BF-61 1 Site Organization
BF-61 1 Site Organization
SITE ORGANIZATION
1
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
TABLE OF CONTENT
2
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
The personnel organization at site should be specified at the beginning period based on the
Stipulation of Management board in order to ensure the management go through, timely and
efficiently. The key divisions are comprised of:
Management board:
- Organize, operate and manage the execution, quality and safety at work.
- Report the site situation to Corporation and deal with the relation with the Owner.
Divisions of administration, personnel, safety at work and environmental sanitation:
- Co-ordinate with Corporation to perform the management works, power supply for
execution at site.
- Establish, manage and follow the performance on the regulation, stipulations of
administration, order and security, safety at work and environmental sanitation at site.
- Propose the solutions, supervise and speed up the performance works on property,
material, equipment, safety at work and environmental sanitation at site.
Technical management department:
- Control the project quality according to the project requirement and internal management
standards.
- Perform the preparation works for execution, such as, forming the detailed drawings for
deploy, detailed schedule, proposing the material sample, experiment and checking the
quality of material, machine and equipment... before put in to operation at site.
- Form the specific and detailed execution measures for execution to the Owner and
relevant authorities for approval.
- Be responsible for the soil investigation.
- Co-ordinate with the technical operation department to supply material, equipment
sufficiently, accurately and timely.
- Co-ordinate with the technical division to make the as-built drawings for project.
Technical operation department:
- Instruction: check and adjust the deploy of execution measure, schedule and put in an
estimation for project.
- Form the schedule according to the day, week, month (works, material, motorbike,
equipment, technical conditions...)
- Manage directly inspection, quality control and the schedule at site.
- Co-ordinate with the quality division to manage the adequate usage and supply of
material, equipment for project.
- Manage the machines and equipment for execution.
3
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
The relationship between the main office and the management at site is defined in the
following chart, as follows:
- The Contractor performs the contract through his Site Management Board, being at the
head is the Leader appointed by the Contractor.
- The site manager is delegated powers by the Contractor to decide in his scope in order to
ensure the management the Site timely and efficiently.
4
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
5
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
4.2 Authority
Preparation stage
- To manage and carry out the work following the approved schedule
- To be responsible for the quality and schedule of the work
- To report and make any suggestion to THE PM regarding to the work status, difficulties,
and any incidents at site.
Coordination
Internal
- To coordinate with Administration, Quality Control, Planning & Contract, and HSSE
Departments to ensure all project requirements are fulfilled.
External
- To coordinate with material suppliers, sub-contractors, and other partners
- To coordinate with government authorities / agencies when required
Other
5.2 Authority
7
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
6.1 Responsibility
- To assist and counsel any planning and contract matter for the PM
- To manage the payments under the contract (A-B and B-B') and the finance status of the
project
- To manage the work schedule
- To manage Material Procurement
- To draft B-B' contracts
- To organize and assign resource internally in order to ensure the function of P&C
department
- To coordinate with other departments to ensure all activities are performed properly in
accordance with the contract.
- To report to PM the project status on a weekly and monthly basis
6.2 Authority
7.1 Responsibility
- To manage and ensure that operational safety standards or other requirements are met
at an operation level
- To manage and monitor project delivery plans to ensure objectives are being satisfied,
review the report outcomes and provide timely advice to the PM on any anticipated
delays.
- Provide technical support to other Road, Transport & Drainage Sections in relation to
project delivery, pavement design and in resolving construction related design issues.
- To solve any issues involving CC1 within or outside the project site (e.g. local people,
traffic matters, etc.)
- To report to PM regarding issues on a weekly and monthly basis
- To perform other tasks assigned by the PM
8.2 Authority
- Decisions affect the work and activities of others within the unit
- The work of the Pavement Manager influences a number of separate community groups
through policy application and development
- Ensure that operational safety standards or other requirements are met at an operational
level
- Look for ways to save costs. Be conscious of budget constrains and be aware of cost
implications of own actions within own work area
- Support the HSE Manager and team with planning, coordinating and implementing of
effective HSE policies, guidelines and procedures to ensure that the department
objectives are met.
- Ensure training, tool box meetings, accident prevention course
- Ensure all worksites are HSE compliant with Company policies and safety standards
- Provide HSE aspects of Company Bid Submissions as requested
9.2 Authority
- To make decision and solve any HSE related matters when it is considered appropriate
- To give warning and discipline for any violations
- To request the HSE Manager to provide efficient resources for assigned tasks
9
The Royal Government of Cambodia
Ministry of Economy and Finance
Ministry of Public Works and National Road No.5 Improvement Project
Transport SITE (Sri Sophorn – Poipet Section)
ORGANIZATION Sta. 84+740 to Sta. 119+880, Length = 35.140 km
10.2 Authority
- To make decision and solve any problems related matters when it is considered
appropriate
- To give warning and discipline for any violations
- To request the HSE Manager to provide efficient resources for assigned tasks
- To propose any measures or procedures to improve the HSE system
10