You are on page 1of 10

Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Permit to Work System Process Maps


Any work to be performed at an SOI Developing Assets location follows the Permit to Work Process. Depending upon the
size and complexity of the job, various levels of permitting, planning, approval and documentation are required. The high-
level process on this page describes the overall process of job planning and execution. Each subsequent page describes in
more detail the sub-processes. These process maps were prepared by the team that developed the Permit to Work document
and are included as an extra tool to be used for PTW System implementation and training.

Job Definition Pre-Job Approval Initiate Work Execute Work Closeout


Planning Work

Approved: February 10, 2000 - (Rev. 1.0) Page 1 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Job Definition Phase


waiver

Allowable Safe Work Plan


Identify job task to Y Safe Work Plan Process
in Required?
Y
(Sec. 2.0)
be performed SIMOPS? (Sec. 2.2)
(Sec. 4.0)

N
Determine if lockout/
tagout (Sec. 5.2) or
N
confined space entry
(Sec. 6.0) is needed

Safe Work Permit (Sec. 3.0) Safe Work


Y
and preliminary JSA Permit
(Attachment L) reviewed by Required?
PIC (Sec. 3.3)

Conduct Work per Start-Up Start-up Permit


Standard Procedure or Permit Y
JSA or PIC's Needed?
Process
(Attachment L/M) (Sec. 7.3) (Sec. 7.0)

N
Inspect work area
and close out
permit

Approved: February 10, 2000 - (Rev. 1.0) Page 2 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Safe Work Plan Process


Pre-Job Planning Approval Initiate Work Execute Work Closeout Work
1. Review Applicable HSE 1. Conduct Preliminary 1. Put HSE Controls in 1. Maintain HSE Controls 1. Remove HSE Controls
Guidance as needed Walkdowns with Opns Place:
Team Leaders, OIM, - site access
Construction Focal Point – LO/TO
and Contractor Leads – Confined Space
– Permit Posting
- Other
2. Conduct Planning 2. Review all permits and 2. Establish 2. If work must be stopped 2. Closeout Permits
meetings with site plans for completeness. Communications before completed, make
management, (LO/TO, Confined Space the work site safe,
contractors, and other Entry attached if needed) closeout permits and
involved parties repermit to complete.
3. Conduct POB planning 3. Brief platform staff on 3. Conduct Tailgate safety 3. When shift and crew 3. Critique the job and
considering all ongoing work activities. meeting changes occur follow the provide feedback to
activities requirements for permit
renewal.
4. Assure all personnel 4. Validate readiness of 4. Final walkdown 4. If scope change occurs, 4. Initiate Startup Plan
have adequate training. Shell staff. initiate MOC and return
to Job Definition
5. Conduct job-specific 5. Validate readiness of 5. 5. Conduct daily 5.
orientation/training for Contract staff. communications and
contract and Shell staff permitting process
6. Review SIMOPs 6. Receive final approval 6. 6. 6.
Requirements from site coordinating
committee, construction
supvsr and Asset Leader.
7. Prepare Documentation: 7. Verify POB 7. 7. 7.
- Safe Work Plan
- Applicable Permits
– Communications Plan
– Start-up Plan
8. Inform Platform Staff of 8. 8. 8. 8.
upcoming work

Approved: February 10, 2000 - (Rev. 1.0) Page 3 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

9. Obtain Regulatory 9. 9. 9. 9.
Approvals

Approved: February 10, 2000 - (Rev. 1.0) Page 4 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Safe Work Permit Process


Pre-Job Planning Approval Initiate Work Execute Work Closeout Work
1. Employee/Contractor 1. Originator and/or Sponsor 1. Conduct a pre-job safety 1. Do the work. Contractor 1. Finish Work and Assure
group recognizes a non- brings Safe Work Permit meeting and for more supervisor or other work the work area is returned
routine job (See list Sec. to Coordinating complex jobs, the entire supervisor is responsible to it’s original condition.
3.3) that will require a Committee Meeting group walks through the for assuring permit Originator performs final
permit to be done. job prior to beginning requirements are met. work site inspection.
work.
2. Responsible team is 2. Presents the Safe Work 2. If applicable, LO/TO 2. Perform a walk through 2. Sign and date the
contacted and a job Permit to the committee equipment per the and Behavior Based completed section of the
sponsor is assigned. for review and approval. LO/TO process. observation as work is safe work permit.
OIM or Sponsor reads the done. In the event of an
permit to the committee accident, the work permit
and asks for comments, must be completed in the
changes, agreement incident documentation
section and closed and
turned into the control
room
3. Permit Originator 3. Committee screens for 3. Assure that all corrections 3. Sponsor and/or OIM/PIC 3. Turn the completed permit
develops a pre-job safety conflicting work using noted on PICS/JSA and periodically monitor site into the control room for
plan for the work (PICS or SIMOPs matrix. worst events on the safe to assure HSE measures records and remove copy
JSA) work permit are are implemented. from control room board.
addressed.
4. Originator fills out a safe 4. Comments discussed, 4. .Sponsor confirms that all 4. At shift changes, the 4. If a LO/TO accompanies a
work permit. changes made, agreement involved personnel are permit must be renewed safe work permit and
- Describes the job to be by all, each team leader familiar with permit and or reissued. LO/TO has been removed,
done. signs concurring that the job requirements and have remove LO/TO from
- Denotes time and day work can be done, and received Orientation 5. When OIM/PIC crew board and file.
work will begin. then the OIM signs off training. changes occur, the new
- Recognizes the worst giving approval for work OIM/PIC must review all
events associated with the to begin. permitted jobs and sign to
job. indicate concurrence with
- Develops and documents ongoing work.
preventive measures for
the worst events..
- Develops a lock-out tag-
out form if needed.

Approved: February 10, 2000 - (Rev. 1.0) Page 5 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Safe Work Permit Process (continued)

Pre-Job Planning Approval Initiate Work Execute Work Closeout Work


5. Originator walks through 5. A copy of the permit is Team Leader / Opns
the job site with sponsor, made and hung on a supervisor or Sponsor
work is described, permit board in the control room conducts safety inspection
is discussed, sponsor for communication to all. prior to starting work
agrees/disagrees (if Original is maintained by
disagrees, corrections the person that does the
made), and sponsor signs work.
off that work can be
permitted.
6. Originator provides the 6. In the event of an
safe work permit, LO/TO incident, develop a new
form, and PICS to safe work permit, walk it
Sponsor for presentation to each team leader for
at the Coord. Comm. signature, and obtain
Mtg. Each day at 5 PM. OIM approval
7. If hot work is involved 8. Work permits can be
follow special “Hot extended for three (3)
Work Permit” days if all requirements
requirements Sec. 3.6. for renewal are met. If
Coord. comm. members
all agree, all team leaders
sign and the OIM signs
for approval.

Approved: February 10, 2000 - (Rev. 1.0) Page 6 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

LockOut / TagOut Process


Pre-Job Planning Approval Initiate Work Execute Work Closeout Work
1. Identify Energy or 1. OIM, TL, review larger 1. LO/TO completed, all 1. All involved review 1. Designated Authorized
hazard type (electrical, jobs requiring Safe Work involved initial, LO/TO insures stored Person or Alternate
hydraulic, gas, etc) Permit/Plan Authorized Person Signs energy released or notifies all involved
@ job site. blocked individuals working on
job reach agreement on
completion
2. Individual or Team 2. Designated Authorized 2. 3 Carbon Copy form 2. Completes work 2. LO/TO removed by
sponsored depending on Person or Alternate utilized, Authorized activities Designated Authorized
job complexity or size insure job is safe Person post Copy Central Person only
Posting area & Control
Room, retains original @
job site
3. Complex or Large jobs 3. All Craft and or Crafts 3. Craft Lock or locks used 3. 3. Closeout and file per
requiring Safe Work required to initial when multiple crafts local procedures (meet
Permits/Plans with condition verification @ working on job, different Shell retention
LO/TO require OIM, TL job site crafts are not keyed same requirements)
involvement (Confined
Space Entry)
4. Locks &Tags required 4. Designated Authorized 4. Individual personal locks 4. 4. Job Task LO/TO not
Craft locks required for Person Communicates to used for jobs performed complete remain on
more than one craft effected work groups and by fewer people of same boards
involvement, color coded area owners craft
5. I.D. resources, drawings, 5. 5. Process Control Locks, 5. 5. If LO/TO active when
manuals, subject experts used for critical process Designated Authorized
controls (relief valve Person leaves TLP
locked open) Alternate is assigned
6. Designated Authorized 6. 6. Only platform operating 6. 6. If LO/TO to remain for
Person (job leader) personnel can reposition extended period an
completes form, ID if process valves / explanation must be
Safe Work Permit/Plan equipment settings. written on posted copies
needed
7. Alternate Authorized 7. 7. Test to get positive 7. 7.
Person assigned if shift assurance that energy
or crew change source is isolated

Approved: February 10, 2000 - (Rev. 1.0) Page 7 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Confined Space Entry Process


Pre-Job Planning Approval Initiate Work Execute Work Closeout Work
1. All other practical 1. Safe work plan 1. PIC of work site ensure 1. support team stand-by 1. Entry supervisor
alternatives to confined approved? conditions of permit are 2. maintain log performs post entry
space entry considered Safe work permit met and maintained. 3. maintain contact review of procedure and
approved? Maintain a copy of the maintain communication problems encountered
Confined Space Entry permit at the work site. with Control Room
Permit approved
Confined Space Entry
Check List approved
2. Training provided. . . 2. Plan to address H2S 2. Support Team – Establish 4. Support Team – protect 2. Entry supervisor files a
Initial and annual approval if needed log of entries, establish air supply. record of the CSE
refresher & records signals.
available

3. Supervisory Experience 3. Verify qualified and 3. Complete Pre-Entry 5. Support Team monitors 3. Maintain a complete set
and overall work authorized supervision is preparations: work space on a regular of CSE records and any
experience considered in provided - isolate the space basis and after every associated incidents.
assigning “Competent (LO/TO) break or work stoppage.
Person” to supervise – Clean and ventilate
entry. – Test and monitor
– Assemble reqd equip.
– Establish access/egress
4. Entry Supervisor – insure 4. Competent person – 6. Support team is always 4. Ensure that inspection
proper documentation atmosphere tested just ready with rescue and maintenance results
including approved Safe prior to entry, recorded on equipment and plan. are documented.
Work Plan and Permit entry permit and a second
record kept of all results.
Certified “gas free”

5. Entry supervisor verify 5. All hazards safeguarded 7. OIM / PIC postpone all 5. Consider need for a Start
contractor personnel are against. drills and any interfering Up Permit
familiar with Shell’s work while CSE is being
policy and qualified. performed.

Approved: February 10, 2000 - (Rev. 1.0) Page 8 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Confined Space Entry Process (continued)

Pre-Job Planning Approval Initiate Work Execute Work Closeout Work


6. ID Support Team 8. In the event of a
members and include in temporary work
the CSE safe work plan. stoppage, take
precautions to prevent
unauthorized entry.

7. Complete CSE Checklist.


Analyze all hazards,
check MSDS sheets.
Contact HS&E if
conditions of entry
uncertain.

8. Leadership team and


CSE entry team assure
job-specific safeguards
are determined and
established.

Approved: February 10, 2000 - (Rev. 1.0) Page 9 of 10


Permit to Work System - Offshore Operations (SWAS Process Improvement Effort) SEPCo - HSE0008A - Appendix K

Start-up Permit Process


Pre-Job Planning Approval Initiate Work Execute Work Closeout Work
1. ID a need to start-up 1. Team Leader / Opns 1. Team Leader / Opns 1. Originator places permit 1. Originator closes permit
Large Complex Supvr - Inspect Supvr – check equipment on activity board with
equipment equipment condition for and condition the appropriate work
start-up permit
2. ID a need for special 2. OIM/PIC - Approve SU 2. Tail gate meeting to 2. Copy provided to the 2. Safe work permit not
procedures for start-up permit discuss specific control room or central closed until start-up
procedures and posting area. permit is complete
precautions
3. ID where 2 or more 3. Do the work
contractors are involved
in a start-up of
equipment

4. Originator – can be any


employee that is in
charge of the equipment
5. OIM / PIC or Team
Leader / Opns Supvr is
responsible to determine
if SU permit is necessary
6. Check SIMOPs Matrix,
Determine Influences on
other systems
7. Originator meets with
contractor or other
affected personnel
8. Inspect / review work
site and equipment
9. Check outstanding
permits. Hot work not
permited during start up
without OIM/PIC
approval.

Approved: February 10, 2000 - (Rev. 1.0) Page 10 of 10

You might also like