360 Electrical & Engineering Services Project: E0360 - 360 Work Orders - Electrical

7650 NW 50th St Field Services


Miami, Florida 33166
P: (786) 348-2156

T&M Ticket #95


Performed on Sep 23, 2023 Reference # 230918-UM-UH 149635

Location UM-UHEALTH TOWER

Status Closed

Description Service Call - Adrian ATS 3 Equipment failed to transfer back to normal. PO: UH 149635

P.O.C Adrian Alcover Work Authorized by Bryan Garcia

Start Time 11:00 am End Time 3:00 pm

Building UHEALTH TOWER Work Status


Name/Room No.

Equipment ATS#3 EQUIPMENT POWER Recommendations • In the ATS configuration, the 'In Phase'
Nameplate option must be disabled to prevent issues
Information during load transfer. This is feasible because
they are configured for open transition,
meaning that at no point will both sources be
electrically coupled.

• It is possible to implement a rotation in the


Normal source in order to reduce the angle of
rotation between the sources of this ATS.
The proposed sequence is as follows:
o Current Sequence: Brown – Purple –
Yellow (BCA).
o Proposed Sequence: Yellow – Brown
– Purple (ABC).

Findings
An inspection and measurement were carried out
on the Equipment Branch ATS located in the
electrical room on the 2nd floor of UHT. It was found
that there is the same degree of electrical phase
displacement between the respective phases of the
utility and emergency power feeds. To confirm this,
a similar situation was discovered in the other ATS
units in the same electrical room (Life Safety and
Critical Branches).
The 90 electrical degrees displayed by ATS #3,
which prevented its operation, resulted from a
sequence displacement (BCA), creating a phase
shift of 120° between the respective phases
(maintaining the same direction of rotation), in
addition to -30° (The polarity of the angles varies
depending on the reference sequence taken)
caused by the phase shift between the feeds (utility
and emergency).
Through the phase rotation meter, it was
determined that both the Normal source and the
Emergency source are in a negative sequence (See
Picture #1 to #4). This implies that changing the
source will NOT affect the direction of rotation of the
loads connected to this Branch. Additionally, it was
verified with the Data Logger equipment that there
were no phasorial problems in both the Normal and
Emergency source (See Picture #5 and #6). Finally,
the sequence in the load (9th floor of the south
tower) in the parking garage elevator machine room
was checked, where it showed a positive sequence
(See Picture #7). This was achieved by making the

360 Electrical & Engineering Services Page 1 of 4 Printed On: Oct 18, 2023 07:32 AM EDT
T&M Ticket #95 Project: E0360 - 360 Work Orders - Electrical Field Services

corresponding rotation at the ATS equipment


output.
Based on the above findings, it can be concluded
that this angular phase shift (approximately 26
electrical degrees) is present throughout the
installation. However, for practical purposes, it does
not pose a problem for people or equipment. This is
because the ATS units perform open transitions,
and therefore, perfect phase synchronization is not
required.

Labor (1)
Employee Classification Time Type Hours

Luis Manotas (360 Electrical & Engineering Services) Field Services Engineer Regular Time 4.0

Total: 4.0

Materials (1)
Material Description Unit Quantity

Parking fee Parking fee ea 1.0

Total: 1.0

Equipment (1)
Equipment Description Unit Quantity

Phase angle meter Meter angle hours 1.0

Total: 1.0

Attachments

Picture #6 Phasorial Diagram Emergency ATS#3.jpg Picture #5 Phasorial Diagram Normal ATS#3.jpg

360 Electrical & Engineering Services Page 2 of 4 Printed On: Oct 18, 2023 07:32 AM EDT
T&M Ticket #95 Project: E0360 - 360 Work Orders - Electrical Field Services

Picture #7 Normal Rotation Load.jpg Picture #2 Normal rotation ATS #3.jpg

Picture #3 Emergency rotation ATS #1.jpg Picture #4 Normal Rotation ATS #1.jpg

Picture #1 Emergency rotation ATS #3.jpg 1696013354430.855957_tempImage.jpeg

1696013354350.658936_tempImage.jpeg 1696013354257.659912_tempImage.jpeg

360 Electrical & Engineering Services Page 3 of 4 Printed On: Oct 18, 2023 07:32 AM EDT
T&M Ticket #95 Project: E0360 - 360 Work Orders - Electrical Field Services

1696013354095.325928_tempImage.jpeg

Approvals

COMPANY SIGNATURE DATE CUSTOMER SIGNATURE DATE

Notes The phase angle was measured in all ATS's of the building and the settings were checked to verify if the phase angle meter
function was enabled. It was found that the function was enabled with a setpoint of 10 degree.

360 Electrical & Engineering Services Page 4 of 4 Printed On: Oct 18, 2023 07:32 AM EDT