MECHANICAL INSPECTION DEFICIENCY REPORT

TAG ID: GB / T14976-2005 (SPOOL ID) DATE: 27-10-2023 REPORT #: MIDR FFI-011

GENERAL INFORMATION
Equipment Tag: 48-TK-10 Equipment Name: ZINC REMOVAL TANK

Description: FLANGE FACE INSPECTION Inspection Date: 27-10-2023

DESCRIPTION OF DEFICENCIES
1. Flange raised face serration damaged noticed on both flanges of the elbow
2.
3.
4.
RECOMMENDED ACTION
ACTION
INTEGRITY
DEFICENCIES# LEAVE PERFORM COMMENTS
REPLACE ASSESSMENT
"AS-IS" REPAIR
REQUIRED
The damaged area of the flange faces shall be re-built up
1.  and re-machining shall be done as per the standard.

2.

3.

4.

FOR THE REPAIR


YES NO COMMENTS

It is pressure vessel equipment 


Need welding procedure 
INSPECTION PERFORMED BY
QC INSPECTOR ✓ CONTRACTED INSPECTOR
Ajimon/Dhanesh
27-10-2023
Print Name Signature Date

DEFICIENCY REPORT ISSUED TO


Name Position Date
Gorba QA/QC Mechanical 27-10-2023
PHOTOS

Fig 1 : General view of the flange Fig 2 Damage areas close view

Fig 3 : Serration Damage identified on flange face area Fig 4 : Serration Damage identified on flange face area

RECOMMENDED ACTION COMPLETED


Comments:
Details repair:

PHOTOS

SIGNATORIES

Name (printed) Signature Date Comments


Mechanical QC
PV Inspector
Inspection Specialist
Chief Inspector