You are on page 1of 17

Inspection Release Certificate

Refinery Development Master Plan (RDMP) Project

RDMP-26071-100-POA-JF04-
IRC Number Date of Issue 14th March, 2023
00001-IRC-0012

Refinery Development Master


Project Name Vendor Name SAMIL
Plan (RDMP) Project

PO Number 26071-100-POA-JF04-00001 PO Description Flow Element

Item Number Item Description Quantity Remarks

- Flow Element 2,082EA


Refer to the
Packing List
(2 Package)

Total: 2,082 EA

Total Partial

Condition

No remaining(open) NCR.
All documents related inspection have been approved.
Packing list has been reviewed by RDMP JO.
Condition:
N/A

Attachment
#1. Packing List
#2. FAT Test report

Issued by RDMP JO

Andry Arifin
Name/Signature: Dong-Keun, Lee
JO QA/QC Manager

WE HEREBY CERTIFY THAT ABOVE MENTIONED COMMODITY HAS SATISFACTORILY PASSED


THE TEST & INSPECTION IN ACCORDANCE WITH THE CONTRACTUAL SPECIFICATION.
HOWEVER, THIS CERTIFICATE DOES NOT RELIEVE VENDOR FROM THE GUARANTEES AND
OBLIGATIONS WHICH ARE SET FORTH IN THE PURCHASE ORDER AND ATTACHMENTS.