. Description Rate (In Rs.)
GEOCOMPOSITE
1 Tensile strength & elongation 3585
2 CBR puncture 2710
3 Mass 510
Thickness 510
In Plane permeability 3010
GEOTEXTILE
1 Mass 510
Thickness 510
Tensile strength & elongation 3585
CBR puncture 2710
Grab strength 1310
Trapezoidal tear 1260
Permittivity 2110
AOS 760
GEOGRID
Apenture size 510
Percent open area 1010
Thickness 510
Flexural rigidity NC
Tensile strength & modulus & elongation 2310
Junction strength & efficiency 3010
EPDM PAD
Hardness 760
Compressor test 3010
Colour 510
Density 1010
Ash content 1010