Professional Documents
Culture Documents
08/17/2023
North Eastern Region.
INTRODUCTION
A meeting was constituted on this date between 0900hrs – 1330hrs with the following members.
Members;
The deliberations were made, and proposals put across towards reduction of distribution
transformer failures. Moreover, need to expedite the same to reduce/mitigate the losses.
NOTES
Technically, the known causes were categorized into various factors depending on the aspects
involved.
1. Voltages
- High Voltage (HV) and Low Voltage (LV) earthing integrity.
o Inadequate, poorly done or vandalized earthing conductor.
o Poor earth resistance values (> 20Ω for LV and > 10Ω for HV). Should be less than.
o The PME (Permanent Multiple Earth) missing, vandalized or with poor earth
resistance values.
- Lack of surge diverters, and arcing horns.
- Terminal TX installation lacking properly earthed surge arrester.
- Long Medium Voltage (MV = 11 or 33kV) lines causes high receiving end voltages.
2. Currents
- Improvised or inadequate HV and LV fuse grading. Ought to adhere to the correct fuse
current rating depending on the TX full load current rating.
- LV phase balancing and loading.
- Clashing or twisted conductors of LV phases.
- Trees on wayleave trace. Prompt trace maintenance to be adhered to.
Page 1|3
TRANSFORMER FAILURE REDUCTION TARGET,
08/17/2023
North Eastern Region.
3. Workmanship
- Lack of the right tools for the job.
o Cable lugs ought to be properly sized and secured using a crimping tool. Avoid use of
pliers and binding wire for connection of conductor to the TX HV and LV termination
rods.
o Lack of use of equipments; voltmeters, ammeters, insulation resistance and earth
resistance meters for the measurement of the various guiding parameters to confirm
sanity and integrity of the substation.
o Lack of adherence to TX handling policy.
It was passed as policy that only a supervisor ought to pick the TX from stores, do
primary tests (continuity and insulation) in stores and test also after reaching site
before installation.
o Poor dressing of HV & LV conductors at the Substation.
o Poor tensioning of the LV conductors. This leads to poor sagging, thus causes
clashing and twisted conductors.
4. Materials
- Lack of availability of materials in stores.
- Lack of availability of funds.
- Compromised or poor Quality of materials available. User dept. ought to be thoroughly
engage in the procurement and acceptance processes.
5. Vandalism
- Known measures are already in use to mitigate this. Further addition action needed for
the activities.
o Actions including, securing the TX on the H-pole, HV Ring fencing, Customer
awareness through media against vandalism.
Page 2|3
TRANSFORMER FAILURE REDUCTION TARGET,
08/17/2023
North Eastern Region.
County O&M Eng. offices to form dedicated substation team headed by a supervisor or
experienced union staff. The said team would only focus on this target with the activities
mentioned here below.
Proposal is to have each depot with such a team. It was noted that currently 3No. Depots
have; Thika, Kiambu and Ruiru. The model is to be replicated to the other depots; Gatundu,
Githunguri, Limuru and Kikuyu who majorly rely on the main team.
- It was further noted that the depots without such a dedicated substation team had
significantly a majority of the tx failures in comparison with the depots that have a team.
It was agreed the teams to tackle the task, prioritizing on the most problematic SSs and
move sequentially to eventually achieve reinstatement of as many of these substations as
possible.
The Corrective Maintenance and Routine Activities in each of the substations would be;
- Correct cable / conductor terminations; ensure proper lagging
- Check and correct HV and LV earthing integrity; wiring and earth resistance values.
- Check and correct HV and LV fuse connections and current ratings.
- Check and correct Phase Balancing and Loadings (per phase and total TX loading)
- Correct TX Cable/conductor substation dressing.
- The Substation team is to liaise and get information from KYN teams.
- Notify Mains team in case of visible poor sagging for action.
- Notify and work with Electrical Plant team in cases requiring specialized expertise and
assistance in corrective maintenance of the TX.
- O&M Eng. to facilitate system reinforcement schemes where needed.
- O&M and Technical Services to facilitate training where needed.
- The team to ensure proper documentation on corrections and recommissioning.
In light of these activities, it was seen inevitable that the team would need a dedicated KPLC
fleet vehicle and a dedicated hiab for the county for this purpose.
C. FURTHER
Page 3|3