Prob. 1:
T B1 B2 B3 B4
P 30 40 50 60
A1 80 1 5 7 4
A2 45 5 7 5 9
A3 55 12 2 3 7
T B1 B2 B3 B4
P 30 40 50 60
1 5 7 4
A1 80 30 50
5 7 5 9
A2 45 (-) (-) 35 10
12 2 3 7
A3 55 40 15
T B1 B2 B3 B4
P 30 40 50 60
4
1 5 7
(50+
(30-θ)
A1 80 θ)
5 7 5 9
A2 45 (θ) (-) (35) (10-θ)
12 2 3 7
A3 55 (-) (40) (15) (-)
θ=10
T B1 B2 B3 B4
P 30 40 50 60
1 5 7 4
A1 80 (20) (60)
5 7 5 9
A2 45 (10) (35)
12 2 3 7
A3 55 (40) (15)
Optimal solution:
1 0 1 4
T B1 B2 B3 B4
P 30 40 50 60
0 1 5 7 4
A1 80 (20) (-) (-) (60)
4 5 7 5 9
A2 45 (10) (-) (35) (-)
2 12 2 3 7
A3 55 (-) (40) (15) (-)
Prob.2
There are 3 power plants and 4 demands (cities) with the relative cost ( cost for
transmiting one electricity unit ):
3 2 3.5 7 25MWh=a1
4 3 7 6 10MWh=a2
5 6 5 6 20MWh=a3
15 15 10 15
u1+v1=3
u1+v2=2
u2+v1=4
u2+v4=6
u3+v3=5
u3+v4=6
→v1=0; u1=3; u2=4; v2=-1; v4=2; u3=4; v3=1
+3.5-3-1=-0.5=c13 new
7-3-2=2
3-4+1=0
7-4-1=2
5-4-0=1
6-4+1=3
X13 =θ
10-θ/3 15/2 θ/3.5 0/7 25
15 15 10 15
Θ=5
5/3 15/2 5/3.5 0/7 25