Abdul Monem Ltd.

Karnaphuli Tunnel Project


Daily Work Program for 29.06.2022
SL
Description of Works Location Material Requirement Remarks
No
Concrete = 4.75 cum.
Brick works,Stair roof top slab ready for shutter = 13.46 sqm
1 castings. Bungalow -1 Beam shuttering =
15.97 sqm.
Re bar = 713.67 kg.
2 Brick works,False slab Lintel rebar work Bungalow -2
Concrete =10.10 cum
Floor slab ( 2700 mm) R.C C. Concrete. Shuttering =2.5 sqm.
3 casting Bungalow -3 Re bar = 788.89 kg.
BFS = 160.67 sqm.
Poly = 160.67 sqm.
4 Brick works Bungalow -4
5 Stair case column shuttering works.. Bungalow -5
Deck slab(L-2850& 2550 mm) brick works,
6 Bungalow -6
Roof tiles work and Floor brick works..
7 Roof tiles fittings and brick work.. Bungalow -7
Concrete = 2.00 cum.
8 Stair case ready for Casting. Bungalow -8 Shuttering= 17.00 sqm.
Re bar = 126.78 kg
9 Brick works.. Bungalow -9
10 brick masonry curing works... Bungalow No-10
11 Brick masonary works... Bungalow No-11
12 Shutter fitting works for flat slab... Bungalow No-12
13 Ceiling plaster works... Bungalow No-13
Pitch slab rebar fabrication works
14 Bungalow No-14
completed and waiting for electric conduit...
15 Brick masonry works... Bungalow No-15
16 Brick masonry works… Bungalow No-16
17 ceiling plaster works… Bungalow No-17 .
Concrete =1.55 cum,
18 Column casting works Bungalow No-18 shutter = 17.12 sqm,
rebar =193 kg
19 Scaffolding fitting works for flat slab... Bungalow No-19
20 Ceiling plaster curing works... Bungalow No-20
Concrete =6.25 cum,
21 Porch slab casting works.. Bungalow No-21 shutter = 55.10 sqm,
rebar =830 kg.
22 ceiling plaster works.... Bungalow No-22
23 Sand compaction works.. Bungalow No-23
24 Pile cap rebar fabrication works… Bungalow No-24
25 Main slab ( L-6.6 m) & pitch slab curing Bungalow No-25
26 Main slab curing... Works.. Bungalow No-28
27 Main slab curing Bungalow No-26
Concrete =2.64 cum.
28 Main column ready for casting. Bungalow No-27 Shutter = 28.16 sqm.
Re bar =316.17 kg.
Concrete = 1.24 cum.
29 Main column ready for casting. Bungalow No-29 Shuttering=3.39 sqn.
Re bar= 54.13 kg.
Abdul Monem Ltd.
Karnaphuli Tunnel Project
Daily Work Program for 29.06.2022
SL
Description of Works Location Material Requirement Remarks
No
Concrete =12.5 cum.
Shuttering =65.44 sqm
Re bar = 2288.26 kg
Grade beam (L-1.1 m) and Porch slab ( L-
30 Bungalow No-30 Porch slab ( L-3.6 m)
3.6 m) ready to casting.
Concrete = 6.25 cum.
Shuttering = 53.23 sqm
Re bar=832.17 kg...
concrete= 3 cum
31 10 Main column casting Mosque shutter=24sqm
rebar= 650 kg
Concrete= 0.6 cum
2 nos Main column shuttering and casting
32 Museum formwork= 5.7 sqm
Brick work (gb to gr floor)
rebar= 135 kg
Roof beam Rebar fabrication at level
33 Health Centre
+_3378 and above+3600
34 Grade beam rebar fabrication VIP Bungalow
Concrete =0.75 cum,
35 Column casting works.. Resort reception shutter = 4.10 sqm,
rebar qty =54 kg
1. Base and wall shutting work. Pit no: 18 to
17, Length: 15m
36 North side Drain Concrete = 3.9 cum
2. Base casting,Pit no: 18 to 17, Length:
20m
1. Wall casting.Pit no: 24 to end pointv
Length: 40m
2. Base casting. Pit no: 24 to 23, Length:
37 Drain south Concrete = 17.46 cum
20m
3. Chute drain wall casting, Length: 4m
Pit no: 24
1.Abutment pile cap concreting work (sea
side)-168 cum
Abutment pile cap
2.Dewatering work in abutment pile cap
38 Bridge -1 concreting work-168
(County side)
cum
3. Abutment pile cap outside Brick wall
making work
1.Pier column reinforcement work (sea
39 side) Bridge -2
2. Wing wall binder rebar fabrication work
Main road drain,
40 pit 536,537,538,539,540,541brick wall work Road
is on going
Swimming Pool pile casting 04 nos, 20 nos Casting qty= 6.62 cum
41 Pre cast pile
Pile driving at Motel mess Rebar qty= 1.25 Tonne
Abdul Monem Ltd.
Design and Construction of the East Bank Service Facility under the Multi Lane Karnaphuli Tunnel Project
Urgent Requireemt
Materials requirement for Program Work
Coarse Coarse
Fine Aggregate
SI No Location Unit Quantity Cement (Kg) AggregateStone Admixer (Kg) Aggregate Rebar (kg)
(cft)
(Kg) Bricks(cft)
Brick works,Stair roof top slab
1 Cum 4.75 1852.5 5206 90.44 18.53 713
ready for castings at Bungalow-1
Floor slab ( 2700 mm) R.C C.
2 Cum 10.10 3939 11069.6 192.30 39.39 789
Concrete. casting at bungalow-3
Stair case ready for Casting at
3 Cum 2.00 780 2192 38.08 7.8 127
bungalow-8
4 column casting at Bungalow-18 Cum 1.55 604.5 1698.8 29.51 6.05 193
5 column casting at Bungalow-27 Cum 2.64 1029.6 2893.44 50.27 10.30 316
6 column casting at Bungalow-29 Cum 1.24 483.6 1359.04 23.61 4.84 54.13
Grade beam and porch slab casting
7 Cum 18.75 7312.5 20550 357.00 73.13 3120
at Bungalow-30
8 column casting casting at Mosque Cum 3.00 1170 3288 57.12 11.70 650
short column casting at resort
9 Cum 0.75 292.5 822 14.28 2.925 54
reception
10 column casting at museum Cum 0.60 234 657.6 11.42 2.34 135
Abutment pile cap concreting work
11 Cum 168.00 65520 184128 3198.72 655.20 29680
(County side)=180 cum at Bridge 2
porchslab castingcasting at
12 Cum 6.25 2437.5 6850 119 24.38 830
Bungalow-21
20 m base casting at North side
13 and 20 m base, 40 m wall and 4 m cum 21.36 6835.2 469.92 3280.90 528
chut wall casting at south side drain
Swimming pool 09 nos PC Pile
14 cum 14.88 6249.6 16055.52 269.92 62.50 2810
casting
Grand total Cum 255.87 98740.50 256770.00 4921.60 4199.95 528.00 39471.13