Document 03-150000-4100001496-SPM-
Contractor M/s. Shapoorji Pallonji Mideast L.L.C ELE-MST-000007_01
submittal no.
Contract no. 4100001496 Date 10/01/2023
To PMC PARSONS
Approval Comments
Information Other
Signature
PMC’s comments
Received by Contractor
Name Date
Signature
1
03-150000-4100001496-SPM-ELE-MST-000007_01
METHOD STATEMENT
METHOD STATEMENT FOR INSTALLATION OF SOLAR LIGHT
POLE
2
03-150000-4100001496-SPM-ELE-MST-000007_01
Document history
Document approval
3
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
Method statement
For
Installation of solar light pole
Employer
a) NEOM
b) Project Management:
c) PARSONS
Main Contractor
d) SHAPOORJI PALLONJI MIDEAST LLC...
Regional office :- Rah mania, Takacs’s St. Opp. Saudi Telecom, P.O Box 300587,Riyadh 11372. Tel + +966 11
464 2487, Fax +966 11 2791928, http://www.shapoorji.in
01 10th Jan 2023 Issued for Approval Mr. Yahatesham Mr. Jayanta
Jahagirdar Sadhukhan (QA/QC Mr. Sunil Krishna
(Sr.Electrical Manager) (Project Director)
Engineer)
Prepared By Reviewed By Approved By
Rev. Submission. Description
Date
4
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
CONTENTS
S. Item Page
No No.
1 Introduction 3
2 Scope of works 3
3 Reference Document 3
4 Abbreviations 3
5 Responsibilities and Supervision 4-5
6 Materials 5
7 Procedure 5-6
8 Safety Requirements: 7
9 Housekeeping 7
11 Distribution 7
II.
5
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
1. INTRODUCTION:
1.1 The Scope of this method statement is to define the procedure that will be followed
for the Installation of Solar light pole installation for NIC water reservoir
Project.
1.2 Prior to any works taking place all operatives will be inducted and trained on the type
of method in which they are carrying out the installation of solar light pole installation for
NIC water reservoir projects at NEOM.
1.3 All material will be delivered in line with approved materials submittal and inspected
as per project protocols. Installation practices that are compliant with project safety
plan and associate's safety procedure compliance.
2. SCOPE OF WORKS:
This method statement defines the general procedures to be carried out for the installation of Solar light
pole at NIC water reservoir, NEOM.
3. REFERENCE DOCUMENTS:
Approved Shop Drawing, Coordination Drawing & Materials submittals
Contract Specification (Appendix C4 Specification – Electrical)
Approved Project Quality Plan (03-360000-4100001496-SPM-QMN-PLN-000001)
Approved HSE Plan (03-360000-4100001496-SPM-HSE-PLN-000001)
Approved ITP & Checklist (03-150000-4100001496-SPM-CIV-ITP-000003)
4. ABBREVATIONS:
Project : Neom Circular City Water Storage Reservoirs
Employer : NEOM, KSA
PMC : PARSONS (Consultant/Project Management) .
Contractor : Shapoorji Pallonji Mideast LLC (SPML)
PQP : Project Quality Plan.
MST : Method Statement.
ITP : Inspection & Test Plan.
ITL : Independent Testing Laboratory.
PVC : Polyvinyl chloride
WIR : Work Inspection Request.
MIR : Material Inspection Request.
HSE : Health, Safety & Environment.
QAQC : Quality Assurance/Quality Control.
IFC : Issued for Construction.
SD : Shop Drawing.
RA : Risk Assessment.
S/C : Sub Contractor
TBT : Tool box talk
PM : Project Manager
6
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
Project Director is representative for the top management of SPML at the projects in NEOM. He
is officially responsible for managing, monitoring, controlling the project construction further to
hand over on time. All relevant technical information will be communicated to personnel in-
charge of the construction, coordinate with surveyor, site engineer to ensure that the necessary
resources and equipment’s including tools and tackles are provided to implement the works in
an acceptable manner as per the approved documents, MS and ITPs, check list and also to
ensure all construction staffs comply with Engineer’s Quality, Health, Safety and Environmental
Management System requirements. He also ensures that MS and ITP for the scope of works are
prepared and approved by the Engineer prior to execution. He shall ensure that all works are
executed as per approved IFC drawings. PM is also responsible for identifying and using only the
approved materials for construction purpose and shall also inform the QC Engineer at site prior
to commencement of any new activities at site.
7
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
CM is responsible for the execution of the activity in accordance with the manufacturer
recommendation, MS, and HSE plan. He is responsible for preparation of site execution drawing,
job safety analysis and application for work permits if required prior to commence of Concrete
works. He will ensure the approved material being used at site and conducting necessary tool
box talks and training to crew and responsible for ensuring all the activities are carried out as
per this method statement, manufacturer recommendation. He shall ensure the controlled
copies of the drawings only using at site, which are issued to the site supervising team.
Site engineer, supervisors & foreman is responsible for ensuring that the workforce is aware of
the quality control procedures and safety requirements and responsible for executing the works
as per approved IFC drawings/ SD, project specification and method statement. Site Engineer
will raise Work inspection request (WIR) to the QC dept. at appropriate stages of the work as
per approved ITP. WIR’s should be raised at least 24 hours in advance to the required time of
inspection. Site engineer is also responsible to fill the inspection checklist and handover to QC
Inspector.
5.5 QC ENGINEER/INSPECTOR
QC Engineer will manage and coordinate the inspection and testing in accordance with ITP and
responsible for ensuring all the activities are carried out as per this method statement,
manufacturer recommendation. He shall ensure the controlled copies of the drawings only using
at site, which are issued to the site supervising team. He is responsible for reviewing WIR for all
the related day to day activities at site as per the approved ITP and attending all the required
day to day inspection along with Project engineer, site engineer and the engineer’s
representative for approvals.
5.6 SURVEYOR
Surveyor is responsible to ensure the location, levels and alignment of each concrete element
and shall comply with approved IFC drawings, project specifications & related Authority
Drawings and also responsible for internal coordination with Site execution team about day to
day survey activities. Site Engineer is responsible to confirm the co-ordinates, levels are as per
IFC drawings.
Conducts safety meetings, audits, and inspections to ensure compliance, evaluate performance,
identify corrective action, and implement follow up assessments.
Plans, implements, and conducts preventative care, safety, and compliance training programs.
8
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
Plans, implements, manages, and maintains comprehensive environmental safety & health
programs on premises or at project site locations.
Provides project management team with guidance on health and safety and confirm project site
fulfills industry, local, state, and federal guidelines, and regulations.
Collaborates with management to develop an Emergency Action Plan and serve as primary
contact for project site injury and incident notification, investigation, and case management.
Maintains a written log of safety inspection activities, reports, and correspondence.
Guarantees that all work is performed in accordance with approved manuals, internal policies
and procedures, contract documents, and good engineering practices.
Provides technical support to project managers.
Develops and maintains project cost/change controls, and project budget and accounting
records. Coordinates and monitors schedule updates, invoices, and submittals.
Reports the status of projects to business and market leaders.
Participates in team meetings and provides regular on-site project presence.
construction site safety supervisors perform a wide range of functions/duties in making sure
that construction sites or workplaces are always safe for the daily operation of workers.
Supervises day-to-day activities within a particular construction workplace
Ensures that workers make use of necessary protective equipment like helmets, hand gloves,
welding shades etc., where and when necessary
Investigates accidents and tackle their causes
Takes note of workers’ safety concerns and immediately acts on them
Arranges training programs on safety measures within the workplace
Develops plans for emergency procedures with the consent of the manager(s) of the workplace
Receives and acts on reports regarding safety concerns from workers within the construction
site/workplace
Serves as a link between workers and top management when it comes to issues that have to do
with the safety and proper organization of the workplace
Introduces measures that will help curb accidents within the workplace.
HSE engineer is responsible for ensuring the activities are carried out as per project specific
safety plan and regulations and all the works shall be executed as per approved HSE plan and
work permit.
JCB
Bobcat.
Plate compector
Water tanker – 5000 Gal
3 ton tripper
Man lift
9
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
7. MATERIAL:
Formwork,
reinforcing steel
Concrete
Plywood
White wood
Nail
Water proofing Material
Street light pole and fittings
8 PROCEDURE:
Number is wrong
7.1. Materials Handling and storage:
On receipt of the solar light & light pole at site, necessary precautions shall
be taken for unloading, shifting, storage and preservation.
Solar light shall be stored indoors in a covered / dry space at all the time. Good
ventilation shall be ensured.
All materials received at site shall be inspected upon MIR raised for inspection and
ensure that the materials are as per approved materials submittal.
Any discrepancies, damage etc., found will be notified and reported for further action.
Ensure that all materials have passed upon receiving inspection [MIR]. Any non-conforming
materials must be labeled and returned to specified redundant area
The foundation will be construct in dry conditions within the defined area where as per
approved layout.
Trim the bed of the desired levels and to create a suitable platform for construction
Blinding concrete will be done as per approve drawing and water proofing will be done
above the blinding.
10
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
Water proofing will apply for culvert face exposed to earth as per drawing and
specification.
Ensure the lighting pole is correctly assembled and fixed all accessories (Light fixture,
arms, PV panel, inbuilt battery etc). prior to lifting (all necessary attachments/fittings
are added and sections have been correctly joined)
Ensure all lifting tackle is checked for its capacity and adequacy for the weight of pole
being lifted.
Attach a single loop sling around the pole at approximately two thirds of the overall
height, taking care not to damage the pole finish (synthetic slings should be used for
painted product). The sling shall not be wrapped tight around the pole.
On the opposite side to the lifting side, attach a safety rope from the sling and attach
the other end to a hook which is to be hooked into the access door. Ensure the safety
rope is tight at all times. The purpose of the above arrangement is to prevent the sling
from slipping up the pole while at the same time transferring all force parallel to the
pole’s axis back through the base of the pole (preventing sections from accidentally
slipping apart). It is important that the sling is not tightly wrapped around the pole and
that the safety rope remains taut at all times. Note: It is the operator’s responsibility to
ensure that the safety rope remains taut and the hook remains in position at all times
until the pole is permanently secured to the footing.
Begin lifting the pole. After lifting the top of the pole approximately 1m above the
ground (base should still be supported on the ground), stop and check the
arrangement. Ensure that the safety rope is still taut and that the sling begins to rotate
around in-line with the lift. Continue lifting the pole ensuring that the safety rope
remains taut at all times and that the sling continues to rotate around. Carefully place
the pole on the foundation bolts. DO NOT release the load from the crane (safety rope
is to still remain taut) until washers and nuts are placed on all threads and initially
tightened.
Release the load from the lifting crane – the lifting sling should loosen and the safety
rope can be used to guide the lifting sling down the pole as the lifting crane cable is
run down.
Remove lifting tackle. Single Loop Sling Safety Rope Ensure always taut Check safety
rope is taut Hook into door before continuing lift.
Plumb the column using the adjusting nuts. It is more important to have the top of the vertical
part of the pole in line with the base of the pole rather than having the base plate level –
particularly so for poles with single outreaches and loading on one side which will exhibit a
natural ‘bowing’.
Tighten all nuts to the underside of the base plate and tighten down the corresponding
nuts above the base plate.
Fill the space between the base plate and the foundation with a non-shrink general
purpose construction grout
Clean up area.
11
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
9. HOUSEKEEPING:
Workplaces where MEP personnel are working will be cleaned from the scrap
materials derived from their work ensuring clean and healthy work environment as
well as to maintain free access and egress in the event of emergency.
12
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
insulation remover
4 Meggar Tester, Multi- Meter, Polarity Tester As Required
No.
1 Site Supervisor As Required 4 Labour As Required
2 Foreman As Required
3 Electrician As Required
11 ENVIRONMENTAL REQUIREMENTS:
13
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
14
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
11. DISTRIBUTION: -
Copies of this Method Statement shall be circulated to the following for Information &
action.
Project Director
Sr. MEP Coordinator
Sr. Electrical Engineer
QC Manager
MEP Engineers
QC Inspectors
HSE Officers
General Foremen
Surveyor
Concrete coordinator
15
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
12. All Calibration logs shall be updated for the measuring apparatus or testing equipment
using at site.
13. Weekly Quality Highlights shall be implemented along with Lesson Learnt Log.
14. All Lab Test Reports shall be submitted through Aconex on timely manner.
13. ATTACHMENTS:
6 Contractor shall implement procedures for handling, storage, and preservation of materials as
specified in all applicable specifications, manufacturer recommendations and company's
standards.
7 Light Fixtures shall be in accordance with the project-specific design drawings, diagrams,
schedules, lists, databases, IP degree of protection, solar light type and basic parameters as per
approved submittal..
8 Aluminum, steel, and fiberglass poles shall be provided with a suitable wiring compartment located
at a height of not less than 150 mm nor more than 900 mm from the base.
Outside area and street lighting shall be controlled by photocells
9
10 All Anchor bolts to be tight properly at the baseplate and cross arms by torque wrench as per
manufacturer recommendation.
The above points have been checked and found to comply the projects requirements and contact specification.
16
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
Name:
Signature:
Date:
17
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
18
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
19
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
20
03-150000-4100001496-SPM-ELE-MST-000007_01
NEOM CIRCULAR CITY WATER RESERVOIRS
21
03-150000-4100001496-SPM-ELE-MST-000007_01
Page 1 of 4
Team members
Risk Assessment Cons. Manager
For Solar light pole installation. Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities Solar light pole installation. Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 09/01/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 1 of 4 22
03-150000-4100001496-SPM-ELE-MST-000007_01
Page 2 of 4
Team members
Risk Assessment Cons. Manager
For Solar light pole installation. Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities Solar light pole installation. Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 09/01/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 2 of 4 23
03-150000-4100001496-SPM-ELE-MST-000007_01
Page 3 of 4
Team members
Risk Assessment Cons. Manager
For Solar light pole installation. Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities Solar light pole installation. Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 09/01/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 3 of 4 24
03-150000-4100001496-SPM-ELE-MST-000007_01
Page 4 of 4
Team members
Risk Assessment Cons. Manager
For Solar light pole installation. Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities Solar light pole installation. Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 09/01/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Name Name
Title Title
Sign Sign
Date Date
Page 4 of 4 25