Professional Documents
Culture Documents
3-1-1. Method Statement Excavation
3-1-1. Method Statement Excavation
: ALF-C-MS-001
Issue: 01 Rev.: 01
Method Statement for Excavation Work Date: 10.03.2020
3. REFERENCE DOCUMENTS:
• Construction drawing
• PTS
• TCS-Q-113.02
4. RESPONSIBILITY:
Project/Construction Manager
Site Manager
Site Manager will be responsible:
➢ Over-all direction
➢ Monitoring
➢ Coordination
➢ Control of all the constructions activities related to the excavation works.
Page 1 of 4
CLASSIFICATION: INTERNAL
Document Title: Ref. No.: ALF-C-MS-001
Issue: 01 Rev.: 01
Method Statement for Excavation Work Date: 10.03.2020
Site Engineer
QA/QC Engineer
Foremen
Foremen will be responsible:
➢ Direct execution of works involves in the excavation according to the plan.
➢ Directly control and give instruction to the working personnel.
➢ Ensure that works are performed with proper tools/equipment, PPE’s and good
housekeeping around the working area.
HSE engineer/Supervisor
Safety engineer / Supervisor will be responsible:
➢ Review prior to the start of the work Safe Work Plan and work permit,
➢ If required a submittal to client/customer that must be implemented and
observed during the steel rebar/reinforcement works.
Page 2 of 4
CLASSIFICATION: INTERNAL
Document Title: Ref. No.: ALF-C-MS-001
Issue: 01 Rev.: 01
Method Statement for Excavation Work Date: 10.03.2020
6. PROCEDURE:
➢ Survey the area and mark the excavation layout and slope cut stakes as per
excavation plan and drawing issued for the construction. Allowance should be
provided to have enough working space between the foundation to be constructed
and the edge of the bottom of the excavation for the personnel, forms, bracing, and
supports to be installed. All dimensions should be taken from the
Benchmark/reference point of the particular site.
➢ Inspection test plan (ITP) specific to project requirements shall be made and
relevant inspection activities shall be recorded either on the company formats or
those supplied by Customer.
➢ The ground level and depth of excavation shall be determine..
➢ Submit request for joint inspection of N.S.L and layout of area to client/consultant.
➢ Ensure the safety requirement as per health and safety plan.
➢ Excavation/Trenching over 1.2M deep shall be provided with sides sloped back to
the natural repose of the soil to avoid creation of caving. Sides which cannot be
sloped to the natural repose because of adjacent structures or ground condition
shall be shored adequately to resist earth movement and to protect workers.
➢ The excavated areas shall be isolated with the other working areas.
Page 3 of 4
CLASSIFICATION: INTERNAL
Document Title: Ref. No.: ALF-C-MS-001
Issue: 01 Rev.: 01
Method Statement for Excavation Work Date: 10.03.2020
7. ATTACHMENT
➢ Risk assessment and analysis/JHA
Page 4 of 4
CLASSIFICATION: INTERNAL