The document provides a daily work program for 29 June 2022 for the Karnaphuli Tunnel Project. It lists 29 tasks across various locations including concrete works, brick works, shutter fitting, plastering, and rebar fabrication. The tasks require a total of approximately 260 cubic meters of concrete, 1900 square meters of shuttering, 27,000 kg of rebar, and 350 cubic feet of bricks. The largest concrete pour is an abutment pile cap requiring 168 cubic meters.
The document provides a daily work program for 29 June 2022 for the Karnaphuli Tunnel Project. It lists 29 tasks across various locations including concrete works, brick works, shutter fitting, plastering, and rebar fabrication. The tasks require a total of approximately 260 cubic meters of concrete, 1900 square meters of shuttering, 27,000 kg of rebar, and 350 cubic feet of bricks. The largest concrete pour is an abutment pile cap requiring 168 cubic meters.
The document provides a daily work program for 29 June 2022 for the Karnaphuli Tunnel Project. It lists 29 tasks across various locations including concrete works, brick works, shutter fitting, plastering, and rebar fabrication. The tasks require a total of approximately 260 cubic meters of concrete, 1900 square meters of shuttering, 27,000 kg of rebar, and 350 cubic feet of bricks. The largest concrete pour is an abutment pile cap requiring 168 cubic meters.
Daily Work Program for 29.06.2022 SL Description of Works Location Material Requirement Remarks No Concrete = 4.75 cum. Brick works,Stair roof top slab ready for shutter = 13.46 sqm 1 castings. Bungalow -1 Beam shuttering = 15.97 sqm. Re bar = 713.67 kg. 2 Brick works,False slab Lintel rebar work Bungalow -2 Concrete =10.10 cum Floor slab ( 2700 mm) R.C C. Concrete. Shuttering =2.5 sqm. 3 casting Bungalow -3 Re bar = 788.89 kg. BFS = 160.67 sqm. Poly = 160.67 sqm. 4 Brick works Bungalow -4 5 Stair case column shuttering works.. Bungalow -5 Deck slab(L-2850& 2550 mm) brick works, 6 Bungalow -6 Roof tiles work and Floor brick works.. 7 Roof tiles fittings and brick work.. Bungalow -7 Concrete = 2.00 cum. 8 Stair case ready for Casting. Bungalow -8 Shuttering= 17.00 sqm. Re bar = 126.78 kg 9 Brick works.. Bungalow -9 10 brick masonry curing works... Bungalow No-10 11 Brick masonary works... Bungalow No-11 12 Shutter fitting works for flat slab... Bungalow No-12 13 Ceiling plaster works... Bungalow No-13 Pitch slab rebar fabrication works 14 Bungalow No-14 completed and waiting for electric conduit... 15 Brick masonry works... Bungalow No-15 16 Brick masonry works… Bungalow No-16 17 ceiling plaster works… Bungalow No-17 . Concrete =1.55 cum, 18 Column casting works Bungalow No-18 shutter = 17.12 sqm, rebar =193 kg 19 Scaffolding fitting works for flat slab... Bungalow No-19 20 Ceiling plaster curing works... Bungalow No-20 Concrete =6.25 cum, 21 Porch slab casting works.. Bungalow No-21 shutter = 55.10 sqm, rebar =830 kg. 22 ceiling plaster works.... Bungalow No-22 23 Sand compaction works.. Bungalow No-23 24 Pile cap rebar fabrication works… Bungalow No-24 25 Main slab ( L-6.6 m) & pitch slab curing Bungalow No-25 26 Main slab curing... Works.. Bungalow No-28 27 Main slab curing Bungalow No-26 Concrete =2.64 cum. 28 Main column ready for casting. Bungalow No-27 Shutter = 28.16 sqm. Re bar =316.17 kg. Concrete = 1.24 cum. 29 Main column ready for casting. Bungalow No-29 Shuttering=3.39 sqn. Re bar= 54.13 kg. Abdul Monem Ltd. Karnaphuli Tunnel Project Daily Work Program for 29.06.2022 SL Description of Works Location Material Requirement Remarks No Concrete =12.5 cum. Shuttering =65.44 sqm Re bar = 2288.26 kg Grade beam (L-1.1 m) and Porch slab ( L- 30 Bungalow No-30 Porch slab ( L-3.6 m) 3.6 m) ready to casting. Concrete = 6.25 cum. Shuttering = 53.23 sqm Re bar=832.17 kg... concrete= 3 cum 31 10 Main column casting Mosque shutter=24sqm rebar= 650 kg Concrete= 0.6 cum 2 nos Main column shuttering and casting 32 Museum formwork= 5.7 sqm Brick work (gb to gr floor) rebar= 135 kg Roof beam Rebar fabrication at level 33 Health Centre +_3378 and above+3600 34 Grade beam rebar fabrication VIP Bungalow Concrete =0.75 cum, 35 Column casting works.. Resort reception shutter = 4.10 sqm, rebar qty =54 kg 1. Base and wall shutting work. Pit no: 18 to 17, Length: 15m 36 North side Drain Concrete = 3.9 cum 2. Base casting,Pit no: 18 to 17, Length: 20m 1. Wall casting.Pit no: 24 to end pointv Length: 40m 2. Base casting. Pit no: 24 to 23, Length: 37 Drain south Concrete = 17.46 cum 20m 3. Chute drain wall casting, Length: 4m Pit no: 24 1.Abutment pile cap concreting work (sea side)-168 cum Abutment pile cap 2.Dewatering work in abutment pile cap 38 Bridge -1 concreting work-168 (County side) cum 3. Abutment pile cap outside Brick wall making work 1.Pier column reinforcement work (sea 39 side) Bridge -2 2. Wing wall binder rebar fabrication work Main road drain, 40 pit 536,537,538,539,540,541brick wall work Road is on going Swimming Pool pile casting 04 nos, 20 nos Casting qty= 6.62 cum 41 Pre cast pile Pile driving at Motel mess Rebar qty= 1.25 Tonne Abdul Monem Ltd. Design and Construction of the East Bank Service Facility under the Multi Lane Karnaphuli Tunnel Project Urgent Requireemt Materials requirement for Program Work Coarse Coarse Fine Aggregate SI No Location Unit Quantity Cement (Kg) AggregateStone Admixer (Kg) Aggregate Rebar (kg) (cft) (Kg) Bricks(cft) Brick works,Stair roof top slab 1 Cum 4.75 1852.5 5206 90.44 18.53 713 ready for castings at Bungalow-1 Floor slab ( 2700 mm) R.C C. 2 Cum 10.10 3939 11069.6 192.30 39.39 789 Concrete. casting at bungalow-3 Stair case ready for Casting at 3 Cum 2.00 780 2192 38.08 7.8 127 bungalow-8 4 column casting at Bungalow-18 Cum 1.55 604.5 1698.8 29.51 6.05 193 5 column casting at Bungalow-27 Cum 2.64 1029.6 2893.44 50.27 10.30 316 6 column casting at Bungalow-29 Cum 1.24 483.6 1359.04 23.61 4.84 54.13 Grade beam and porch slab casting 7 Cum 18.75 7312.5 20550 357.00 73.13 3120 at Bungalow-30 8 column casting casting at Mosque Cum 3.00 1170 3288 57.12 11.70 650 short column casting at resort 9 Cum 0.75 292.5 822 14.28 2.925 54 reception 10 column casting at museum Cum 0.60 234 657.6 11.42 2.34 135 Abutment pile cap concreting work 11 Cum 168.00 65520 184128 3198.72 655.20 29680 (County side)=180 cum at Bridge 2 porchslab castingcasting at 12 Cum 6.25 2437.5 6850 119 24.38 830 Bungalow-21 20 m base casting at North side 13 and 20 m base, 40 m wall and 4 m cum 21.36 6835.2 469.92 3280.90 528 chut wall casting at south side drain Swimming pool 09 nos PC Pile 14 cum 14.88 6249.6 16055.52 269.92 62.50 2810 casting Grand total Cum 255.87 98740.50 256770.00 4921.60 4199.95 528.00 39471.13