Professional Documents
Culture Documents
description
IEC 60947 Volumes Description
1 General requirements
AC-1 Non-Inductive or slightly inductive loads, for example, resistive furnaces, Heaters
Utilization
Typical Application
Category
AC-8a Hermetic refrigerant compressor motor control with manual resetting overloads
AC-8b Hermetic refrigerant compressor motor control with automatic resetting overloads
AC-12 Control of resistive loads and solid state loads with optocoupler isolation
AC-22 Switching of mixed resistive and inductive loads, including moderate overloads
DC-12 Control of resistive loads and solid state loads with optocoupler isolation
DC-14 Control of D.C. electromagnetic loads having economy resistors in the circuit
DC-22 Switching of mixed resistive and inductive loads, including moderate overloads (i.e. shunt
motors)
Utilization
Typical Application
Category
AC-1
These are primarily non-inductive loads or loads having a
power factor greater than 0.95. Making and breaking for these
loads are easier. Example: Resistive heaters,.
AC-3
AC-3 category primarily applies to squirrel cage induction
motors. These motors have an inrush current of 5 to 8 times its
rated current during start. At that instant, the terminal voltage
may drop to 20% of the line voltage. Therefore contactors
manufactured for AC-3 loads should be capable of such a high
current. The breaking can be easy.
AC-4
Like the AC-3 category, AC-4 is also applied to start and
breaking of squirrel cage induction motors. But in this case,
the breaking is more severe than that of the AC-3 category.
This category applies to induction motors that require inching
or plugging operations.
REQUIREMENT OF MATERIALS OF 3MW TG SET FOR ERECTION AND
COMMISIONING
1. Busbar duct from alternator to main incoming supply panel 6000 Amp.Length- 15
mtr. (approx.)
2. Main incoming supply ACB panel 4000 A with complete control & protection.
3. PCC panel with APFC for distribution of power supply.
4. Busbar duct from old power house to new power house approx. length 75mtr for
distribution of supply
5. Online UPS and battery charger with batteries.
6. EOT Crane complete in all respect.
7. LED lights and lighting cables.
8. Power cables for distribution of power supply from feeders.
9. Control & Gauge panel for 3MW TG set.
10. Main Steam line and Exhaust line.
11. Steamline Valve and Exhaust line valve and water line valve.
12. All drain valve and Traps.
13. MS pipe, angle,channel,plate for erection and commissioning.
14. Steam line spring support as per drawing.
15. Steam separator.
16. Paint for equipment and structure.