This document is a comment resolution sheet for the Riyadh City South - Phase 5 infrastructure and streetscape project. It addresses 8 comments on material submittals, noting the contractor's responses and any additional remarks. The contractor agreed to comply with all comments, including providing certificates of origin and bills of lading with deliveries, installing materials according to approved documents, and submitting samples for inspection before procurement.
This document is a comment resolution sheet for the Riyadh City South - Phase 5 infrastructure and streetscape project. It addresses 8 comments on material submittals, noting the contractor's responses and any additional remarks. The contractor agreed to comply with all comments, including providing certificates of origin and bills of lading with deliveries, installing materials according to approved documents, and submitting samples for inspection before procurement.
This document is a comment resolution sheet for the Riyadh City South - Phase 5 infrastructure and streetscape project. It addresses 8 comments on material submittals, noting the contractor's responses and any additional remarks. The contractor agreed to comply with all comments, including providing certificates of origin and bills of lading with deliveries, installing materials according to approved documents, and submitting samples for inspection before procurement.
Project Name : RIYADH CITY SOUTH –PHASE 5 –INFRASTRUCTURE AND STREET SCAPE
SUBJECT TITLE RCS PH5 MATERIAL ORGINATOR SAIF BIN DARWISH
SUBMITTAL FOR CCS DOCUMENT REF NO RS-02-00001-05-11-EL-SBD- REVISION 00 MI-000062
SL COMMENTS CDT RESPONE REMARKS
1 Warranty is subject to ADDC requirements Noted & Complied & contract documents 2 Original certificate of origin and Bill of Complied If delivery is partial we lading certificate to be provided during will provide copy of each site delivery B/L and country of origin of full lot 3 Installation shall be as per approved NotedNoted & Complied Contractors Complied by Scope method statement, approved shop Contractor drawing, manufacturer recommendation & authority standard 4 This is conditional approval subject to Noted Contractors by Complied Scope Noted & Complied acceptance on proposed product during all Contractor stages like SAT & final handing over 5 Any additional requirements by ADDC is Noted Noted & Complied Contractors Complied by Scope the responsibility of the contractor I Contractor manufacturer without any additional cost 6 Original Certificate of origin to be provided Complied If delivery is partial we during site delivery. will provide copy of Country of origin of full lot 7 Sample to be provided for inspection & Noted & Complied acceptance prior to procurement of the material.
8 Earth resistance should not exceed 1 ohm. Noted & Complied