Professional Documents
Culture Documents
TE-419896-001 - 863-U-3002 - Liquid Corrosion Inhibitor Injection Package - Rev.B
TE-419896-001 - 863-U-3002 - Liquid Corrosion Inhibitor Injection Package - Rev.B
MWK
HCK
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
SBK
SBK
JFGP 2
Jafurah Utilities, Sulfur and Interconnecting Systems
DESCRIPTION
(Package 3)
10-14329-0003 ISSUED FOR REVIEW
BI No. 10-14329
16-DEC-21
18-FEB-22
DATE
DISCIPLINE
ENGINEER
DATE
JHK
18-FEB-22
FOR
CERTIFIED
MWK
LIQUID CORROSION INHIBITOR
DATE
CONSTRUCTION
AGENCY
18-FEB-22
INJECTION PACKAGE
DATE
(863-U-3002)
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B______
OF THIS DRAWING IS COVERED, FOR ALL
OPRNS
PMT
ENG'G CERT. SAUDI ARABIAN OIL COMPANY
MWK
HCK
SBK
SBK
CONTENTS
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
SECTION DESCRIPTION Page No.
1 Introduction 3
2 Process Duty 4
3 Mechanical Design 6
4 Control, Safeguarding and Instrumentation 7
DESCRIPTION
5 Electrical 8
6 Utilities 8
7 Notes 8
8 Package Data 10
9 Dosing Pump 11-12
10 Dosing Pump Motor Data Sheet 13-14
11 Mixer Motor Data Sheet 15-16
10-14329-0003 ISSUED FOR REVIEW
16-DEC-21
18-FEB-22
DATE
REV
NO.
A
DISCIPLINE
ENGINEER
SBK
DATE 18-FEB-22
ENGINEERING
MANAGER
JHK
DATE 18-FEB-22
CERTIFIED
MWK
DATE 18-FEB-22
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B______
OF THIS DRAWING IS COVERED, FOR ALL
1.1 General
ENG'G CERT.
MWK
HCK
This Data Sheet covers the requirements for the Liquid Corrosion Inhibitor Injection Package 863-U-3002, for the
Jafurah Project, JFGP Processing Trains 1 & 2.
SBK
SBK
Corrosion Inhibitor is required to maintain the integrity of the Processing trains 1 & 2 for the condensate lines and
will be injected upstream of the Inlet Condensate Separators (864-D-1002 & 865-D-2002). Corrosion Inhibitor will
be injected on a continuous dosing basis to minimise corrosion and protect equipment during normal and
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
dewatering operations.
The 863-U-3002 Package shall consist of, but not be limited to, the following:
- 1 x 100% vertical bulk storage tank (with mixer if necessary) installed on skid for a required
storage volume of 113.5 ft3 (based on 80% working volume for 30 days consumption of
maximum dosing rate). 315
Tank to be fitted with necessary level gauges & instruments.
DESCRIPTION
- 3 x 100% electrical dual head dosing pumps, one operating and two stand-by.
- All interconnecting piping and instrumentation within the package boundary, including all
isolation, control and relief valves; strainers; calibration pots; pulsation dampers; pressure
gauges, flow meter on metering pump discharge, etc.
- All instrumentation wired to skid edge junction box for wiring to the SCADA (wiring to SCADA by
others).
. . .
- Necessary sample and drain connections.
34-15430-3002 ISSUED FOR REVIEW
. . .
- Platform and ladder for access to the top of storage tank, as necessary.
- All other mechanical and electrical equipment, instrumentation and controls necessary for safe
and reliable operation.
- Structural steel base frame with sun shades (VTC for sun shades).
JO/EWO
18-FEB-22
DATE
1.2 Abbreviations
The following acronyms and abbreviations are used in this document:
REV
NO.
Bbl. US Barrels
DISCIPLINE
ENGINEER
BEDD Basic Engineering Design Data
SBK
DATE 18-FEB-22
DCS Distributed Control System
ENGINEERING MANAGER
GOSP Gas Oil Separation Plant
JHK
JFGP Jafurah Gas Processing Train
DATE 18-FEB-22
CERTIFIED MBCD Thousand Barrels per Calendar Day
MWK
MDB Thousand Barrels per Operating Day
DATE 18-FEB-22
CONSTRUCTION NPS Nominal Pipe Size
AGENCY
PD Positive Displacement
DATE
OPERATIONS
P&ID Process and Instrumentation Diagram
PFD Process Flow Diagram
DATE
PZV Process Safety Valve
CONTROL NUMBER
TBC To Be Confirmed
VTA VENDOR to advise
DATE:
BY:
This document shall be read in conjunction with the following related project documents:
ENG'G CERT.
MWK
HCK
TD-254011 P&ID - Liquid Inlet Manifolds, JFGP Inlet Storage & Export
TD-204002 PFD - Liquid Inlet Manifolds, JFGP Inlet Storage & Export
SBK
SBK
TD-234002 MSD - Liquid Inlet Manifold, JFGP Inlet Storage & Export
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
TD-821950 Basic Engineering Design Data (BEDD)
TD-821403 Electrical Basis of Design
TD-821310 Control & Instrumentation - Basis of Design
TD-821303 Control & Instrumentation - Package Equipment
DESCRIPTION
18-FEB-22
MWK
2.1 Design Parameters
DATE 18-FEB-22 Liquid Corrosion Inhibitor Package is to provide sufficient dosing for normal operation and during dewatering.
CONSTRUCTION
AGENCY
The package shall be available 24 hours/day, 365 days/year.
DATE
Dosing will be fully automatic with minimum operator intervention during normal operation.
OPERATIONS The Liquid Corrosion Inhibitor Package shall have one storage tank feeding the injection chemical directly to
the dosing pumps.
DATE No day tank is required in the design in order to minimise liquid handling.
chemical vendor.
CONTROL NUMBER
Corrosion inhibitor type and properties to be provided by the Vendor during detailed engineering.
VERIFICATION
EDSD
The dosing pumps discharge requirements and tank volumes shown in table 1 below shall be sufficient for
APPROVAL/CERTIFICATION REQUIREMENTS,
supplying the selected injection chemical, which has a maximum operating pressure of 280 psig and a design
THIS INDICATES THAT REV NO ____B_____
OF THIS DRAWING IS COVERED, FOR ALL
pressure of 1300 psig. Design case is Y6 Rich Winter Case, Mixed Condensate from Liquid
REVISION CERTIFICATE
Liquid Corrosion Inhibitor dosing pumps shall provide the specified dosing concentration and dosing flow rates
ENG'G CERT.
MWK
HCK
of the corrosion inhibitor for normal operation to the injection point as shown in table 1.
Table 1: Corrosion Inhibitor Dosing Rates and Tank Volumes per Train
SBK
SBK
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Inlet Cond. Separator
Description
Chemical Liquid Corrosion Inhibitor
Case Description Y6 Rich Case Winter
Dosing Conc. (ppmv) 15 10
Per Train 1
Water flow / Train (USGPM) 290.6 113.2
0.013
DESCRIPTION
Detail Engineering.
* Based on 30 days consumption, 80% working volume and considering common storage tank for two
trains, minimum 1000 gallon tank. Corrosion Inhibitor - CORR11011B
3000 maximum dosing rate= 1.486 USGPH
Specific Gravity= 0.922
JO/EWO
ENGINEERING MANAGER The Package shall include controlled volume dual head pumps, tank, level gauges, strainer, filter, pressure
relief valves, sight glasses and flow metering/monitoring devices, check valves, hand valves, a power source for
JHK the pump and instrumentation to control the injection and to monitor its effectiveness.
DATE 18-FEB-22
CERTIFIED
Electrical dosing diaphragm pumps shall be used. Dosing pumps shall be provided with appropriate alarms and
automated controls to provide immediate switchover from running to standby pump, in case of pump failure or
MWK the need for maintenance.
DATE 18-FEB-22
Each pump shall have an adjustable stroke length to achieve turndown ratio from maximum flow.
CONSTRUCTION AGENCY
Alteration of the stroke length shall be possible without shutting the pump down.
DATE Stroke length to be adjustable, both locally and by a control signal from the remote control room. Mechanical lost
OPERATIONS motion capacity adjustment is not permitted. Hydraulic lost motion capacity is not permitted for duties with motor
rating > 1 HP.
DATE Dosing will be designed for unattended and minimum operator intervention during normal operation and
automatic safe shutdown without the operator intervention
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B_____
OF THIS DRAWING IS COVERED, FOR ALL
MWK
HCK
While the design conditions of the equipment and piping within the package shall be determined by the Vendor
based on the specified operating pressures (refer section 2.2) and criteria detailed in the Basic Engineering
SBK
SBK
Design Data, BEDD, and applicable Aramco standards, the following criteria shall be followed:
a) Design temperature shall be set at 50ºF above the maximum operating temperature. The minimum
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
upper design temperature shall be 185ºF (for solar gain, higher local temperature in summer).
b) The maximum operating temperature is defined as the highest material balance temperature.
Consideration shall also be given to other conditions such as start-up, shut-down etc. Such
temperatures should be considered on a case by case basis to establish if they should be taken as the
maximum operating temperature.
c) The minimum design temperature for which the package equipment must be designed will normally
be specified as the minimum operating temperature. Where there is no specified minimum design
temperature data the (metal - MMDT) temperature for this equipment 41°F shall be used.
DESCRIPTION
d) Design Pressure for pumped systems: process piping and equipment which form part of a pumped
hydraulic system, and which may operate liquid full, shall be designed for the maximum pressure that
can be developed by the pump.
e) A pressure relief valve must be installed on the pump discharge to vent fluid back into the chemical
tank or suction line if pressure builds up. The pump internal relief valve setting shall be between 110%
and 120% of the rated discharge pressure.
ISSUED FOR REVIEW
3.3 Noise
DATE
3.4 Piping
A
DISCIPLINE
ENGINEER All threaded joints downstream of the pump discharge shall be seal welded.
SBK
DATE Piping to be adequately supported to avoid vibration. Pipes to be anchored at skid edge. Refer to SAES -L-310
00/01/1900
ENGINEERING MANAGER
Section 17.
Nozzle loads permitted at all terminal points shall be agreed with BUYER. ‘Zero Load’ condition shall not be
DATE accepted.
OPERATIONS
The three pumps shall have their discharge piping arranged so that:
DATE
- Each pump head is capable of delivering corrosion inhibitor to either train
CONTROL NUMBER
VERIFICATION
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B_____
OF THIS DRAWING IS COVERED, FOR ALL
The storage tank shall be sized for 30 days storage at maximum dosing rate for two trains, minimum 133.5 ft3
ENG'G CERT.
SBK
Tanks shall be manufactured in accordance with 32-SAMSS-030 by an approved Saudi Aramco fabricator.
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
VENDOR may propose a non-metallic tank as an alternative design for approval by Saudi Aramco. The Package
VENDOR shall complete tank data sheet Form SA-2696 for review by BUYER.
Chemical storage tanks shall, as a minimum, be equipped with fill nozzle, utility nozzle, vent, pressure relief,
overflow, discharge, low point drain, level and temperature instrumentation.
Connections smaller than 1½ " or smaller shall be gusseted to prevent potential damage.
Anti-swirl baffles (vortex breakers) shall be provided on liquid outlet nozzles upstream of a pump suction side.
(2) One 750 mm (30 in) NPS roof manway for tanks larger than 10,000 gallons capacity.
Tanks with mixers shall be provided with at least one manway that does not require removal of the mixer.
Tanks smaller than 36 inches in diameter shall be povided with minimum of two flanged NPS 4 openings.
10-14329-0003 ISSUED FOR REVIEW
Block valves shall be installed directly at the tank nozzles. If more than one line connects to the same nozzle,
valves shall be installed in each line, in addition to the nozzle block valve.
Connections for venting devices shall be designated only to provide protection against overpressure / vacuum
conditions. No other devices shall be installed in combination with venting devices without agreement with
BUYER.
18-FEB-22 10-14329-0003
JO/EWO
A clearly graduated calibration tube, vented back to tank above the high liquid level, shall be installed on the
suction piping to each chemical injection pump. Calibration tube shall be provided with all necessary valves
and fittings so the injection rate can be checked during operation.
REV
NO.
DISCIPLINE Calibration pot shall be robust design with calibrated toughened glass enclosed in steel guard.
ENGINEER
SBK
Main line chemical feed and calibration tube shut-off valves shall be ¼ turn ball valves and shall be positioned
DATE
such that the operator can easily and simultaneously operate both valves during calibration.
18-FEB-22
Each pump shall have an minimum operating capacity of 10 - 110% of the recommended dosing rate based on
stroke adjustment and further lower turndown possible based on variable speed drive.
EDSD
Each pump should be capable of being set to zero (no strokes per minute) for conditions when the condensate
DATE:
Mechanical lost motion capacity adjustment is not permitted. Hydraulic lost motion capacity adjustment is not
REVISION CERTIFICATE
A pulsation damper is to ensure an even chemical application, shall be provided in each pump head discharge
line and shall be sized to provide sufficient degree of damping. Any fitting required for charging the pulsation
ENG'G CERT.
MWK
HCK
dampers shall be provided. Suppression devices shall be furnished as necessary to meet the following criteria.
Unfiltered peak to peak pulsation levels shall not exceed +/- 3% as per SABP-A-015 of:
SBK
SBK
• Rated suction pressure or 100 kPa gauge (15 psig) whichever is less;
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
• Rated discharge pressure or 100 kPa gauge (15 psig) whichever is less.
The following situations shall be avoided:
• Cavitation in the suction or discharge of the pump;
• Over delivery due to suction losses or uncontrolled delivery;
Any fittings required for charging the pulsation dampers shall be securely connected to the discharge piping and
accessible from grade/skid. Pulsation dampers shall be designed so that no solids settle in the interior of these
devices.
4.0 CONTROL, SAFEGUARDING AND INSTRUMENTATION
The package / equipment shall be automated with equipment control, monitoring and safety functions
incorporated and controlled by the Supervisory Control & Data Acquisition (SCADA).
ISSUED FOR REVIEW
Safeguarding shall be incorporated in the Emergency Shutdown system (ESD). VENDOR shall provide the
functional specification for the control and logic diagrams or similar for the safeguarding.
The incorporation of the control in SCADA and safeguarding in the ESD is by Others.
The liquid corrosion inhibitor flow rate to injection point will be measured and flow controlled through the
16-DEC-21 10-14329-0003
18-FEB-22 10-14329-0003
SCADA. The injection pumps will have adjustable strokes that will be used to control the flow when the pumps
JO/EWO
Temperature gauge shall be supplied on the tank for indication of bulk fluid temperature.
REV
NO.
The pumps shall be provided with a local panel with start/stop facility, emergency stop, selector switch and
DISCIPLINE running indication. Remote running indication, pump selection and pump start/stop/trip shall also be provided.
ENGINEER
Pump shall be provided with a selector switch for the standy pump to start on failure of the running
SBK
DATE pump.
18-FEB-22
ENGINEERING MANAGER Pressure indication shall be supplied on each pump suction and discharge line.
JHK Pressure and flow transmitters (coriolis) shall be supplied on the discharge lines per head.
DATE 18-FEB-22
CERTIFIED Double diaphragm pumps shall be provided with a diaphragm failure signal system.
MWK Instrumentation shall be wired to skid edge Junction Box or the local control panel. Wiring to the SCADA shall be
DATE 18-FEB-22 by Others.
CONSTRUCTION AGENCY
Control facilities to be provided to auto start standby-pump in case of operating pump trip.
Instrumentation and Control shall be in accordance with the minimum requirements specified in ‘Control and
DATE Instrumentation Basis of Design’, TD-821310, ‘Control & Instrumentation - Package Equipment’, TD-821303 and
OPERATIONS ‘Instrumentation for Packaged Units’, 34-SAMSS-831.
DATE
5.0 ELECTRICAL
CONTROL NUMBER
VERIFICATION
Hazardous Materials Schedule area classification for the Liquid Corrosion Inhibitor Package to be confirmed in
the Detail Design Enginnering phase once the Corrosion Inhibitor is selected.
DATE:
BY:
Chemical Hazardous Area Classification to be confirmed by EPC contractor during detailed engineering.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B______
All electrical equipment shall be fully in accordance with Electrical Design Basis TD-821403 and Basic
OF THIS DRAWING IS COVERED, FOR ALL
All electrical equipment shall meet voltage levels and supply voltage variations as stated in Electrical Design
All electrical equipment shall meet ambient conditions as stated in Electrical Design Basis TD-821403.
MWK
HCK
All equipment installed in hazardous (classified) areas, electrical equipment/component meeting the
SBK
SBK
requirement of IEC 60079 shall be labelled, listed, or certified by any of the agencies in the Approved IECEx
Certification Bodies (ExCBs) under the IECEx Certified Equipment Scheme. Method of protection must be
marked and must correspond with NEC Article 505 requirements for suitable protection method(s) for the
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
hazardous area where the equipment is applied.
Vendor shall provide single-phase power outlets (120V) on the skid for maintenance purposes.
Vendor shall provide Low Voltage power panels and protection system as applicable Saudi Aramco
standards.
Power cablings to motors will be provided by CONTRACTOR directly to the motor terminal boxes. VENDOR
shall provide on-skid supporting cable tray for the incoming power cables.
DESCRIPTION
All on-skid grounding and bonding connection shall be wired to skid-edge earth busbars. CONTRACTOR shall
provide cabling up to these earth busbars. The grounding and bounding shall be as per SAES-P-111.
Electrical control cabling on skid shall be wired to skid-edge junction boxes by VENDOR. CONTRACTOR
shall provide control cabling up to these junction boxes.
Main drive motors shall be sized for relief valve settings including accumulation.
ISSUED FOR REVIEW
6.0 UTILITIES
Following utilities are envisaged to be required for the Liquid Corrosion Inhibitor Package. VENDOR to
indicate requirement of any other utilities.
- Electrical Power 460V / 3Phase / 60Hz (at Users)
16-DEC-21 10-14329-0003
18-FEB-22 10-14329-0003
JO/EWO
- Instrument Air
REV
NO.
For operating and design conditions of utilities, refer to the ‘Basic Engineering Design Data’ BEDD document -
A
DISCIPLINE TD-821950.
ENGINEER
SBK
DATE 18-FEB-22 7.0 NOTES
ENGINEERING MANAGER
1. Liquid Corrosion Inhibitor Injection skid will be installed in a relative humidity from zero to 100%
JHK (condensing) and exposed to heat and sand.
DATE 18-FEB-22
2. Skid mounted injection system shall be designed, inspected and tested as per 32-SAMSS-038. Nameplate
CERTIFIED
and stamping requirements shall follow 32-SAMSS-038..
MWK
DATE 18-FEB-22
3. Skid shall be equipped wit adequate drainage and drip tray in the event of chemical spill.
CONSTRUCTION AGENCY 4. VENDOR shall provide a complete P&ID for the Liquid Corrosion Inhibitor Package.
5. VENDOR shall identify all risks associated with the equipment and provide necessary measures for the
DATE elimination or minimisation of such risks. VENDOR shall supply all information necessary for the safe
OPERATIONS operation of the equipment, in particular to evaluate potential sources of ignition.
6. VENDOR shall include for any required special tools
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B_____
OF THIS DRAWING IS COVERED, FOR ALL
OPRNS
SAUDI ARABIAN OIL COMPANY
Pump Tag No TBC
PMT
Rev.0A
No. of Pumps 3x100% (1 duty/2 standby)
No. of Heads/Pump 2
CERT.
MWK
HCK
SBK
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Flow per Head USGPM Ref. section 2.2
Discharge Pressure psig Ref. section 2.2
Material VTA (NOTE 1) Shaft Length VTA Strainers: per System / Pump / Head
Corrosion allowance NIL Shaft Seal arrangement VTA Calibration: Level Gauge / Calibration Gauge
Lid YES Material Wetted Parts (Note 1) VTA Relief Valve External to Pump YES
Access YES Mounting Arrangement VTA Pressure Gauges ON DISCHARGE
Atmospheric Vent / Purge System VTA Motor 460 Volts 3 Ph 60Hz kW VTA Diaphragm failure signal system : YES
Dissolving Basket N/A Chemical Mixed VTA
Relief Valve N/A Mixing Time . VTA .
10-14329-0003 ISSUED FOR REVIEW
18-FEB-22
Hazardous Area Classification: TBC - See section 5 TP08 PULSATION DAMPER (VENT) TBC TBC
Weather Rating SEE BEDD DOCUMENT (TD-821950) TP09 PRESSURE GAUGE (VENT) TBC TBC
REV
NO.
A
DISCIPLINE
NOTES
ENGINEER
SBK
1) Materials of construction shall be suitable for the concentrated chemical solution. Refer to Section 3.2.
DATE 18-FEB-22
2) Equipment Tag Nos shall be confirmed by EPC Contractor during Detailed Design phase. will be finalized later.
ENGINEERING
3) VTA = Vendor to advise. TBC = To be confirmed.
MANAGER
JHK
DATE 18-FEB-22
CERTIFIED
MWK
DATE 18-FEB-22
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B______
OF THIS DRAWING IS COVERED, FOR ALL
SBK
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
4. STEADY STATE ACCURACY %
1. LIQUID PUMPED LIQUID CORROSION INHIBITOR (TBC) 6. MAX./MIN. ALLOWABLE SPEED RPM -
.1 MAX. FLOW TEMPERATURE °F 131 8. BHP CONS. AT MAX. CAPACITY (C.1)* BHP
3. SPECIFIC GRAVITY AT FLOW TEMP./ MAX. TEMP. 0.922 0.98 1.03 9. BHP CONS. AT MAX. CAP. AND 110% OF E.12* BHP
4. VISCOS. AT FLOW TEMP./ MAX. TEMP. cP 2.5 3.5 10. MAX. DISCH. PRESSURE psig
5. VAPOR PRESSURE AT FLOW TEMP. psi(a) 0.07 Negligible 11. MAX. RELIEF VALVE SETTING psig
DESCRIPTION
.1 V.P AT MAX. FLOW TEMP. psi(a) Negligible 12. ACTUAL RELIEF VALVE SETTING psig
FOR REVIEW
3. SUCTION PRESS. MIN/RATED psi(g) VTA VTA F. PUMP AND COUPLING MODEL,
18-FEB-22 10-14329-0003 ISSUED
6. LOCATION .1 TYPE/SIZE
JO/EWO
MODEL G. UTILITIES
APPROVAL/CERTIFICATION REQUIREMENTS,
AC PHASE
RATIO : AGMA FACTOR DC VOLTS HERTZ
REVISION CERTIFICATE
H. MATERIALS OF CONSTRUCTION
MWK
HCK
SBK
2. PLUNGER VTA 3.
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
3. CONTOUR PLATE VTA
5. PLUNGER DIAPHRAGM VTA 1) Reported NPSHa is referenced at the pump center line and does not
6. PLUNGER PACKING VTA include any margin. Vendor to ensure NPSHa exceeds NPSHr
7. FRAME VTA by at least 3.3ft at rated flow. No further design margin is required
8. SUCTION PULSATION BOTTLE VTA when considering NPSHr at 120% of rated capacity.
9. DISCHARGE PULSATION BOTTLE VTA 2) Minimum pump differential pressure required to ensure guaranteed
11. RELIEF VALVE, SEAT AND TRIM VTA 3) Single head positive displacement pump with variable stroke
13. PIPEWORK VTA 4) Dose rate initially set using calibration pot. Subsequent increases or
1. PUMP NOZZLE
FOR REVIEW
FLANGED IN.
18-FEB-22 10-14329-0003 ISSUED
FLANGED IN.
JO/EWO
2 CAPACITY ADJUSTMENT
.1 MECHANICAL, TYPE
16-DEC-21
DATE
ENGINEERING
.1 SUCT.-VOL./CHARG. PRESS. cu.ft./psi(g)
MANAGER
.2 DISCH.-VOL./CHARG. PRESS. cu.ft./psi(g)
JHK
DATE 18-FEB-22
.3 CHARGING MEDIUM:
CERTIFIED 4. VALVES
OPERATIONS 5. LUBRICATION
.2 DRIVER
CONTROL NUMBER
VERIFICATION
SPLASH SUBMERGED
EDSD
6. TYPE OF DOUBLE DIAPHRAGM PUMPS OF THE SAME TYPE & SIZE IN OPERATION
7. TYPE OF DOUBLE DIAPHR. RUPTURE SIGNALING PUMPS MARK NO. INQ./ORDER NO. DATA SHEET NO.
DATE:
Plant: JFGP JFGP Plant No. 863 Driven Equipment: LIQUID CORROSION INHIBITOR INJECTION
PUMP MOTOR - (TAG No. - TBC)
ENG'G CERT.
MWK
HCK
SBK
BASIC DATA
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Volts: 460 Phase: 3 Hertz: 60 Nameplate: kW hp
Full Load RPM: Speed Range for Variable Speed Drive:
Rotation When Facing Motor Opposite Drive End:
Clockwise Counter-Clockwise Bi-Directional
Motor Thrust Loads: None Other
Type Load: Direct Coupled Belt Driven Other
NEMA Torque Design: “B” (normal) Other (specify)
DESCRIPTION
SITE DATA
Area Classification: Non-Hazardous
Hazardous (Classified) Class: HOLD Zone HOLD Group: HOLD
Temperature Class: HOLD
Elevation (Specify if Above 3000 ft.): ft
STARTING
ISSUED FOR REVIEW
MOUNTING
10-14329-0003
10-14329-0003
18-FEB-22
ENCLOSURE
DATE
DISCIPLINE
ENGINEER Space Heaters
SBK Space Heater Required for motors rated less than 75kW (100HP); Operating Voltage: 120 V, 1 ph
DATE 18-FEB-22 Other Voltage Max. Surface Temp. at Operating Volts ºC
ENGINEERING
MANAGER Heater Leads: Main Terminal Box Separate Heater Terminal Box
JHK
DATE 18-FEB-22
CERTIFIED
MWK
DATE 18-FEB-22
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B_____
OF THIS DRAWING IS COVERED, FOR ALL
GENERAL INFORMATION
SBK
SBK
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MOTOR DATA
Rating Data at 1.0 Service Factor:
Nameplate Power kW (hp) Voltage 460 Phase 3 Hertz 60
Full Load Speed RPM Enclosure Type Frame Size
Rotation When Facing Motor Opposite Drive End:
Clockwise Counter-Clockwise Bi-Directional
DESCRIPTION
Torque:
Speed-Torque Curve No. Speed-Current Curve No.
Power Factor
Nominal Efficiency
Guaranteed Efficiency
18-FEB-22 10-14329-0003
JO/EWO
Insulation System
Class Temperature Class ºC above ºC ambient at 1.0 SF
16-DEC-21
DATE
Bearing Information
Coupling End Bearing: Manufacturer’s Type Part No.
REV
NO.
A
DATE
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B_____
OF THIS DRAWING IS COVERED, FOR ALL
OPRNS
SAUDI ARABIAN OIL COMPANY
17-SAMSS-503, SEVERE DUTY TOTALLY ENCLOSED SQUIRREL CAGE INDUCTION MOTORS
APPLICABLE TO: Inquiry Proposal Purchase As Built
PMT
Plant: JFGP Plant No. 863 Driven Equipment: LIQUID CORROSION INHIBITOR INJECTION
ENG'G CERT.
TBC)
Purchaser’s Data to Be Supplied With Inquiry:
SBK
SBK
BASIC DATA
Volts: 460 Phase: 3 Hertz: 60 Nameplate: kW hp
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Full Load RPM: Speed Range for Variable Speed Drive:
Rotation When Facing Motor Opposite Drive End:
Clockwise Counter-Clockwise Bi-Directional
Motor Thrust Loads: None Other
Type Load: Direct Coupled Belt Driven Other
NEMA Torque Design: “B” (normal) Other (specify)
DESCRIPTION
SITE DATA
Area Classification: Non-Hazardous
Hazardous (Classified) Class: HOLD Zone HOLD Group: HOLD
Temperature Class:
Elevation (Specify if Above 3000 ft.): ft
STARTING
ISSUED FOR REVIEW
MOUNTING
10-14329-0003
10-14329-0003
18-FEB-22
ENCLOSURE
DATE
DISCIPLINE
ENGINEER Space Heaters
MWK
DATE
18-FEB-22
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B______
OF THIS DRAWING IS COVERED, FOR ALL
Vendor Data: LIQUID CORROSION INHIBITOR CHEMICAL TANK MIXER MOTOR (TAG No - TBC)
MWK
HCK
GENERAL INFORMATION
SBK
SBK
THIS DRAWING AND THE INFORMATION CONTAINED WITHIN HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR PART SHALL BE OBTAINED FROM THE DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MOTOR DATA
Rating Data at 1.0 Service Factor:
Nameplate Power kW (hp) Voltage 460 Phase 3 Hertz 60
Full Load Speed RPM Enclosure Type Frame Size
Rotation When Facing Motor Opposite Drive End:
Clockwise Counter-Clockwise Bi-Directional
DESCRIPTION
Torque:
Speed-Torque Curve No. Speed-Current Curve No.
Power Factor
Nominal Efficiency
Guaranteed Efficiency
Insulation System
18-FEB-22
DATE
Bearing Information
Coupling End Bearing: Manufacturer’s Type Part No.
REV
NO.
A
DATE
OPERATIONS
DATE
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV NO ____B______
OF THIS DRAWING IS COVERED, FOR ALL