DATE CONTRACTOR NAME NATUR OF WORK NO OF WORKERS FLOOR DECRIPTION WORK OUTPUT

PIPING FULL WELDING FOR PIPE SUPPORTS 12 NOS


PIPING BASEMENT-4 SUPPORTS FABRICATION AND INSTALLATION 2 NOS
SRI PRASAD ENTERPRISES 7 NOS
PIPING MS PLATES FIXED 4 NOS
1/8/2023 PIPING SHAFT-3 SUPPORTS FIXING 12 NOS
FAIZA AIR SYSTEMS DUCTING 5 NOS BASEMENT-2 ELBOW ERECTION 6 NOS
TOTAL SOLUTIONS ELECTRICAL WORKS 3 NOS BASEMENT-3 CABLE TRAY ERECTION 55 METERS
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 6 NOS ALL FLOORS UNLOADING AND SHIFTING UNLOADING AND SHIFTING
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 4 NOS ALL FLOORS UNLOADING AND SHIFTING UNLOADING AND SHIFTING
TOTAL SOLUTIONS ELECTRICAL WORKS 3 NOS BASEMENT-2 CABLE TRAY ERECTION 55 METERS
2ND FLOOR MARKING & DRILING COMPETED
FAIZA AIR SYSTEMS DUCTING 5 NOS
BASEMENT-2 ELBOW&OFFSET ERECTION 2 &1
2/8/2023
REDUCER FABRICATION AND WELDING 2 NOS
BASEMENT-4
SRI PRASAD ENTERPRISES PIPING 7 NOS RED OXIDE PAINTING 12 NOS
SHAFT-3 SUPPORTS FIXING 12 NOS
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 2 NOS 4TH FLOOR AHU ASSEMBLED ZONE -3 ASSEMBLED
FAIZA AIR SYSTEMS DUCTING 5 NOS 2,3,4 FLOORS SUPPORTS DRILLING FOR DUCT COMPLETED EXCEPT TOILETS
MARKING,SUPPORTS DRILLING &CABLE TRAY
TOTAL SOLUTIONS ELECTRICAL WORKS 6 NOS BASEMENT-2 70 METERS
LAYING
3/8/2023 KEERTHANA ENTERPRISES UNLOADING& SHIFTING 8 NOS ALL FLOORS SHIFTING OF AHU FANS TO FLOORS 2 FANS TO 7TH FL & 3 FANS TO 4TH FL
SRI PRASAD ENTERPRISES PIPING 7 NOS BASEMENT-4 400 DIA PIPE LIFTED 60 METERS
4TH FLOOR ZONE-4 AHU SEMI-ASSEMBLED &2ND
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 2 NOS 2ND & 4TH 1 ZONE AHU SEMI ASSEMBLED &1 ZONE FAN INSTALLED
FLOOR AHU FAN INSTALLED
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 3 NOS ALL FLOORS VEHICLE UNLOADING UNLOADED ONE VEHICLE
4/8/2023 SRI PRASAD ENTERPRISES PIPING 3 NOS B4 FABRICATION OF 45 DEGREE L-BOW 6 NOS
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS B2 CABLE TRAY ERECTION 40 MTR
4TH FLOOR ZONE-4 AHU FULL ASSEMBLED 2ND
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 2 NOS 2ND & 4TH 1 ZONE ASSEMBLED & 1 ZONE SEMI ASSEMBLED
FLOOR ZONE-4 SEMI ASSEMBLED
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 6 NOS ALL FLOORS VEHICLE UNLOADING UNLOADED ONE VEHICLE
SRI PRASAD ENTERPRISES PIPING 4 NOS SHAFT-3 RISER PIPE ERECTION 12 MTR
5/8/2023 TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS B2 & B3 CABLE TRAY ERECTION B2-25 MTR & B-3 SUPPORTIND DONE 30 MTR
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 2 NOS 2ND FLOOR ZONE-3 SEMI ASSEMBLED & ZONE 4 ASSEMBLED 1 ZONE ASSEMBLED & 1 ZONE SEMI ASSEMBLED

FAIZA AIR SYSTEMS DUCTING 5 NOS 2ND & 3RD & 4TH THREADING RODS FIXING & DUCT INSTALLATION 152.625 SQM
6/8/2023
SRI PRASAD ENTERPRISES PIPING 5 NOS SHAFT-3 RISER PIPE ERECTION 24 METERS
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS BASEMENT-3 CABLE TRAY ERECTION 75 METERS
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS BASEMENT-3 CABLE TRAY ERECTION 60 MTRS
SRI PRASAD ENTERPRISES PIPING 5 NOS SHAFT-3 RISER PIPE ERECTION 38 MTRS
8/8/2023 KEERTHANA ENTERPRISES UNLOADING& SHIFTING 2 NOS ALL FLOORS VEHICLE UNLOADING ONE VEHICLE UNLOADED
FAIZA AIR SYSTEMS DUCTING 5 NOS 2ND DUCTING CONNECTIONS 2,3,4,5 COMPLETED
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 4 NOS 6TH &7TH AHU ASSEMBLING 2 ZONES SEMI ASEMBLED 6TH FLOOR Z-3 & 7TH FLOOR Z-4
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS B-3 CABLE TRAY ERECTION 40 MTR
9/8/2023 SRI PRASAD ENTERPRISES PIPING 5 NOS SHAFT-3 RISER PIPE ERECTION 16 MTRS
FAIZA AIR SYSTEMS DUCTING 6 NOS 2ND & 3TH DUCTING CONNECTIONS AND INSTALLATION 2ND & 3TH FLOOR TOILET COMPLETED
FAIZA AIR SYSTEMS DUCTING 5 NOS 3RD &4TH DUCTING CONNECTIONS AND INSTALLATION 3RD FLOOR 3 TOILETS COMPLETED AND 4TH FLOOR DRILING COMPLETED

45 DEGREE L-BOW FABRICATION AND 200 DIA 45 DEGREE 6 NOS FABRICATED AND CONNECTIONS 12M DONE AND PUFF
SRI PRASAD ENTERPRISES PIPING 5 NOS BASEMENT-4
CONNECTIONS AND PUFF SADDLE INSTALLATION SADDLE AND 400 DIA PIPE CONNECTIONS
10/8/2023
KANNAYYA 1 NO SHAFT-2 FABRICATION OF DUCTING SUPPORTS FOR SHAFT 22 NOS DONE
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 2 NOS ALL FLOORS UNLOADING OF VEHICLE ONE VEHICLE UNLOADED
TOTAL SOLUTIONS ELECTRICAL WORKS 6 NOS BASEMENT-3 CABLE TRAY ERECTION 50 M DONE
FAIZA AIR SYSTEMS DUCTING 3 NOS 3RD &4TH DUCTING CONNECTIONS AND INSTALLATION 3RD FLOOR TOILETS COMPLETED AND 4TH FLOOR TOILETS COMPLETED

KANNAYYA 1 NO SHAFT-2 FABRICATION OF DUCTING SUPPORTS FOR SHAFT 22 NOS DONE


11/8/2023

SRI PRASAD ENTERPRISES PIPING 4 NOS BASEMENT-4 PIPE SUPPORTS FABRICATION AND PIPE ERECTION 4 NOS COMPLETED
TOTAL SOLUTIONS ELECTRICAL WORKS 6 NOS BASEMENT-3 CABLE TRAY ERECTION 45 MTRS
SRI PRASAD ENTERPRISES PIPING 5 NOS CONDENSER SHAFT CONDENSER SHAFT SUPPORT FABRICATION 4 NOS
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 4 NOS ALL FLOORS VEHICLE UNLOADING ONE VEHICLE UNLOADED
12/8/2023
KANNAYYA 1 NO SHAFT-2 PAINTING FOR DUCTING SUPPORTS 44 NOS
TOTAL SOLUTIONS ELECTRICAL WORKS 6 NOS BASEMENT-3 CABLE TRAY ERECTION 50 MTRS
FAIZA AIR SYSTEMS DUCTING 4 NOS 2ND & 3RD DUCT ERECTION 24 MTRS
14/08/2023 TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS BASEMENT-3 CABLE TRAY ERECTION 40 MTRS
SRI PRASAD ENTERPRISES PIPING 5 NOS CONDENSER SHAFT SUPPORT FABRICATION 3 SUPPORTS
2ND FLOOR DUCT ERECTION &SUPPORTS DRILLING
FAIZA AIR SYSTEMS DUCTING 4 NOS 2ND & 5TH 2ND FLOOR CONNECTIONS AND 5TH FLOOR SUPPORTING WORK DONE
IN 5TH FLOOR
15/08/2023
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS BASEMENT-2 CABLE TRAY ERECTION 50 MTRS
SRI PRASAD ENTERPRISES PIPING 5 NOS SHAFT-3 SUPPORTS FIXING 9 NOS
SRI PRASAD ENTERPRISES PIPING 5 NOS SHAFT-3 RISER PIPE INSTALLTION 24 MTRS
16/08/2023 KEERTHANA ENTERPRISES UNLOADING& SHIFTING 3 NOS S-1 &S-2 VEHICLE UNLOADING 3 VEHICLES
FAIZA AIR SYSTEMS DUCTING 4 NOS 5 TH TOILET 24 MTRS
FAIZA AIR SYSTEMS DUCTING 5 NOS 6TH DUCTING CONNECTIONS FOR TOILET AND CORIIDOR CONECTIONS DONE
FABRICATION OF RISER PIPE SUPPORTS FOR SHAFT-
SRI PRASAD ENTERPRISES PIPING 4 NOS SHAFT-4 60 NOS
18/08/2023 4
TOTAL SOLUTIONS ELECTRICAL WORKS 3 NOS BASEMENT-4 CABLE TRAY MARKING IN BASEMENT-4 30 % COMPLETED
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 9 NOS ALL FLOORS SHIFTING OF AHU MATERIALS 4 FANS,15 COILS SHIFTED AND 1 TOP BOTTOM
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 2 NOS 4TH 4TH FLOOR ONE AHU ASSEMBLED 4TH ZONE-4 DONE
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 3 NOS 4TH FLOOR AHU ASSEMBLING 2 ZONES ASSEMBLED
FABRICATION OF RISER PIPE SUPPORTS FOR SHAFT-
SRI PRASAD ENTERPRISES PIPING 4 NOS SHAFT-4 30 NOS
4
19/08/2023
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 7 NOS ALL FLOORS SHIFTING OF AHU MATERIALS COILS 6 NOS AND TOP& BOTTOM 7 NOS
KANNAYYA 1 NO STP SHAFT STP DUCT SUPPORTS HOLES 33 NOS COMPLETED
FAIZA AIR SYSTEMS DUCTING 5 NOS STP SHAFT DUCT ERECTION B4 TO S2
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 5 NOS 6th,7TH &8TH AHU ASSEMBLING 6 AHUS ASSEMBLED
FULL WELDING FOR PIPE SUPPORTS & PIPE 5TH TO 8TH FLOOR FULL WEILDING DONE IN SHAFT 3 AND 24MTR 200DIA PIPE
SRI PRASAD ENTERPRISES PIPING 5 NOS B-4, 5TH TO 8TH
INSTALLATION INSTALLED IN B-4
21/08/2023
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 2 NOS S1 DUCTING UNLOADING 1 VEHICLE UNLOADING DONE
FAIZA AIR SYSTEMS DUCTING 13NOS STP SHAFT & 7TH DUCT ERECTING S2 TO 6TH FLOOR [ TOTAL 7 FLOOR] ERECTION DONE
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS B-4 DRILLING FOR CABLE TRAY SUPPORT 70% DRILLING DONE FOR CABLE TRAY SUPPORTS
FAIZA AIR SYSTEMS DUCTING 12 NOS 7TH FLOOR STP DUCT SHIFTED TO FLOORS SHIFTED TO 7TH & 8TH FLOOR
TOTAL SOLUTIONS ELECTRICAL WORKS 4 NOS BASEMENT-4 MARKING AND DRILLING FOR SUPPORTS 90% COMPLETED
22/08/2023
SRI PRASAD ENTERPRISES PIPING 5 NOS BASEMENT-4 PIPE LIFTED & FULL WELDING 12M PIPE LIFTED & B-4 TO 4TH FLOOR FULL WELDING COMPLETED
LUFTEK ENGINEERING PVT LTD AHU ASSEMBLING 5 NOS 6TH FLOOR & 7TH FLOOR 6TH FLOOR ZONE1,2 & 7TH FLOOR ZONE-2 3 ZONES ASSEMBLED
LUFTEK ENGINEERING PVT LTD ENGINEERING PVT LTD AHU ASSEMBLING 5 NOS 3th&7th AHU ASSEMBLING 2 AHUS ASSEMBLED
FULL WELDING FOR PIPE SUPPORTS & PIPE FULL WELDING IN HEADER LINE IN B-4 , 4 SUPPORTS INSTALLED & 12 MTRS PIPE
SRI PRASAD ENTERPRISES PIPING 5 NOS b-4
INSTALLATION INSTALLED
23/8/2023
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 3NOS S-2, B-4 & S1 PIPE UNLOADING & SHIFTING 1 VEHICLE UNLOADING DONE & SHIFTTED TO B-4
CORRIDOR DUCT INSTALLED IN 6TH FLOOR & Y PIECE INSTALLED FOR MOKE UP
FAIZA AIR SYSTEMS DUCTING 5NOS 6TH & 1ST DUCT ERECTING
IN 1ST FLOOR
LUFTEK ENGINEERING PVT LTD ENGINEERING PVT LTD AHU ASSEMBLING 5 NOS 5TH & 2ND AHU ASSEMBLING 5TH FLOOR ZONE 3 SEMI ASSEMBLED & MOTOR FIXED IN 2ND FLOOR ZONE 2
SRI PRASAD ENTERPRISES PIPING 4 NOS BASEMENT-4 PIPE SUPPORTS & FULL WELDING 2 SUPPORTS FIXED AND FULL WELDING DONE FOR 8 JOINTS
24/8/2024
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 7 NOS 9TH FLOOR SHIFTED FROM STILT-2 TO 5TH FLOOR 9TH FLOOR 5TH ZONE 3 TOP AND BOTTOM , 4FAN & 4 COIL SHIFTED TO 9TH FLOOR
CORRIDOR DUCT INSTALLED IN 7TH FLOOR & 50% DUCTING DONE IN CORRIDOR
FAIZA AIR SYSTEMS DUCTING 6 NOS 6th & 7th DUCTING INSTALLATION
8TH FLOOR
LUFTEK ENGINEERING PVT LTD ENGINEERING PVT LTD AHU ASSEMBLING 5 NOS 5TH FLOOR ZONE-2 AHU ASSEMBLED ONE ZONE FULLY ASSEMBLED
SRI PRASAD ENTERPRISES PIPING 10 NOS BASEMENT-4 BASE PLATES FIXING 24 NOS 200X200 DONE & 300X300 8 NOS DONE
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 3 NOS BASEMENT-1 UNLOADED ONE VEHICLE UNLOADED CABLE TRAY VEHICLE & 3 MOTORS SHIFTED
25/8/2024
FAIZA AIR SYSTEMS DUCTING 7 NOS 8TH & 9TH DUCT ERECTION 8TH FLOOR 50% CORRIDOR COMPLETED & 9TH FLOOR CORRIDOR COMPLETED
TOTAL SOLUTIONS ELECTRICAL WORKS 3 NOS BASEMENT-4 SUPPORTING WORKS 15% SUPPORING COMPLTED
LUFTEK ENGINEERING PVT LTD ENGINEERING PVT LTD AHU ASSEMBLING 5 NOS 3th & 7th AHU MOTOR & FAN PULLY FIXING 7th floor zone-4 AHU MOTOR FIXED & 3TH FLOOT ZONE 2 FAN PULLY FIXED
SRI PRASAD ENTERPRISES PIPING 5NOS b-4 PIPE BRANCH TAPPING IN MAIN HEADER 200 DIA PIPE BRANCH TAPPING DONE IN MAIN HEADER
26/08/2023
CORRIDOR DUCTING INSTALLED IN 9TH FLOOR & 10TH FLOOR AND IN 11TH
FAIZA AIR SYSTEMS DUCTING 10 NOS 9th,10th&11 DUCT ERECTION
FLOOR CORRIDOR DUCTING CONNECTION DONE
TOTAL SOLUTIONS ELECTRICAL WORKS 3 NOS b-4 CABLE TRAY SUPPORTING WORKS 30% SUPPORTING DONE IN B-4
4 NOS SUPPORTING INSTALLED IN B-4 & B-4 TO S-3 SUPPORTING DONE IN SHAFT -
SRI PRASAD ENTERPRISES PIPING 8 NOS b-4 & shaft-4 SUPPORTING WORKS
4
KEERTHANA ENTERPRISES UNLOADING& SHIFTING 2 NOS ALL FLOORS HOUSE KEEPING FOR FLOORS 2ND FLOOR TO 8TH FLOOR HOUSE KEEPING COMPLETED
28/08/2023 11TH FLOOR CORIDOR DUCTING ERECTED & 6TH FLOOR TOILET DUCTING
FAIZA AIR SYSTEMS DUCTING 6 NOS 6TH &11TH DUCT ERECTION & CONNECTIONS
CONNECTION DONE
30MTR CABLE TRAY INSTALLED & TILL DATE 300 MTR CABLE TRAY INSTALLED IN B-
TOTAL SOLUTIONS ELECTRICAL WORKS 3 NOS b-4 CABLE TRAY ERECTION
4
SRI PRASAD ENTERPRISES PIPING 8 NOS SHAFT-4 B=4 TO STILT-1 SUPORTING WORK 15 SUPPORTS INSTALLED AND 200 DIA PIPE SHIFTED NEAR SHAFT-4
29/08/2024
FAIZA AIR SYSTEMS DUCTING 7 NOS 8,9,10 DUCT CONNECTIONS 3 FLOORS DUCT CONNECTIONS OF TOILETS DONE
SRI PRASAD ENTERPRISES PIPING 6 NOS B-4&SHAFT-4 PIPE INSTALLATION 12 MTR PIPE INSTALLED IN SHAFT -4 & 2 NOS 400 DIA ELBOWS FABRICATED
31/08/23
1 PLENIUM INSTALLED IN B-2 , 6TH & 7TH FLOOR TOILED DUCT INSTALLED IN
FAIZA AIR SYSTEMS DUCTING 6nos B2,6TH & 7TH DUCT ERECTION & CONNECTIONS
BOTH SIDE