Professional Documents
Culture Documents
Homework #5
Q1. A plan is being developed for a commercial office building. The present design of the
building includes the following features:
Given Data:
Requirement:
A simple parametric estimate based on the size of the building (square feet) is needed for the
current project plan.
a) Using the RS Means square foot cost estimating data provided on the attached sheets,
estimate the following costs to construct the building: (i) Total cost ($), and (ii) Total cost
per square foot ($/SF). No location factors are needed for this part.
b) Using the RS Means location factor tables provided, would the building cost more in
Seattle, WA or Portland, OR, and how much more?
Solution:
Part – a:
13,0
i) Area of 1 Floor = 00 Sq. Ft
10,5
Area of Basement = 60 Sq. Ft
No of Floors = 7 Nos
91,0
Area of 7 Floors = 00 Sq. Ft
101,5
Total Area of Building Including Basement = 60 Sq. Ft
4 Linear
Exterior Perimeter = 50 Ft
96.
Cost per Sq. Ft = 45 US $
Total Cost per Sq. Ft Area of Building (Area of Building x Cost per Sq. 9,795,4
Ft) = 62 US $
108,5
Price of 1 Passenger Elevator with Capacity 3500 LBs with 5 Stops = 00 US $
113,0
Price of 1 Service Elevator with Capacity 5000 LBs with 5 Stops = 00 US $
Additional Stop = 3
17,4
Cost for Additional Stops = 75
125,9
Price of 1 Passenger Elevator with Capacity 3500 LBs with 8 Stops = 75 US $
As No of Passenger Elevators with Capacity 3500 LBs are 2
251,9
Price of 2 Passenger Elevators with Capacity 3500 LBs with 8 Stops = 50 US $
130,4
Price of 1 Service Elevator with Capacity 5000 LBs with 8 Stops = 75 US $
382,4
Total Cost of Elevators = 25 US $
iii Total Cost of Closed Circuit Surveillance, One Camera and Monitor 1,4
) Station = 00 US $
iv 6
) Cost of one, 25 Watt, Nickel Cadmium Battery = 65 US $
79,8
Total Cost of Nickel Cadmium Battery Lights = 00 US $
1
v) Cost of Smoke Detector, Ceiling Type = 55 US $
4,9
Total Cost of Smoke Detectors required = 60 US $
vi
) Intercom System:
Total cost of One Master Station = 2,0 US $
50
1
Cost of One Intercom Outlet per Floor and Basement = 31 US $
No of Floors = 8 Nos
1,0
Total Cost of Intercom Outlets = 48 US $
3
Cost of One Handset = 60 US $
No of Floors = 8 Nos
2,8
Total cost of 8 Handsets = 80 US $
5,9
Total Cost of One Master Station = 78 US $
10,270,0
Total Cost of the Project = 25 US $
Part - b
1.
Seattle Factor = 05
1.
Portland = 06
10,783,526.
Total Cost of Project using Seattle Factor = 25 US $
10,886,226.
Total Cost of Project using Portland Factor = 50 US $
11,322,7
Difference by using Seattle Factor = 03 US $
11,539,4
Difference by using Portland Factor = 00 US $
Q2. The following bar chart shows the activity schedule for the design of a project. The total
estimated project design cost is $1,470.
After four weeks of work on the project, a progress report shows the following information
about the percent complete and actual costs of each activity:
a) Draw a cost profile (cumulative cost curve with time on horizontal axis and $ on vertical
axis) showing the cumulative project cost over the course of the project for the as
planned condition with estimated costs.
b) What is the status of the project in terms of budget (over or under)? Check CV and CPI.
CV = EV - AC $115
CV is positive which means we are cost efficient and we spent less than Planned. CPI > 1 means
we are under Budget.
c) What is the status of the project in terms of schedule (ahead or behind)? Check SV and
SPI.
SV = EV - PV ($142)
SPI = EV / PV 0.78
SV is negative and SPI < 1, which means we are behind the Schedule.
d) What is the estimated total cost of completing all of the work (EAC)? Assume the CPI will
remain the same for the remainder of the project.
Based on the above if we keep the same CPI for the remainder works, Project will end
up on cost lower than what was initially planned.
e) What is the expected cost to complete all of the remaining project work (ETC) assuming
the work is proceeding as planned?
If the future work is assumed to be at the same planned rate, Project will end up under
the Planned Budget.
VAC is positive which means Project will end up under the Planned / Estimated
Budgeted Value by using above criteria that remaining work will end up at the planned
rate.
g) Based on the efficiency that must be maintained in order to complete the current EAC,
will it be harder, easier, or the same level of effort to complete the work? Use the “To
Complete Performance Index” (TCPI).