You are on page 1of 6

2019 2nd International Conference on High Voltage Engineering and Power Systems (ICHVEPS) - Bali - Indonesia

Study of Increasing Surge Impedance Loading (SIL)


and Voltage at DEPOK Substation by Changing
TASIK-DEPOK 500 kV Transmission Line's
Configuration
Fajar Tri Wardana Rudy Setiabudy
PT PLN (Persero) UIW Aceh Electrical Engineering Department
PT PLN (Persero) University of Indonesia
Jakarta, Indonesia Jakarta, Indonesia
fajar.tw@pln.co.id rudy@ee.ui.ac.id

Abstract— In electric power systems, good electric power amount of electric power that could be flowed, when a large
transmission is vital to occupy the load requirements. Power amount of current flow in the transmission line, the voltage at
transmission capacity on transmission lines restricted by Surge receiver sides will be lower than sender sides. The more
Impedance Loading (SIL). When the transmission line loaded at significant amount of current flow makes an immense value of
its SIL value, then the transmission line will be purely resistive.
the voltage drop in the transmission line. Commonly used
If the transmission line is purely resistive, then the value of drop
voltage will decrease and will improve the power quality. The
ways for overcoming voltage drop are by using reactive power
voltage that below its reasonable value would cause the electrical compensator on the receiver side, the increasing voltage at the
equipment does not work in the maximum performance. When a sender side and increasing the level of surge impedance
transmission line SIL level is increased, the capacity of a loading (SIL) on its line. The last ways will be discussed in
transmission line will also increase. Increasing the level of SIL this paper.
can be done by changing the configuration of the transmission
line. The conversion is done inter alia, expand the diameter of the In this paper, a study case will be performed on the 500 kV
conductor, increasing the distance between sub-conductor, Jawa-Bali grid. By changing the line’s configuration, which
increasing the number of sub-conductor per phase, and
also changes inductance and capacitance of the line, at the
decreasing the gap between phases. From all of these variations,
it can be seen that the value of SIL and drop voltage of 500kV same time, it will change surge impedance loading (SIL) level.
transmission line TASIK-DEPOK. From the results obtained, it Changing the line’s configuration purposed to get a higher
can be concluded that the value of the largest SIL occurs when level of surge impedance loading (SIL) and will be observed
the number of sub-conductor as much as 6 pieces with the sub- the drop voltage value on the connected bus. The purpose of
conductor distance between 80cm. The highest SIL is 2429.45 this study is to obtain a relationship between surge impedance
MW, and the highest %voltage of DEPOK bus is 96.81%. loading (SIL) and drop the voltage on the transmission line so
that it can decrease drop voltage in Jawa-Bali 500 kV
Keywords—transmission line, surge impedance loading, drop transmission line. The reviewed line on this paper is TASIK-
voltage DEPOK line.
I. INTRODUCTION
II. THEORY REVIEW
Electric Power System generally divided into three A. Surge Impedance Loading (SIL)
subsystems that are generating electricity, transmission and Surge Impedance Loading (SIL) is defined as active
distribution. Transmission is using to drain a large amount of power/loading (MW) consumed by a resistive load through a
electrical power. The transmission system is using high line in which its value as the same as surge impedance value on
voltage to drain electrical power. It is aimed at decreasing its line. While surge impedance is a characteristic impedance
losses caused by conductor dissipation. When the voltage is (Zc) of the specified line. The transmission line produces
increased, then the electric current will decrease. When reactive loading MVAr) as a result of its natural capacitance.
electric current decreases, then it will be decreasing the MVAr amount produced is dependent on its capacitive
dissipation losses. The transmission line has a restriction reactance (XC) and voltage in the line. Not only produces
capability to drain power electrical. One restriction is the line MVAr, but also the transmission line absorbs reactive loading
conductor temperature limit. When an electrical current is to produces the magnetic field. The magnetic field strength is
flowing in a line conductor, it will arise some heat caused by dependent on the magnitude of the current flow in the line and
dissipation. This temperature limit will restrain the amount of the line’s natural inductive reactance (XL). Absorbed reactive
current flow within the conductor and directly will restrain the

978-1-7281-2669-2/19/$31.00 ©2019 IEEE 097

Authorized licensed use limited to: Cornell University Library. Downloaded on August 16,2020 at 04:40:03 UTC from IEEE Xplore. Restrictions apply.
load also dependent on the current flow and XL. When the B. Surge Impedance Loading Increasing Method
transmission line is loaded on its SIL level, this line will have From Eq. (4), it can be seen that SIL is dependent on
the same amount of both produced and absorbed MVAr. So characteristic impedance (Zc). Zc is also dependent on the
that, the transmission line will appear in its nature resistive. inductance and capacitance of the line. On formulizing
Absorbed and produced reactive power in the transmission line transmission line impedance and capacitance, it can be seen
can be expressed as, that affect variable is the value of the line geometric mean
distance (GMD or DEq) and geometric mean radius (GMR or
= (1) r' or Ds). As known before, the line inductance and capacitance
can be rewritten as,
= (2)
= 0.7411 log (6)
When line is loaded on its SIL level,
.
= (7)
=

= Therefore, to change and increase the SIL level, can be


performed by changing transmission line geometric mean
distance (GMD) and geometric mean radius (GMR)
= L/C (3) magnitude. GMD and GMR magnitude can be changed by
changing the transmission line configuration. In this study, SIL
Where V: phase to phase voltage at receiver side (VR) magnitude will be increased. Thus, transmission line
I: current at receiver side (IR). configuration can be performed in several ways, inter alia:

As known before Zc = / , The SIL level is occur when  Close phase distance, it will decrease GMD, so that
ratio between voltage and current (at receiver side) is equal to inductance will decrease and SIL will increases.
Zc in its line. Active power (MW) magnitude in SIL level can
be expressed as,  Dissociate sub-conductor distance, it will increase GMR
and decrease inductance and also increase SIL.
= [ ] (4)
/

and current IR at SIL level can be written as,

= [ ] (5)
√ /

When a line is loaded below its SIL, then the line will supply
reactive load into the system. Otherwise, when a line is loaded
over its SIL, then the line will absorb reactive load from the
system, so it will decrease the voltage. SIL chart is generally Figure 2. Bundle conductor arranged from 4 conductor
can be shown as,
 Increasing conductor diameter, it will increase GMR and
decrease inductance and also increase SIL.

 Increase sub-conductor on each phase, GMR will increase,


the inductance will decrease and also increase SIL.

By applying these methods above, inductance will decrease


and capacitance will increase automatically, so that SIL will
increase. With increasing SIL, drop voltage will decrease.
C. Transmission Line characteristic on SIL Level
Transmission line characteristic can be expressed as,

Figure 1. Line SIL characteristic = cosh( ℓ) + sinh( ℓ) (8)

098

Authorized licensed use limited to: Cornell University Library. Downloaded on August 16,2020 at 04:40:03 UTC from IEEE Xplore. Restrictions apply.
IR will change in SIL situation, therefore Eq.(8) can be written A. X and Y Transmission Line Calculation
as, Because of using bundle conductor and various transmission
line configuration, so the 500 kV Jawa-Bali X and Y
On SIL level, transmission line calculation needs more attention. Geometric
Mean Radius (GMR) for each configuration of bundle
= (9) conductor can be expressed as,
TABLE 1.
GMR FORMULAS FOR EACH BUNDLE CONDUCTOR
By substitute eq.(09) into (08) obtained, CONFIGURATION

= cosh( ℓ) + sinh( ℓ) Number


of Configuration GMR Formula
= [cosh( ℓ) + sinh( ℓ)] (10) conductor

Remembering ,

= = + (11) 2 =√

cosh( ℓ + ℓ) = cosh ℓ cos ℓ + sinh ℓ sin ℓ

sinh( ℓ + ℓ) = sinh ℓ cos ℓ + cosh ℓ sin ℓ (12)


3 = ′
Eq.(10) can be written as,

= (cosh ℓ + sinh ℓ)(cos ℓ + sin ℓ) (13)

= (cosh ℓ + sinh ℓ) ∠ ℓ (14)

Where : attenuation constant [neper/mile] 4 = 1.09

: Phase angle constant [radian/mile].

From Eq. (14) can be seen that voltage magnitude at receiver


side is depends on α magnitude and its phase angle is depends 6 = 1.272 ′
on β magnitude.
III. 500 KV JAWA BALI GRID SIMULATION
Where ′ is GMR of every ACSR stranded conductor used in
In this study, the observed object is a drop voltage on a bus.
the bundle conductor, ′ and d is in meter and also GMR
Conductor diameter (either aluminum or steel), sub-conductor
produced is in meter. Especially for line capacitance
distance, sub-conductor number in a bundle conductor and
calculation, ′ is changed by r (radius) of the ACSR stranded
phase spacing will become a variable. TASIK-DEPOK line
conductor.
will be selected for observed. It is because this line, from Tasik
Substation to Depok Substation, has 279,5 km long. The
B. Vertical Line Configuration
performed variation will significantly be seen. Through data
Vertical line that used in 500 kV Jawa-Bali grid is generally
was obtained from PT PLN (Persero) P2B Jawa-Bali, can be
double vertical. There is a difference in Deq/GMD and Ds/GMR
made a 500 kV Jawa-Bali grid simulation using ETAP
calculation for double vertical line configuration. Deq and Ds
(Electrical Transient and Analysis Program) 12.6.0. This
calculation can be written as below,
simulation will perform load flow simulation, so the voltage at
each bus while the grid operates can be known. Especially on
the transmission line, parameters that need to be inputted to =
ETAP will be entered based on calculation before. It is because
variations carried out throughout the study will directly affect =
the value of these parameters. Parameters which needs to be
inputted on transmission line rating in ETAP is reactance (X) =
and susceptance (Y).

099

Authorized licensed use limited to: Cornell University Library. Downloaded on August 16,2020 at 04:40:03 UTC from IEEE Xplore. Restrictions apply.
= (15) • Line configuration : Double vertical
Phase distance and TASIK-DEPOK line configuration as
and the calculation for Ds can be expressed as, seen in Figure 4.
From the rating and data, magnitude of each parameters can
be carried out and written as,
=
L = 0.4259 (mH/phase/km)
C = 0.0266 (μF/km to neutral)
= X = 0.1337 (ohm/phase/km)
Y = 8.3481 (μSiemens/km)
= Zc = 126.5648 (ohm)
SIL = 1975.2729 (MW)
= (16) On Jawa-Bali 500 kV grid, TASIK-DEPOK line connects
between Tasik substation busbar and Depok substation busbar.
The load is flow from Tasik to Depok. Depok busbar is also
Furthermore, inductance and capacitance of the double vertical
connected to Gandul substation and Cibinong substation.
line can be written as,
Moreover, on Depok substation busbar is installed two units
500 MVA IBT (Inter Bus Transformer) 500 kV/150 kV.
= 0.461 log (17)
A. Changing Radius of Gannet ACSR
. Because of using ACSR conductor, the radius change
= (18) variation is performed not only to the steel strand but also
aluminum strand. Data obtained from the simulation can be
Where, L : Inductance (mH/phase/km) seen in Table 2. The blue row is an original rating of the used
C : Capacitance (μF/km to neutral) conductor. Radius variation is performed by increase and
Deq : Mutual GMD (m) decreases the stranded conductor radius. From Table 2, it can
Ds : Self GMD (m) be seen that inductance and reactance magnitudes will increase
while the radius is shortened. Otherwise, it will decrease while
the radius is extended. At the same time, capacitance and
susceptance magnitudes will increase while the radius is
extended and will decrease while the radius is shortened. This
is because while the radius is extended, r' and also GMR will
increase.
With this effect, it will impact to characteristic impedance
(Zc), SIL, and voltage magnitude at DEPOK bus. The impact
can be seen in Table 2. While inductance decrease and
capacitance increase, Zc will decrease, and SIL will increase.
Furthermore, DEPOK voltage will increase because the drop
voltage in TASIK-DEPOK line has decreased. In Table 2, the
highest DEPOK voltage magnitude is on the sixth row, where
the stranded conductor radius is the widest.
TABLE 2.
PARAMETER DATA DUE TO CHANGE CONDUCTOR RADIUS
∆V (%)
Figure 3. Double vertical line configuration r St r Al SIL %V
No TASIK-
(cm) (cm) (MW) DEPOK
DEPOK
IV. CASE STUDY
1 0.12 0.16 1946.14 96.08 7.08
500 kV transmission line from extra high voltage substation 2 0.13 0.17 1953.851 96.09 7.07
in Tasik to Depok is using double vertical configuration.
TASIK-DEPOK line has 279.5 km long. TASIK-DEPOK 3 0.14499 0.1858 1964.932 96.11 7.05
rating and data can be seen below, 4 0.14499 0.2 1970.396 96.12 7.05
• Conductor : Gannet ACSR 5 0.1581 0.20335 1977.657 96.13 7.03
• Number of steel/aluminum : 7/26
6 0.17 0.25 1994.073 96.16 7.02
• Radius of steel/aluminum :0.1581cm/0.20335 cm
• Number of sub-conductor per phase : 4
• Sub-conductor distance : 40 cm
• Bundle conductor configuration : Quadruple

100

Authorized licensed use limited to: Cornell University Library. Downloaded on August 16,2020 at 04:40:03 UTC from IEEE Xplore. Restrictions apply.
B. Changing Sub-Conductor Distance From the data above, it can be seen that the more the number
TASIK-DEPOK line uses quadruple bundle conductor with of sub-conductors used in bundle conductor, the greater the SIL
a 40 cm long distance between each stranded conductor. Data magnitude and the higher the DEPOK bus voltage. For each
obtained from the simulation results can be seen in Table 3. distance variation between sub-conductors, the same
The distance between sub-conductor variation in a bundle conclusion can be drawn that the farther the distance between
conductor is performed by distancing and bringing the distance the sub-conductors, the greater the SIL magnitude and the
closer. From Table 3, it can be seen that the farther the distance higher the DEPOK bus voltage.
between sub-conductors, the inductance and reactance
magnitudes will be smaller and vice versa. While for the TABLE 4.
PARAMETER DATA DUE TO CHANGE THE NUMBER OF SUB-
capacitance and susceptance magnitudes will be greater when
CONDUCTOR
the distance between the sub-conductors farther and vice versa.
This is because the change in distance between sub-conductors Number ∆V (%)
Spacing SIL %V
will affect the GMR value of the bundle conductor. The farther No of Sub- TASIK-
(m) (MW) DEPOK
the distance between the sub-conductors, the greater the GMR conductor DEPOK
magnitude and vice versa. From the influence on the parameter
1 4 0.4 1977.66 96.13 7.03
magnitudes above, the value of Zc, SIL and the voltage on the
DEPOK bus will also change. The farther the distance between 2 0.2 1504.13 95.39 7.74
the sub-conductors, the lower the magnitude of Zc and the 3 0.3 1561.20 95.49 7.65
greater the value of SIL. Furthermore, it will cause the voltage
drop magnitude to be smaller, and the voltage on the DEPOK 4 2 0.4 1604.40 95.56 7.57
bus will be increased. 5 0.5 1639.59 95.61 7.52
TABLE 3.
PARAMETER DATA DUE TO CHANGE SUB-CONDUCTOR 6 0.6 1669.51 95.66 7.48
DISTANCE 7 0.2 1645.94 95.62 7.48
∆V (%) 8 0.3 1738.68 95.76 7.36
Spacing SIL %V
No Zc (ohm) TASIK-
(m) (MW) DEPOK 9 3 0.4 1811.08 95.88 7.25
DEPOK
10 0.5 1871.53 95.97 7.18
1 0.2 142.1458 1758.758 95.79 7.31 11 0.6 1924.00 96.05 7.12
2 0.3 133.0315 1879.254 95.98 7.15 12 0.2 1918.02 96.03 7.1
3 0.4 126.5648 1975.273 96.13 7.03 13 0.3 2079.59 96.28 6.91
4 0.5 121.5488 2056.787 96.25 6.95 14 6 0.4 2211.79 96.48 6.78
5 0.6 117.4505 2128.557 96.36 6.88 15 0.5 2326.50 96.65 6.68
6 0.7 113.9853 2193.264 96.46 6.81 16 0.6 2429.45 96.81 6.58
7 0.8 110.9837 2252.583 96.55 6.76

C. Changing Number of Sub-Conductor D. Changing Phase Distance


On TASIK-DEPOK line, the number of sub-conductors Changing phase distance is performed by changing the
used is 4 Gannet ACSR. The variation that will be performed vertical distance between A, B, C phase, and also by changing
is to change the number of sub-conductors into 2, 3, and 6. For the horizontal distance between one circuit with another.
each change in the number of sub-conductors, there will also Simulation data for the changing phase distance can be seen in
be a variation of the distance between sub-conductors as much Table 5.
as 5 data. Simulation data for variations in the number of sub- Changing the phase distance can change the transmission line
conductors can be seen in Table 4. parameters magnitude. It can be seen in Table 5, the reactance
Changing the number of sub-conductors in a bundle magnitude will decrease, and the susceptance magnitude will
conductor will affect the calculation of the GMR from the increase when the phase distance gets closer and vice versa.
bundle conductor. So, it will affect the value of the This is because changing the inter-phase distance will change
transmission line parameters. The reactance magnitude will be the GMD value of the line. GMD will decrease when the phase
decreased while the number of sub-conductors is multiplied distance gets closer and vice versa.
and vice versa. Otherwise, the susceptance magnitude will be With the influence on the transmission line characteristic, the
increasing while the number of sub-conductors is multiplied SIL magnitude and the DEPOK bus voltage will change. Both
and vice versa. of them will increase when the phase distance is getting closer.
But bringing the inter-phase distance closer in practice also has

101

Authorized licensed use limited to: Cornell University Library. Downloaded on August 16,2020 at 04:40:03 UTC from IEEE Xplore. Restrictions apply.
to consider several things, because the phase distance affects V. CONCLUSION
the air insulation strength between the line conductor.
1. The highest SIL and DEPOK bus voltage is obtained
TABLE 5.
PARAMETER DATA DUE TO CHANGE THE PHASE DISTANCE when the number of sub-conductors is 6 with 60 cm
spacing.
∆V (%) 2. The highest SIL is 2429.4543 MW and DEPOK
DAB DBC DAC D SIL %V
No TASIK- bus %voltage is 96.81%
(m) (m) (m) (m) (MW) DEPOK
DEPOK 3. The highest SIL level and DEPOK bus voltage for each
changing is:
1 9.7 12.2 21.9 29 1969.799 96.12 7.05
∆V (%)
2 9.7 13 22.7 27 1962.623 96.11 7.05 SIL %V
No Change Type TASIK-
(MW) Depok
3 9.7 12.2 21.9 28 1972.435 96.12 7.05 DEPOK
Sub-conductor
4 10 12.2 22.2 27 1969.559 96.12 7.05 1 1994.07 96.16 7.02
diameter
5 9.7 12.2 21.9 27 1977.657 96.13 7.03 Sub-conductor
2 2252.58 96.55 6.76
6 9.7 12.2 21.9 26 1978.33 96.13 7.04 spacing
7 9.7 11 20.7 27 1996.197 96.16 7.02 Number of
3 2429.45 96.81 6.58
sub-conductor
8 9.7 12.2 21.9 25 1981.625 96.14 7.03 4 Phase distance 2037.95 96.22 6.97
9 8 12.2 20.2 27 2011.97 96.18 7
10 9.7 10 19.7 27 2015.784 96.19 6.99 VI. SUGESSTION
11 7 12.2 19.2 27 2037.956 96.22 6.97 Because the stranded conductor used is ACSR Gannet with a
total number of strands is 33 strands, it will be difficult to
determine the ACSR GMR value. In this study the GMR value
E. Result Analysis of stranded conductors uses the approach of ′. To obtain a
Increasing the SIL level and DEPOK bus voltage, it can be result that is closer to real, the GMR formula of stranded
performed by increasing the diameter of the conductor ACSR, conductor should be determined first. Further research can also
distancing the sub-conductors spacing in a bundle conductor, be done for channels with horizontal configurations.
increasing the number of sub-conductors and get closer the
phase distance in the transmission line. The most impactful REFFERENCES
way is to add the number of sub-conductors in a bundle [1] Kothari, D.P. Nagrath, I.J. Modern Power System Analysis 3th. Tata
conductor where the highest SIL level and highest DEPOK bus McGraw-Hill Education, New Dehli. 2011.
voltage occurs when the number of sub-conductors is [2] Taihan Electric Wire Co.Ltd. ”Overhead Electrical Alumunium
converted into 6 pieces with a 60 cm spacing. Conductors”.Seoul: Author
[3] R. N. Nayak, Y K Sehgal and Subir Sen,”EHV Transmission Line
Capacity Enhacement Through Incsrease in Surge Impedance
With this configuration, the bundle conductor GMR Loading Level”, Published in Transmission and Distribution
magnitude will increase. From Table 1, it can be seen that the Conference and Expansion, (2003 IEEE)
GMR formula for bundle conductor with the number of sub- [4] Varun Patel, J.G.Jamnani,”Technique to Increase Surge Impedance
conductors of 6 pieces has the greatest value. Whereas the sub- Loading level of EHV AC Transmission Lines for Improving
Power Transfer Capability”, Published in International Conference
conductors spacing is 60 cm, it will increase the bundle on Computation Power, Energy, Information and Communication
conductor GMR magnitude is compared with the 40 cm and 50 (2015 IEEE)
cm spacing. As know before, the farther the sub-conductors [5] Rafik, Houssem. (2009). Transmission and Distribution System.
spacing, the greater the conductor GMR magnitude. With this Mekkah: Umm Al-Qura Unversity.
[6] Midal Cable. Conductor Datasheet Aluminium Conductor Steel
configuration, the GMR magnitude is about 0.3861 m, and the Reinforced (ACSR). Bahrain: Author.
GMD magnitude is 19.75734 m. It was the same GMD as the [7] Sural. Product Catalog Aluminium Conductor Steel Reinforced
line with the initial configuration. (ACSR). Venezuela: Author.
[8] General Cable. ACSR Bare Overhead Conductor. Kentucky:
With the increased GMR magnitude, the inductance and Author
reactance values will decrease, and the capacitance and [9] M. T. Wikara, Studi Analisis Perecepatan Tahap I 10.000 MW,
Depok: Universitas Indonesia, 2008.
susceptance will increase. Moreover, the transmission line SIL [10] P.T.PLN (Persero) P3B Jawa Bali.”Topologi Konfigurasi Jaringan
magnitude and DEPOK bus voltage will be increased. With this P3B Jawa Bali 2015”.Jakarta.2015.
configuration, the SIL magnitude is 2429.4543MW, and the [11] D. Marsudi, Operasi Sistem Tenaga Listrik, Yogyakarta: Graha
DEPOK bus %voltage is 96.81%. Ilmu, 2006.
[12] P. P. (Persero), Buku Statistik PLN 2008-2014, Jakarta: PT. PLN
(Persero), 2014.
[13] W. S. Sawai, Studi Aliran Daya Sistem Jawa Bali 500 kV Tahun
2007-2011, Depok: Universitas Indonesia, 2008.

102

Authorized licensed use limited to: Cornell University Library. Downloaded on August 16,2020 at 04:40:03 UTC from IEEE Xplore. Restrictions apply.

You might also like