Professional Documents
Culture Documents
Document 03-150000-4100001496-SPM-
Contractor M/s. Shapoorji Pallonji Mideast L.L.C ELE-MST-000005_01
submittal no.
Contract no. 4100001496 Date 09/01/2022
To PMC PARSONS
Signature
PMC’s comments
Received by Contractor
Name Date
Signature
03-150000-4100001496-SPM-ELE-MST-000005_01 1
MAIN DOCUMENT TYPE
METHOD STATEMENT FOR INSTALLATION OF WIRING DEVICES
“03-150000-4100001496-SPM-ELE- MST- 000005 " " Rev 01 " " Jan - 2022"
03-150000-4100001496-SPM-ELE-MST-000005_01 2
Document history
Document approval
03-150000-4100001496-SPM-ELE-MST-000005_01 3
NEOM CIRCULAR CITY WATER RESERVOIRS
Method statement
For
Installation of Wiring Devices
Employer
NEOM
Project Management:
PARSONS
Main Contractor
SHAPOORJI PALLONJI MIDEAST LLC...
Regional office :- Rah mania, Takacs’s St. Opp. Saudi Telecom, P.O Box 300587,Riyadh 11372. Tel + +966 11
464 2487, Fax +966 11 2791928, http://www.shapoorji.in
01 9th Jan 2022 Issued for Approval Mr. Ahmed Elsheikh Mr. Jayanta
(Sr. MEP Sadhukhan (QA/QC Mr. Sunil Krishna
Coordinator ) Manager) (Project Director)
Prepared By Reviewed By Approved By
Rev. Submission. Description
Date
SPML SPML SPML
03-150000-4100001496-SPM-ELE-MST-000005_01 4
NEOM CIRCULAR CITY WATER RESERVOIRS
CONTENTS
S. Item Page
No No.
1 Introduction 3
2 Scope of works 3
3 Reference Document 3
4 Abbreviations 3
5 Responsibilities and Supervision 4-5
6 Materials 5
7 Procedure 5-6
8 Safety Requirements: 7
9 Housekeeping 7
11 Distribution 7
03-150000-4100001496-SPM-ELE-MST-000005_01 5
NEOM CIRCULAR CITY WATER RESERVOIRS
1. INTRODUCTION:
1.1 The Scope of this method statement is to define the procedure that will be followed
for the Installation of wiring devices including wires termination for ROSHN Villas
Project.
1.2 Prior to any works taking place all operatives will be inducted and trained on the type
of method in which they are carrying out the installation of wiring devices including
wires termination.
1.3 All material will be delivered in line with approved materials submittal and inspected
as per project protocols. Installation practices that are compliant with project safety
plan and associate's safety procedure compliance.
2. SCOPE OF WORKS:
This method statement defines the general procedures to be carried out for the installation of wiring
devices including wires termination for the NEOM Projects.
3. REFERENCE DOCUMENTS:
• Approved Shop Drawing, Coordination Drawing & Materials submittals
• Contract Specification (Appendix C4 Specification – Electrical)
• Approved Project Quality Plan (03-360000-4100001496-SPM-QMN-PLN-000001)
• Approved HSE Plan (03-360000-4100001496-SPM-HSE-PLN-000001)
• Approved ITP & Checklist (03-150000-4100001496-SPM-CIV-ITP-000003)
4. ABBREVATIONS:
Project : Neom Circular City Water Storage Reservoirs
Employer : NEOM, KSA
PMC : PARSONS (Consultant/Project Management) .
Contractor : Shapoorji Pallonji Mideast LLC (SPML)
PQP : Project Quality Plan.
MST : Method Statement.
ITP : Inspection & Test Plan.
ITL : Independent Testing Laboratory.
PVC : Polyvinyl chloride
WIR : Work Inspection Request.
MIR : Material Inspection Request.
HSE : Health, Safety & Environment.
QAQC : Quality Assurance/Quality Control.
IFC : Issued for Construction.
SD : Shop Drawing.
RA : Risk Assessment.
S/C : Sub Contractor
TBT : Tool box talk
PM : Project Manager
03-150000-4100001496-SPM-ELE-MST-000005_01 6
NEOM CIRCULAR CITY WATER RESERVOIRS
PD is responsible for the overall execution of the work; prior to the commencement of the
works, the approved shop drawings will be reviewed by construction management team. The
project document control department will ensure the latest revision and controlled copy of
drawing are issued to site. All relevant technical information will be communicated to personnel
in –charge of the construction, coordinate with surveyor, site Engineer to ensure that the
necessary resources and equipment’s including tools and tackles are provided to implement the
works in an acceptable manner as per the approved documents, MS and ITPs, check list and also
to ensure all construction staffs comply with Engineer’s quality, Health, Safety and
Environmental Management System requirements. He also ensures that MS and ITP fir the
scope of works are prepared and approved by Engineer prior to execution. He shall ensure that
all works are executed as per approved materials for construction purpose and shall also inform
the QC engineer at site prior to commencement of any new activities at site.
QC Engineer will manage and coordinate the inspection and testing in accordance with ITP and
responsible for ensuring all the activities are carried out as per this method statement,
manufacturer recommendation. He shall ensure the controlled copies of the drawings only using
at site, which are issued to the site supervising team. He is responsible for reviewing WIR for all
the related day to day activities at site as per the approved ITP and attending all the required
day to day inspection along with Project engineer, site engineer and the engineer’s
representative for approvals.
MEP engineer, supervisors & foreman is responsible for ensuring that the workforce is aware of
the quality control procedures and safety requirements and responsible for executing the works
as per approved IFC drawings/ SD, project specification and method statement. MEP Engineer
will raise Work inspection request (WIR) to the QC dept. at appropriate stages of the work as
per approved ITP. WIR’s should be raised at least 24 hours in advance to the required time of
inspection. Site engineer is also responsible to fill the inspection checklist and handover to QC
engineer.
03-150000-4100001496-SPM-ELE-MST-000005_01 7
NEOM CIRCULAR CITY WATER RESERVOIRS
5.5 SURVEYOR
Surveyor is responsible to ensure the location, levels and alignment of each concrete element
and shall comply with approved IFC drawings, project specifications & related Authority
Drawings and also responsible for internal coordination with Site execution team about day to
day survey activities. Site Engineer is responsible to confirm the co-ordinates, levels are as per
IFC drawings
HSE engineer is responsible for ensuring the activities are carried out as per project specific
safety plan and regulations and all the works shall be executed as per approved HSE plan and
work permit.
6 MATERIALS:
Materials shall be brought to site along with proper documents such as delivery note and
test certificate. Material to be supplied to site as per the daily requirement.
7 PROCEDURE:
7.1. Materials Handling and storage:
7.1.1 On receipt of the wiring devices and accessories at site, necessary precautions shall
be taken for unloading, shifting, storage and preservation.
7.1.2 Wiring devices shall be stored indoors in a covered / dry space at all the time. Good
ventilation shall be ensured.
7.1.3 All materials received at site shall be inspected upon MIR raised for inspection and
ensure that the materials are as per approved materials submittal.
7.1.4 Any discrepancies, damage etc., found will be notified and reported for further action.
7.1.5 Ensure that all materials have passed upon receiving inspection [MIR]. Any non-conforming
materials must be labeled and returned to specified redundant area
7.2.1 Ensure that the work area is ready and safe to start the installation of wiring devices
and accessories. All safety precautions/ measures have been taken as JSA of this activity
7.2.2 Ensure that the civil works including finishing are completed for the area of installation
and released/cleared from civil section to proceed on, with the installation of wiring devices
and accessories.
7.2.3 Ensure that wiring devices and accessories are received at site as per approved
materials submittal.
7.2.4 Prior to start of installation, refer to the latest Approved Shop Drawings related to the
area of installation and ensure that required materials are available at the site.
7.2.5 Ensure that installed wiring type and size are as per latest approved shop drawings
and load schedule.
03-150000-4100001496-SPM-ELE-MST-000005_01 8
NEOM CIRCULAR CITY WATER RESERVOIRS
7.2.6 Wiring devices shall be installed after the inspection of wire pulling, Meggar test shall
be tested at 500V.
7.2.7 Ensure that all boxes are clean from cement stains and foreign materials. Cross verify
the back boxes location as per shop approved drawing.
7.2.8 Before Installation check the ratings of sockets, switches, shall be as per approved
shop drawing. Weather proof switches / sockets shall be provided wherever applicable as per
the approved drawing.
7.2.9 Ensure that Devices earthing connections shall be made by means of screw-type
pressure connectors to the box’s frame and receptacle earth pin.
7.2.10 Ensure the clearance or Gap between wiring accessories in the same wall (or location)
are as per approved shop drawings & Elevation. Adjust wiring devices to operate in the
indicated and required sequence as per approved shop drawing. Height of switch and sockets
are as per approved Elevation drawing.
7.2.11 Ensure that Mounting screws and stealing caps to be fixed properly.
7.2.12 Earthing wires should be connected to earth terminals..
7.2.13 Install wall switches with “OFF” position down and upward position when in the “ON”
position.
7.2.14 Ensure that finishing plates should be as per approved material submittals and
Approval MIR. Device plates shall be installed with all four edges in continuous contact with
finished wall. .surfaces Device plates shall be installed vertically with an alignment with Arch
discipline.
7.2.15 Alignment of wiring accessories should be check by spirit level.
7.2.16 Ensure all wire terminals shall be checked to assure tight connection, electrical
continuity and for short circuit.
7.2.17 Prior to fixation of cover / Face plate and shall be submit the WIR.
7.2.18 All wiring services shall be clean before energizing. Test all Socket outlets etc. For
correct polarity, Termination and device fixation.
7.2.19 Test all socket outlets for instantaneous tripping of associated distribution board
current operated earth leakage circuit breaker using testing equipment.
7.2.20 Polarity test should be conducted after energization of sockets.
7.2.21 Identification of switch socket shall be done.
03-150000-4100001496-SPM-ELE-MST-000005_01 9
NEOM CIRCULAR CITY WATER RESERVOIRS
9. HOUSEKEEPING:
• Workplaces where MEP personnel are working will be cleaned from the scrap
materials derived from their work ensuring clean and healthy work environment as
well as to maintain free access and egress in the event of emergency.
insulation remover
4 Meggar Tester, Multi- Meter, Polarity Tester As Required
No.
1 Site Supervisor As Required 4 Labour As Required
2 Foreman As Required
3 Electrician As Required
11. DISTRIBUTION: -
Copies of this Method Statement shall be circulated to the following for Information &
action.
• Project Director
• Sr. MEP Coordinator
• QC Manager
• MEP Engineers
• QC Inspectors
• HSE Officers
• General Foremen
• Surveyor
• Concrete coordinator
03-150000-4100001496-SPM-ELE-MST-000005_01 10
NEOM CIRCULAR CITY WATER RESERVOIRS
13. ATTACHMENTS:
03-150000-4100001496-SPM-ELE-MST-000005_01 11
NEOM CIRCULAR CITY WATER RESERVOIRS
2 Ensure that all boxes are clean from cement stains and foreign materials
3 Check the ratings / Type of sockets, switches, shall be as per approved shop drawing
4 Check the installation / Height of switch and sockets are as per approved Shop
Drawing.
5 Ensure the circuit have been maggered.
7 Check the Wiring connection completed to switch / socket & polarity is correct.
8 Check the earthing wire connect properly with all the devices.
The above points have been checked and found to comply the projects requirements and contact specification.
Name:
Signature:
Date:
03-150000-4100001496-SPM-ELE-MST-000005_01 12
RISK ASSESSMENT
RISK ASSESSEMET FOR RA for general installation of Date
Reference No.: Embedded PVC Conduit end RSC, EMT, Metal Flexible
Steps 08/01/2022
Revision No.: 1 Conduit & Liquid Tight and Earthing System
Activity Hazards IMPACT Risk Risk Control Measures Risk Who is Responsible
Ranking Rankin
g
L C R L C R
.
1 Transportation Traffic Equipm 3 3 9 1 3 3 Site Engineer
and unloading ent Assign the qualified driver, operator and
of materials to Accidents failure, signalman
site
Material fell Physical
Prepare work Obey traffic rules & regulations (speed
Injury,
area limits, lane discipline, signage etc.
Unauthorized
untrained workers Fatality,
Make sure the access road and the
Property unloading roads are clear and level
Damage Logistic Manager
Inspected equipment to be used for
Cuts unloading. Use trained flagman to control
. the equipment.er.
Abrasio
ns
Do not stay in the line of fire area.
Secure the load with come alone to
avoid collapse/fall of materials
Page 1 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 13
foreman/safety officer Prior to work
commencement.
. Task specific safety ranging to be
provided.
2 Damage to Manual 1 3 3
musculoskeletal system handling Required approved permit shall be
of the body. injuries acquired from designated permit issuer
prior to start of execution.
Manual •Musculoskeletal serious
Handling disorders from repetitive implicati
(Preparation ons All works involved in this activity shall be
manual handling. covered by permit in Site Management,
and hauling of person 5 4 20 Supervisor,
necessary accordance to NEOM Work Permits
Injuries from fall of loads Foreman,
tools and Injured.
equipment) on body parts.
Coordination and communication from
awkwar
Personal injuries while d
respective counterpart and other parties
handling/ shifting of shall be observed prior to commence
postures
materials , any scaffolding works
repetitiv
Page 2 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 14
Slips, trips and falls e Approved Permit Receiver shall process
when handling/ shifting moveme the permit.
of materials nts of
Unauthorized work arms,
legs Daily TBM shall be conducted to make
execution.
sure all employees aware of the hazards
Incorrect lifting of loads previous for their daily construction activities.
/existing
Shape gdges
injury Ensure all safety requirement mentioned
can in the work permit is available at jobsite.
increase
Placing the object while the risk
Vehicle movement shall follow the speed
Fingers undemeath Back limit (less than 10km/h)
injuries
Slip/trip/fall (same level) PTW for the activity available at site with
. Cut to RA &MS
unsafe posture finger
Skilled employees for the activity
. Strain
Execution and HSE supervision made
Musculo
available
skeletalI
njuries
Proper use of PPE’s
03-150000-4100001496-SPM-ELE-MST-000005_01 15
project and destination points should be
known to the working crew prior to start
the task.
Page 4 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 16
Grip the object firmly and pull it close to
you.
Page 5 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 17
3 Unloading and Slips, trips Serious 3 4 12 All waste materials to be removed from 1 4 4 Site Engineer
shifting personal the work area as soon as possible –
Falls injury, or before break times and the end of the Site Foreman
other shift.
Unauthorized unwanted Workers
Untrained Workers. situations All trailing cables to be positioned above
Fatality head height when possible.
. Lifting failure
. Fractures
. Property Ensure all materials are delivered to the
Damage site with the aid of mechanical means
. unsafe lifting . Injury to when possible.
Swinging of material personal . Pre check to be carried out by the
. Sprain and operator prior to start the work to ensure
Damaged single wire strain that no hydraulic leaks or other visible
rope or chai . Crush damages seen.
. Cuts . Ensure the crane and forklift engaged is
Poor maintenance
tested and having vailed licenses and the
Of vehicle.
operators has a vailed licenses and
approved 3rd party certificate.
.Speedy operation
. Barrication and warning sings shall be
provided for the area where lifting
. Over turn operation is a carried out restrict the entry.
. Use tagline for control of swings and
. Over load alignment.
. All lifting equipment’s and gears shall
Poor Communication having vailed third party certificate.
Poor lifting
. The crane must be stopped when the
wing speed exceeds 38 km/hr.
. Never exceed the SWL marked on the
crane.
. All load shall be secured prior to lifting.
. The crane and trucks inspection shall be
conducted periodically and record
maintained.
. Vehicle routs kept free of obstrucllons
(with spillages being cleaned up prompt).
Page 6 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 18
. Operator should follow the site speed
limit and obey
The traffic rule.
. Color coded system to be implemented
to all lifting
Equipment’s as per the month.
. Close supervision to be done at all time.
5 Operating of Rollovers Minor to 3 5 15 The operator and the equipment’s must be 3rd 1 5 5 Site Engineer
heavy Struck by moving major party certified and the certificates must be
equipment equipment. injuries and displayed or present in the equipment. Site Foreman
fatality.
Unit with using Crushed between The operators must trained and experienced Workers
forklift or equipment and other person.
crane objects.
The operator must inspect their area and must
Subjected to electrical be fully aware of the surroundings.
contact while operating
a vehicle or equipment. A toolbox talk must be conducted by the
supervisor In presence of safety person.
Struck or crushed by
equipment tipping PTW must be signed by each and every one
over. involved in the operation and must be briefed
in their native language by the site supervisor.
Page 7 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 19
Daily inspection checklist must be filled by the
operators.
Page 8 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 20
Appropriate Fire extinguisher must be
available in the equipment must be inspected
and registered.
6 Installation of Untrained, unauthorized Cut and 3 3 9 . Competent team shall be involved to 1 5 5 Site Engineer
unit workers. abrasion execute the activity Work location shall be
. Material fall . Back inspected by concerned Site Foreman
. Sharp edges injuries supervisor/foreman.
. Unsafe posture. . Fatigue . Close supervision to be done at all times.
. Slip, trip and fail .Musculosk . Materials should not kept in walkways,
eletal edge of the opening.
injuries . Deploy enough number of personal for
material lifting shall be appointed to the
task depending upon the distance.
. Manufacture recommendations shall be
followed during the installation.
Page 9 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 21
. Proper communication to be maintained
between the workers while doing the
installation.
. maintain a good housekeeping police to
prevent from slip, trip fall hazards.
. Safe and obstruction free access for
working personals shall be maintained at
all times.
. Emergency evacuations plan shall be
ready available according to site condition
and briefed to the workforce prior to start.
. Trained first aider, fire warden and
emergency vehicle to be available at the
site during the activity.
. Emergency contact numbers shall be
displayed at work location for easy
communication.
. PPE to be wom at all times (gloves,
goggles, mask, helmet, shoe, vest, coverall).
Slip, trip and fall . Fatigue 3 3 9 . Defective tools should not be issued or 3 3 9
. Damaged/whom out . Trigger used to perform the task, to be checked by
hand tools. finger store keeper
. Flying objects . Cuts and . Don’t extend the spanner by using a pipe
. Mushroom heads abrasions as an extension bar
Prepare work . Using incurred type . Hand tools shall be free from oil, grease &
area etc.
. Never use a file as a lever
Never use a screw driver as a chisel
. Use eye/face protection, wear gloves
while required to protect the hands
. Use right tools for the job
Page 10 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 22
9 Vehicle movement. Slip, Overturning 3 3 9 3rd party Competent operator with 3rd party 1 3 3 Site Engineer
trip and fall of Crane. approved equipment. Operator to adhere to
. Damaged/wom out Vehicular speed limit. Site Foreman
accident/ Provision of pedestrian segregation from
hand tools. hitting vehicle. logistic
. Flying objects person or Provision of banks men/ flagmen at critical
Manual . Mushroom heads property locations.
Handling Use . Using incurred type damage Defective tools should not be issued or
of hand tools Fatigue used to perform the task, to be checked by
(Torque . Trigger store keeper
wrench finger . Don’t extend the spanner by using a pipe
spanner, nail . Cuts and as an extension bar
puller, abrasions . Hand tools shall be free from oil, grease &
cutter). etc.
. Never use a file as a lever
Never use a screw driver as a chisel
. Use eye/face protection, wear gloves
while required to protect the hands
. Use right tools for the job
Mechanical Failure of Collapse, 3 4 12 Provision of competent operator and 1 4 4 Site Engineer
mobile crane Overturning supervisor.
Unloading of crane Equipment should be tested and certified Site Foreman
and shifting from approved third party. SWL should be
of Busway marked. Avoid overloading. Never exceed logistic
SWL and ensure all limit switches are in
Unit with operating condition. All the out riggers must
using forklift be fully extended. Ensure sufficient
or crane illumination during operation.
Ensure all limit switches are in good
operating condition.
Failure of lifting tackles. Property 3 4 12 Use only third party certified tools & tackles. 1 4 4 Site Engineer
Stanching and (Master ring/D or Bow damage, Inspect tackles prior to use.
shackles /Slings(Wire serious Mark SWL on all the tackles & ensure that its Site Foreman
Storing injury, SWL is always higher than the load to be
rope, Belt, Chain) etc.
fatality. lifted. logistic
Page 11 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 23
Competent person should do placing and
fixing of tackles.
Provide adequate cushioning in between to
protect sling from sharp edges when required.
Sling angles should not be more than 90
degree in any case. (Angle between sling
legs).
3 5 15 All lifting gears should be color coded, tested 1 5 5 Site Engineer
Fall of material during Property and certified from approved third party.
lifting damage, Ensure right type of lifting gear is used for Site Foreman
serious the job
injury, Ensure load is secured properly; material; Logistic
fatality. Use lifting cage/basket certified by third party
for lifting of blocks/cement bags/ loose Workers
scaffolding materials like clamps, jacks and
Installation of base plats etc. Use lifting bucket certified by
Busway unit third party for lifting sand/lowering or removal
of construction waste. Ensure the area is
barricaded no trespasser allowed during
lifting.
3rd part certified riggers must be assigned for
securing loads and communication setup with
the operator.
No person allowed being standing under a
suspended load.
Hydraulic fluid and other Health 3 3 9 Regular inspection and maintenance of 1 3 3 Logistic
lubricant spillage problems equipment. Provision of emergency
Use of hand due to arrangement in case of spillage( dip trays or
tools (Torque exposure to plastic sheets)
wrench chemicals Proper disposal of contaminated material
e.g. (rags oil or plastic sheets) as per local
spanner, nail dermatitis regulation, at designated disposal facilities.
puller, due to
cutter). prolonged
contact with
the skin,
Page 12 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 24
respiratory
illnesses.
Environment
al impact
contaminatio
n of land
and water.
10 Handling of Heavy materials, sharp, Hand 3 3 9 Materials to be loaded in/out close to the 1 3 3 Site Engineer
Materials hot, wrong posture Injuries/ point of lift. Site Foreman
back Mechanical aid to be used where possible.
injuries, loss Gloves to be worn when handling materials
time, delay that are likely to cause injury to hands.
in work Ensure competent , trained and experienced
progress person perform the task
Strain and Route of carriage of materials to be clear
sprain from tripping hazards/ obstructions. Materials
injuries not to be lifted above people.
All materials to be stored in a safe manner
on a suitable surface.
All workers must have sort of information
about the objects being used or lifted.
Falls of materials Serious 4 4 16 Post warning signs and work within the 1 4 4 Site Engineer
personal sealed off area Site Foreman
injuries / All raising and lowering of materials to be
fatality carried out in a controlled manner i.e. Hand
Property to hand, by light-line and fitting bags.
damage Supervision and monitoring must be
Financial available all time.
loss All tools to be always tethered. However,
when using heavier tools, an exclusion zone
will be set around the working area.
All workers must be trained in their desire
task and Toolbox talk should be delivered
prior start working
Page 13 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 25
11 Manual Over exertion Slip, trip and 3 3 9 Personnel shall be briefed/trained on proper 1 3 3 Site Engineer
Handling Fall hazards fall related manual material handling techniques.
injuries. Demonstrates how to do manual lifting. Site Foreman
Legs shall carry the weight not the back
Workers
Do not bend the back while picking up a load,
keep the back straight
12 Material Inappropriate material Minor or 3 3 9 Materials to be stored in a designated area, 1 3 3 Site Engineer
storage storage. major injury, do not stock materials in access or escape
property routes. Site Foreman
damage.
Materials to be stored on stable level base to Workers
avoid from toppling down.
Page 14 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 26
After removal of the platform should be shifted
to assigned area.
Use of hand tools Minor cut 3 3 9 All hand tools must be inspected, and color 1 3 3
and injury coded prior to use. Site Foreman
Use eyes & Hand protection while using
hand tools. Workers
All damaged tools must be removed from site
immediately.
No handmade tools to be used on site.
Use only suitable and inspected approved
tools for the task
Use tools as per manufacturer’s instructions
Wear suitable PPE as per NEOM standards
Check tools for damage before use
Damage tools store in safe lock room to
restrict it usage
Operatives must be trained when using all
tools
Task specific Toolbox talk to be carried out for
daily tasks
Exercise caution always.
No lone working.
Usage of power tools Electrocutio Allow only competent person to perform the
n, injury, 3 4 12 job. 1 4 4 Site Engineer
damage to
property All power tools must be in good condition. Site Foreman
Page 15 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 27
All power tools must have dead man’s
switch.
Page 16 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 28
Power tools used must be routed through
ELCBs of 30 mA tripping current
Using of grinder machine Electrocutio 3 4 12 Grinder must be inspected, color coded and 1 4 4 Site Engineer
n , Burn, fire registered by the competent person.
or Major Site Foreman
Injury, trip The task shall be carried out by the
and fall competent and trained person. Workers
Page 17 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 29
machine and grinder wheel for the maximum speed
and cause that it can be used.
injury.
To reduce risk of vibration syndrome, the
Contact with operator may work 20 min and can take 10
disc/ mins break.
entangleme
nt causing check that the wheel speed (rpm) marked on
cuts severe the wheel is equal to or greater than the
laceration maximum speed of the grinder
due to
contact with Follow manufacturer’s manual for the safe
grinding or use of grinder wheel guards.
cutting disc.
Ensure that a machine will not operate when
Eye injuries unattended by checking the dead-man
caused by (constant pressure) switch.
shattering or
other Exclusion zone shall be set around to
particles prevent un authorized entry.
Page 18 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 30
Insufficient Keep the power cord away from the grinding
space wheel.
around the
machine Use racks or hooks to store portable
may result in grinders.
operator
pushed by Appropriate fire extinguisher to be present
passers nearby.
Page 19 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 31
16 Interface with Lack of coordination and Injury, loss 3 3 9 Coordination meeting to be set up when 1 3 3 Site Engineer
other communication Exposure of time, possible.
subcontractor to unknown hazards from delay in Project plans review by all parties Site Foreman
activities activities by others work Communication between various contractors
progress encouraged on supervisory level.
Signage, barriers to be put in place to mark
the work locations where activities can be
hazardous to others.
Operatives to be briefed by all site.
Severity of Risk
Page 20 of 20
03-150000-4100001496-SPM-ELE-MST-000005_01 32