ﺍﺗﺼﺎﻝ ﻏﻼﻑ ﺩﻭﺗﻜﻪ ﻛﺎﻣﻞ ) (F.E.S.Sﺭﺍ ﺑﻄﻮﺭ ﻣﺘﻌﺎﺭﻑ ﺑﺮﺍﺳﺎﺱ ﻛﻼﺱ ﻓﺸﺎﺭ ﻛﺎﺭﻱ ) ﻣﻄﺎﺑﻖ ﺑﺎ ANSI
( Flange Pressure Classﻃﺮﺍﺣﻲ ﻣﻲ ﻛﻨﻨﺪ ؛ ﺑﻌﺒﺎﺭﺕ ﺩﻳﮕﺮ ﺍﻳﻦ ﻧﻮﻉ ﺍﺗﺼﺎﻝ ﺩﺍﺭﺍﻱ ﻓﺸﺎﺭ ﻛﺎﺭﻱ ﺍﺳﺖ ﻛﻪ
ﺑﻪ ﻃﻮﺭ ﻣﻌﻤﻮﻝ ﺑﺮ ﺭﻭﻱ ﭘﻼﻙ ﻣﺸﺨﺼﺎﺕ ﻳﺎ ﺑﺪﻧﻪ ﺍﺗﺼﺎﻝ ﻣﻴﺰﺍﻥ ﻓﺸﺎﺭ ﺣﻚ ﺷﺪﻩ ﺍﺳﺖ .
ﺍﻳﻦ ﺍﺗﺼﺎﻝ ﭘﺲ ﺍﺯ ﺗﻨﻈﻴﻢ ﻭ ﻗﺮﺍﺭ ﮔﺮﻓﺘﻦ ﺑﺮ ﺭﻭﻱ ﻣﺤﻞ ﻣﻮﺭﺩ ﻧﻈﺮ ﺧﻂ ﻟﻮﻟﻪ ﺍﺑﺘﺪﺍ ﭘﻴﭽﻬﺎﻱ ﺗﻨﻈﻴﻢ ﻛﻨﻨﺪﻩ ﺁﻥ ﻛﻪ
ﻛﻤﻲ ﺑﻠﻨﺪ ﺗﺮ ﺍﺯ ﺳﺎﻳﺮ ﭘﻴﭽﻬﺎ ﻫﺴﺘﻨﺪ ،ﺑﺴﺘﻪ ﻣﻲ ﺷﻮﺩ ﻭ ﺳﭙﺲ ﺳﺎﻳﺮ ﭘﻴﭽﻬﺎ ﺑﺎ ﺭﻋﺎﻳﺖ ﺩﺍﺷﺘﻦ ﻓﺎﺻﻠﻪ ﺁﺯﺍﺩ ﻳﻜﺴﺎﻥ
ﺑﻴﻦ ﺍﺗﺼﺎﻝ ﺗﺎ ﺳﻄﺢ ﻟﻮﻟﻪ ﻣﺤﻜﻢ ﻣﻲ ﺷﻮﻧﺪ .
ﻧﻜﺘﻪ :ﺑﻠﺤﺎﻅ ﺩﺍﺷﺘﻦ ﻧﺸﺖ ﮔﻴﺮ ﻫﺎ ﺩﺭ ﺩﺍﺧﻞ ﺍﺗﺼﺎﻝ ﺿﺮﻭﺭﺕ ﺩﺍﺭﺩ ﻗﺒﻞ ﺍﺯ ﻧﺼﺐ ﺍﺗﺼﺎﻝ ﺩﺭ ﻣﺤﻞ ﺍﻗﺪﺍﻣﺎﺕ ﺯﻳﺮ
ﺻﻮﺭﺕ ﭘﺬﻳﺮﺩ :
-1ﺍﺗﺼﺎﻝ ﺗﻤﻴﺰ ﻛﺎﺭﻱ ﻭ ﻛﻠﻴﻪ ﭘﻴﭽﻬﺎﻱ ﺁﻥ ﺭﻭﻏﻨﻜﺎﺭﻱ ﻭ ﺭﻭﺍﻧﻜﺎﺭﻱ ﮔﺮﺩﻧﺪ .
-2ﺩﺭ ﺻﻮﺭﺗﻲ ﻛﻪ ﺍﺯ ﻣﺸﺘﻘﺎﺕ ﻧﻔﺘﻲ ﺑﺮﺍﻱ ﺗﻤﻴﺰ ﻛﺎﺭﻱ ﺍﺳﺘﻔﺎﺩﻩ ﺷﻮﺩ ؛ ﻛﻠﻴﻪ ﻗﺴﻤﺘﻬﺎ ﺍﺯ ﺟﻤﻠﻪ ﺩﺭﺯﻫﺎﻱ ﺩﺍﺧﻠﻲ ﺑﺎ
ﺟﺮﻳﺎﻥ ﻫﻮﺍﻱ ﻓﺸﺮﺩﻩ ﻛﺎﻣﻼ" ﺧﺸﻚ ﺷﻮﺩ .ﺩﺭ ﻏﻴﺮ ﺍﻳﻦ ﺻﻮﺭﺕ ﺿﻤﻦ ﺟﻮﺷﻜﺎﺭﻱ ﺑﺨﺎﺭﺍﺕ ﺧﺮﻭﺟﻲ ﺍﺯ ﺩﺭﺯﻫﺎ ﺁﺗﺶ
ﺧﻮﺍﻫﻨﺪ ﮔﺮﻓﺖ ﻭ ﺑﺎﻋﺚ ﺻﺪﻣﻪ ﺯﺩﻥ ﺑﻪ ﻧﺸﺖ ﮔﻴﺮ ﻫﺎ ﺧﻮﺍﻫﺪ ﺷﺪ .
-3ﺳﻄﺢ ﻟﻮﻟﻪ ﺍﺯ ﻫﺮ ﮔﻮﻧﻪ ﺯﻧﮕﺰﺩﮔﻲ ،ﺗﺮﺷﺤﺎﺕ ﺟﻮﺵ ) ، (Spatterﺭﻧﮓ ،ﺁﻟﻮﺩﮔﻲ ﻭ ﻟﻜﻪ ﭼﺮﺑﻲ ﻛﺎﻣﻼ ﺗﻤﻴﺰ
ﮔﺮﺩﺩ .
-4ﻃﻮﻝ ﺍﺗﺼﺎﻝ ﺩﻗﻴﻘﺎ" ﺍﻧﺪﺍﺯﻩ ﮔﻴﺮﻱ ﺷﺪﻩ ﻭ ﺍﺯ ﻃﺮﻓﻴﻦ ﻣﺤﻞ ﻣﻌﻴﻮﺏ ﺭﻭﻱ ﺧﻂ ﻟﻮﻟﻪ ﺑﻪ ﻃﻮﺭ ﻣﺴﺎﻭﻱ ﺩﻭﺭﺗﺎ ﺩﻭﺭ
ﻟﻮﻟﻪ ﺑﻪ ﻣﻴﺰﺍﻥ ﻧﺼﻒ ﻃﻮﻝ ﻏﻼﻑ ﺑﺎﺿﺎﻓﻪ 6ﻣﻴﻠﻴﻤﺘﺮ ﺑﻴﺸﺘﺮ ،ﻋﻼﻣﺖ ﮔﺬﺍﺭﻱ ﺷﻮﺩ .
26
ﻧﺤﻮﻩ ﺟﻮﺷﻜﺎﺭ ﻏﻼﻑ ﺩﻭ ﺗﻜﻪ ﻛﺎﻣﻞ )(Welding Full Encirclement Sleeve
ﺍﺗﺼﺎﻝ ﻏﻼﻑ ﺩﻭ ﺗﻜﻪ ﻛﺎﻣﻞ ﺭﺍ ﻣﻲ ﺗﻮﺍﻥ ﺑﻪ ﺻﻮﺭﺕ ﻣﻜﺎﻧﻴﻜﻲ )ﺑﺴﺘﻦ ﭘﻴﭽﻬﺎ( ﺭﻭ ﺧﻂ ﻟﻮﻟﻪ ﻧﺼﺐ ﻧﻤﻮﺩ ﻛﻪ ﺍﻳﻦ
ﻭﺿﻌﻴﺖ ﺍﺗﺼﺎﻝ ﺭﺍ ﻣﻬﺎﺭ ﻧﺸﺪﻩ ) (Not Anchoredﻧﺎﻣﮕﺬﺍﺭﻱ ﻛﺮﺩﻩ ﺍﻧﺪ .ﭼﻨﺎﻧﭽﻪ ﺑﺨﻮﺍﻫﻨﺪ ﺑﺎ ﺟﻮﺷﻜﺎﺭﻱ ﺗﻌﻤﻴﺮ
ﺩﺍﺋﻤﻲ ﺍﻧﺠﺎﻡ ﮔﻴﺮﺩ ﻭ ﺑﻪ ﺍﺻﻄﻼﺡ ﺍﺗﺼﺎﻝ ﺭﺍ ﻣﻬﺎﺭ ) (Anchoredﻧﻤﺎﻳﻨﺪ ،ﻣﻮﺍﺭﺩ ﺯﻳﺮ ﺭﺍ ﺑﺮﺍﻱ ﺟﻮﺷﻜﺎﺭﻱ ﺍﺗﺼﺎﻝ ﺗﺎ
ﻛﻼﺱ ANSI 600ﻳﻌﻨﻲ ﻓﺸﺎﺭ ﻛﺎﺭﻱ ﻣﺠﺎﺯ ) 10 MPa (1440PSIﭘﺲ ﺍﺯ ﺑﺴﺘﻦ ﻭ ﻣﺤﻜﻢ ﻧﻤﻮﺩﻥ ﻛﻠﻴﻪ
ﭘﻴﭽﻬﺎ ؛ ﺗﻮﺻﻴﻪ ﻣﻲ ﮔﺮﺩﺩ:
-1ﺍﺑﺘﺪﺍ ﺩﺭﺯﻫﺎﻱ ﻣﺤﻴﻄﻲ ﻟﻮﻟﻪ ﺗﻮﺳﻂ ﺩﻭ ﺟﻮﺷﻜﺎﺭ ﻛﺪ ﺩﺭ ﺩﻭﺟﻬﺖ ﻣﺨﺘﻠﻒ ﺟﻮﺷﻜﺎﺭﻱ ﮔﺮﺩﺩ .
-2ﺍﺭﺗﻔﺎﻉ ﺟﻮﺵ ﮔﻮﺷﻪ ﺍﻱ ﻣﺤﻴﻄﻲ ﻟﻮﻟﻪ ﺑﻪ ﺍﺗﺼﺎﻝ ﺑﺎﻳﺪ ﺣﺪﺍﻗﻞ 1/4ﺑﺮﺍﺑﺮ ) (1.4 × t of Pipelineﺿﺨﺎﻣﺖ
ﻟﻮﻟﻪ ﺍﺻﻠﻲ ﺑﺎﺷﺪ .
)ﺟﻮﺷﻜﺎﺭﻱ ﻛﺎﻣﻞ ﺿﺨﺎﻣﺖ ﺍﺯ ﺳﻄﺢ ﻟﻮﻟﻪ ﺗﺎ ﺳﻄﺢ ﻣﺮﺋﻲ ﺍﺗﺼﺎﻝ ﺿﺮﻭﺭﺗﻲ ﻧﺪﺍﺭﺩ( .
-3ﭘﻴﭽﻬﺎﻱ ﻣﺤﻜﻢ ﻛﻨﻨﺪﻩ ﺍﺗﺼﺎﻝ ﺑﺎ ﺭﻋﺎﻳﺖ ﺗﺮﺗﻴﺐ ﻣﺠﺪﺩﺍ" ﺁﭼﺎﺭﻛﺸﻲ ﻭ ﻣﺤﻜﻢ ﺷﻮﻧﺪ .
-4ﺩﺭﺯ ﻫﺎﻱ ﻃﻮﻟﻲ ﺍﺗﺼﺎﻝ ﺩﺭ ﺩﻭ ﺟﻬﺖ ﻣﺨﺘﻠﻒ ﺗﻮﺳﻂ ﺩﻭ ﺟﻮﺷﻜﺎﺭ ،ﺟﻮﺷﻜﺎﺭﻱ ﮔﺮﺩﻧﺪ .
-5ﺗﻤﺎﻣﻲ ﻣﻬﺮﻩ ﻫﺎﻱ ﭘﻴﭽﻬﺎ ) (Nutsﺑﻪ ﺑﺪﻧﻪ ﺍﺗﺼﺎﻝ ﺟﻮﺷﻜﺎﺭﻱ ﺷﻮﻧﺪ.
- -6ﺍﻧﺘﻬﺎﻱ ﺩﻭ ﺳﺮﻛﻠﻴﻪ ﭘﻴﭽﻬﺎ ﺑﻪ ﻣﻬﺮﻩ ﻫﺎ ﺟﻮﺷﻜﺎﺭﻱ ﮔﺮﺩﻧﺪ .
27
ﻧﻜﺎﺕ ﻣﻬﻢ :
-1ﭼﻨﺎﻧﭽﻪ ﺧﻂ ﻟﻮﻟﻪ ﺩﺭ ﺣﺎﻝ ﺳﺮﻭﻳﺲ ﻭﺗﺤﺖ ﻓﺸﺎﺭ ﺑﺎﺷﺪ ﺑﺎﻳﺪ ﻓﺸﺎﺭ ﻣﺠﺎﺯ ﺿﻤﻦ ﺟﻮﺷﻜﺎﺭﻱ ﻣﺤﺎﺳﺒﻪ ﻭ ﺭﻋﺎﻳﺖ
ﮔﺮﺩﺩ .
-2ﻓﺸﺎﺭ ﺧﻂ ﻟﻮﻟﻪ ﺑﺎﻳﺪ ﺑﻪ ﻃﻮﺭ ﻣﻨﻈﻢ ﻛﻨﺘﺮﻝ ﻭ ﻗﺮﺍﺋﺖ ﻭﺛﺒﺖ ﮔﺮﺩﺩ .
-3ﻛﻠﻴﻪ ﻭﺳﺎﻳﻞ ﺍﻳﻤﻨﻲ ﻣﺎﻧﻨﺪ ﻛﭙﺴﻮﻝ ﺁﺗﺶ ﻧﺸﺎﻧﻲ ،ﺷﻠﻨﮓ ﻫﺎﻱ ﭘﺮ ﻓﺸﺎﺭ ﺁﺏ ،ﺩﺳﺘﮕﺎﻩ ﺳﻨﺠﺶ ﮔﺎﺯ ﺑﺎﻳﺪ ﺩﺭ
ﻣﺤﻞ ﻣﻮﺟﻮﺩ ﺑﺎﺷﺪ .
-4ﺣﺪﺍﻗﻞ ﻧﻔﺮﺍﺕ ﺑﺎﻳﺪ ﺩﺭ ﻣﺤﻞ ﺟﻮﺷﻜﺎﺭﻱ ﺑﺎﻳﺪ ﺑﺎﺷﻨﺪ ﻭ ﺳﺎﻳﺮ ﺍﻋﻀﺎﻱ ﮔﺮﻭﻩ ﺩﺭ ﻓﺎﺻﻠﻪ ﺍﻳﻤﻦ ﻗﺮﺍﺭ ﮔﺮﻓﺘﻪ ﺑﺎﺷﻨﺪ .
-5ﺗﺠﻬﻴﺰﺍﺕ ﺟﻮﺷﻜﺎﺭﻱ ﻭ ﺣﺮﺍﺭﺕ ﺯﺍ ﺑﺎﻳﺪ ﺣﺘﻲ ﺍﻟﻤﻘﺪﻭﺭ ﺩﺭ ﺩﻭﺭﺗﺮﻳﻦ ﻓﺎﺻﻠﻪ ﺍﺳﺘﻘﺮﺍﺭ ﻳﺎﺑﻨﺪ .
-6ﺑﺮﺍﻱ ﺟﻮﺷﻜﺎﺭﻱ ﺍﻟﻜﺘﺮﻭﺩﻫﺎﻱ ﻛﻢ ﺋﻴﺪﺭﻭژﻥ ) (Low Hydrogen E7018ﻣﻲ ﺗﻮﺍﻥ ﺍﺳﺘﻔﺎﺩﻩ ﻧﻤﻮﺩ .
-7ﺟﻬﺖ ﺍﻳﻤﻨﻲ ﺑﻴﺸﺘﺮ ﻭ ﺟﻠﻮﮔﻴﺮﻱ ﺍﺯ ﺻﺪﻣﻪ ﺭﺳﻴﺪﻥ ﺑﻪ ﻧﺸﺖ ﮔﻴﺮﻫﺎ ،ﭘﺲ ﺍﺯ ﺍﻧﺠﺎﻡ ﻣﺮﺣﻠﻪ ﺩﻭﻡ ﺟﻮﺷﻜﺎﺭﻱ
)ﭘﺎﺱ ﺩﻭﻡ( ﺑﺮﺍﻱ ﺧﻨﻚ ﺷﺪﻥ ﺍﺗﺼﺎﻝ ﻭ ﺳﻄﺢ ﻟﻮﻟﻪ ﻣﻲ ﺗﻮﺍﻥ ﻭﻗﻔﻪ ﻫﺎﻱ 5ﺗﺎ 10ﺩﻗﻴﻘﻪ ﺍﻱ ﺑﻴﻦ ﻣﺮﺍﺣﻞ ﺑﻌﺪﻱ ﺩﺭ
ﻧﻈﺮ ﮔﺮﻓﺖ .
28
)ﻏﻼﻑ ﻛﺎﻣﻞ ﺩﻭ ﺗﻜﻪ( Full Split Sleeve
ﺩﺍﺭﺍﻱ ﺩﻭ ﻧﻮﻉ ﭘﭻ ﺳﻔﺖ ﻛﻨﻨﺪﻩ ﻭ ﺗﻨﻈﻴﻢ ﻛﻨﻨﺪﻩ ﻧﺸﺖ ﮔﻴﺮ ﻭ ﻣﻨﺎﺳﺐ ﺑﺮﺍﻱ ﭘﺮ ﺷﺪﻩ ﺑﺎ ﺭﺯﻳﻦ ﺍﭘﻮﻛﺴﻲ
)ﻏﻼﻑ ﻛﺎﻣﻞ ﺩﻭ ﺗﻜﻪ ﺩﺳﺖ ﺳﺎﺯ( Local Made Full Split Sleeve
29
ﻧﺤﻮﻩ ﻧﺼﺐ ﻏﻼﻑ ﻛﺎﻣﻞ ﺩﻭ ﺗﻜﻪ
L/2 + 6 mm
30
-3ﻣﺤﻜﻢ ﻛﺮﺩﻥ ﭘﻴﭽﻬﺎﻱ ﻏﻼﻑ ﺩﻭ ﺗﻜﻪ
ﻣﻬﺮﻩ ﻫﺎﻱ ﻏﻼﻑ ﺭﺍ ﺑﺎ ﺭﻋﺎﻳﺖ ﺗﺮﺗﻴﺐ ﻭ ﺑﺘﻨﺎﻭﺏ ﺗﺎ ﺗﻤﺎﺱ ﻛﺎﻣﻞ ﻏﻼﻑ ﺑﺎ ﺳﻄﺢ ﻟﻮﻟﻪ ﺳﻔﺖ ﻭ ﻣﺤﻜﻢ ﻣﻲ ﻧﻤﺎﺋﻴﻢ .
31
ﭘﺲ ﺍﺯ ﺗﻜﻤﻴﻞ ﺟﻮﺷﻬﺎﻱ ﻣﺤﻴﻄﻲ ﺩﺭ ﺩﻭ ﻃﺮﻑ ﻏﻼﻑ ،ﻛﻠﻴﻪ ﭘﻴﭽﻬﺎ ﺭﺍ ﻣﺠﺪﺩﺍ" ﺁﭼﺎﺭﻛﺸﻲ ﻭ ﻣﺤﻜﻢ ﻣﻲ ﻧﻤﺎﺋﻴﻢ .
ﺳﭙﺲ ﺟﻮﺷﻬﺎﻱ ﻃﻮﻟﻲ ﺭﺍ ﺗﻮﺳﻂ ﺩﻭ ﺟﻮﺷﻜﺎﺭ ﺩﺭ ﺩﻭ ﺟﻬﺖ ﻣﺨﺘﻠﻒ ﺟﻮﺷﻜﺎﺭﻱ ﻣﻲ ﻧﻤﺎﺋﻴﻢ .
ﭘﺲ ﺍﺯ ﺗﻜﻴﻞ ﺟﻮﺷﻬﺎﻱ ﻃﻮﻟﻲ ﺩﺭ ﺩﻭ ﻃﺮﻑ ؛ ﺗﻤﺎﻣﻲ ﻣﻬﺮﻩ ﻫﺎ ) 12ﻣﻬﺮﻩ(ﺭﺍ ﺑﺎ ﺭﻋﺎﻳﺖ ﺗﺮﺗﻴﺐ ﻭ ﺗﻮﺯﻳﻊ ﺣﺮﺍﺭﺕ ﺑﻪ
ﺑﺪﻧﻪ ﻏﻼﻑ ﺟﻮﺷﻜﺎﺭﻱ ﻣﻲ ﻧﻤﺎﺋﻴﻢ .
-7ﺑﺮﺷﻜﺎﺭﻱ ﻗﺴﻤﺖ ﺍﺿﺎﻓﻲ ﭘﻴﭽﻬﺎ ﻭ ﺟﻮﺷﻜﺎﺭﻱ ﺍﻧﺘﻬﺎﻱ ﭘﻴﭽﻬﺎ ﺑﻪ ﻣﻬﺮﻩ ﻫﺎ
ﺩﺭ ﻧﻬﺎﻳﺖ ﻗﺴﻤﺖ ﺍﺿﺎﻓﻲ ﭘﻴﭽﻬﺎ ) (Stud Boltsﺭﺍ ﺑﺎ ﺳﻨﮓ ﺟﺖ ) (Grinding Machineﺑﺮﻳﺪﻩ ﻭ
ﻗﺴﻤﺖ ﺳﺮ ﺍﻧﺘﻬﺎﺋﻲ ﭘﻴﭽﻬﺎ ﺭﺍ ﻫﺮﻛﺪﺍﻡ ﺑﻪ ﻣﻬﺮﻩ ﺧﻮﺩﺵ ﺟﻮﺷﻜﺎﺭﻱ ﻣﻲ ﻧﻤﺎﺋﻴﻢ .
32
................................................. Split Sleeve with Branch Connection ...............................................
ﻓﻠﻨﺞ
33
-11ﺟﺪﺍﺳﺎﺯﻱ ﻭ ﺑﺮﺷﻜﺎﺭﻱ ﻟﻮﻟﻪ )(Pipe Replacement / Cutout Repair
ﺩﺭﺑﺮﺧﻲ ﺍﺯ ﻣﻮﺍﺭﺩ ﻋﻴﻮﺏ ﺑﻮﺟﻮﺩﺁﻣﺪﻩ ﺭﻭﻱ ﺧﻂ ﻟﻮﻟﻪ ﻏﻴﺮ ﻗﺎﺑﻞ ﺗﻌﻤﻴﺮ ﻭ ﻳﺎ ﺗﻘﻮﻳﺖ ﻭ ﻣﺮﻣﺖ ﻣﺤﻞ ﻣﻌﻴﻮﺏ ﻣﺎﻧﻨﺪ
ﺧﻮﺭﺩﮔﻴﻬﺎﻱ ﺣﻔﺮﻩ ﺍﻱ ﻋﻤﻴﻖ ﺩﺭ ﺳﻄﺢ ﮔﺴﺘﺮﺩﻩ ﻳﺎ ﺧﺮﺍﺷﻬﺎﻱ ﻋﻤﻴﻖ ،ﺗﺮﻛﻬﺎ ﻭ ﭘﺎﺭﮔﻲ ﺧﻂ ﻟﻮﻟﻪ ،ﻏﻴﺮ ﻋﻤﻠﻲ ﻭﻳﺎ
ﻏﻴﺮ ﺍﻗﺘﺼﺎﺩﻱ ﻣﻲ ﺑﺎﺷﺪ .ﺩﺭ ﺍﻳﻦ ﺷﺮﺍﻳﻂ ﺟﺪﺍﺳﺎﺯﻱ ﻭ ﺑﺮﺷﻜﺎﺭﻱ ﻗﺴﻤﺖ ﻣﻌﻴﻮﺏ ﻭ ﺟﺎﻳﮕﺰﻳﻨﻲ ﺁﻥ ﺑﺎ ﻟﻮﻟﻪ ﻣﺸﺎﺑﻪ ﺭﺍﻩ
ﭼﺎﺭﻩ ﻣﻮﺭﺩ ﻗﺒﻮﻝ ﻣﻲ ﺑﺎﺷﺪ .
34
ﻫﺮﭼﻨﺪ ﺍﻳﻦ ﺭﻭﺵ ﺗﻌﻤﻴﺮ ﻳﻌﻨﻲ ﺑﺮﺷﻜﺎﺭﻱ ﻭ ﺣﺬﻑ ﻗﺴﻤﺖ ﻣﻌﻴﻮﺏ ﻟﻮﻟﻪ ﻭ ﺟﺎﻳﮕﺰﻳﻨﻲ ﻣﺤﻞ ﺑﺎ ﻟﻮﻟﻪ ﻣﺸﺎﺑﻪ ﺟﺪﻳﺪ ﺭﺍ
ﺑﺮﺍﻱ ﻫﺮ ﻧﻮﻉ ﻋﻴﺐ ﺩﻳﮕﺮ ﻧﻴﺰ ﻣﻲ ﺗﻮﺍﻥ ﺍﺟﺮﺍ ﻧﻤﻮﺩ ؛ ﺍﻣﺎ ﻫﻤﻮﺍﺭﻩ ﺑﺎﻳﺪ ﺗﻮﺟﻪ ﺩﺍﺷﺖ ﻛﻪ ﺍﺟﺮﺍﻱ ﺍﻳﻦ ﺭﻭﺵ ﻣﺴﺘﻠﺰﻡ
ﺧﺎﺭﺝ ﻧﻤﻮﺩﻥ ﺧﻂ ﻟﻮﻟﻪ ﺍﺯ ﺳﺮﻭﻳﺲ ) (Shut Downﻭ ﺻﺮﻑ ﺯﻣﺎﻥ ﺑﻴﺸﺘﺮﻱ ﺑﺮﺍﻱ ﺗﻌﻤﻴﺮ ﻣﻲ ﺑﺎﺷﺪ .
35
-5ﺻﺎﺣﺐ ﺧﻂ ﻟﻮﻟﻪ ﺑﺎ ﻫﻤﺂﻫﻨﮕﻲ ﺍﻓﺮﺍﺩ ﻣﺴﺌﻮﻝ ﺟﻬﺖ ﺟﻠﻮﮔﻴﺮﻱ ﺍﺯ ﻫﺮ ﮔﻮﻧﻪ ﺣﺎﺩﺛﻪ ﺍﺣﺘﻤﺎﻟﻲ ،ﺗﺎ ﻓﻮﺍﺻﻞ ﺍﻳﻤﻦ ﻭ
ﺩﻭﺭﺍ ﺩﻭﺭ ﺧﻂ ﻟﻮﻟﻪ ﺭﺍ ﺍﺯ ﺍﻓﺮﺍﺩ ﻣﺤﻠﻲ ﻭ ﻏﻴﺮ ﻣﺠﺎﺯ ﺗﺨﻠﻴﻪ ﻭ ﺩﺭ ﺻﻮﺭﺕ ﻧﻴﺎﺯ ﻣﺴﻴﺮﻫﺎﻱ ﻋﺒﻮﺭﻱ ﻣﺴﺪﻭﺩ ﻭ ﺍﺯ ﻫﺮ ﮔﻮﻧﻪ
ﺍﻗﺪﺍﻣﺎﺕ ﺍﺟﺮﺍﺋﻲ ﻭ ﻛﺎﺭﻱ ﺩﻳﮕﺮ ﺩﺭ ﻣﺤﺪﻭﺩﻩ ﺧﻄﺮ ﻣﺤﻞ ﻣﻌﻴﻮﺏ ﺧﻂ ﻟﻮﻟﻪ ﺭﺍ ﺑﺎﻳﺪ ﺗﻌﻄﻴﻞ ﻭ ﻣﻤﻨﻮﻉ ﻧﻤﺎﻳﺪ .
-6ﺩﺭ ﺻﻮﺭﺕ ﻭﺟﻮﺩ ﻧﺸﺘﻲ ﻧﺴﺒﺖ ﺑﻪ ﻫﺪﺍﻳﺖ ﻭ ﺍﻧﺘﻘﺎﻝ ﻣﺎﻳﻌﺎﺕ ﻗﺎﺑﻞ ﺍﺷﺘﻌﺎﻝ ﺑﻪ ﻣﺤﻞ ﺍﻣﻦ ﻭ ﺩﻭﺭ ﺍﺯ ﺧﻂ ﻟﻮﻟﻪ ﺍﻗﺪﺍﻡ
ﺷﻮﺩ .
-7ﺧﻂ ﻟﻮﻟﻪ ﺗﻮﺳﻂ ﺗﻮﭘﻜﺮﺍﻧﻲ ) (Piggingﻭ ﺳﻴﺎﻝ ﺁﺏ ﺗﺨﻠﻴﻪ ﻭ ﺷﺴﺘﺸﻮ ﮔﺮﺩﺩ .
-8ﺑﺮﺍﻱ ﺧﻄﻮﻁ ﺭﻭ ﺯﻣﻴﻨﻲ ﺣﺪﻭﺩ ﻋﻴﺐ ﻣﺸﺨﺺ ﻭ ﻃﻮﻝ ﺗﻌﻮﻳﻀﻲ ﺧﻂ ﻟﻮﻟﻪ ﻋﻼﻣﺖ ﮔﺬﺍﺭﻱ ﮔﺮﺩﺩ .
-8ﺑﺮﺍﻱ ﺧﻄﻮﻁ ﺯﻳﺮ ﺯﻣﻴﻨﻲ ،ﻋﻠﻤﻚ ﻫﺎﻱ ﻧﺸﺎﻧﮕﺮ ﺧﻂ ﻟﻮﻟﻪ ﺩﺭ ﻃﺮﻓﻴﻦ ﻣﺤﻞ ﺗﻌﻤﻴﺮﻱ ﺩﻗﻴﻘﺎ ﺭﻭﻳﺖ ﻭﺛﺒﺖ ﺷﻮﻧﺪ ﻭ
ﭘﺲ ﺍﺯ ﺧﺎﻛﺒﺮﺩﺍﺭﻱ ﻣﺤﻞ ﻧﻴﺰ ﺑﺎ ﺍﻧﺪﺍﺯﻩ ﮔﻴﺮﻱ ﻣﺸﺨﺼﺎﺕ ﺧﻂ ﻟﻮﻟﻪ ﺑﺎ ﺳﻮﺍﺑﻖ ﺁﻥ ﻛﻨﺘﺮﻝ ﮔﺮﺩﺩ .
-9ﻗﺒﻞ ﺍﺯ ﻫﺮﮔﻮﻧﻪ ﺑﺮﺷﻜﺎﺭﻱ ﺳﺮﺩ ) (Cold Cutﺍﺯ ﺗﺮﺧﻴﺺ ﻓﺸﺎﺭ ) (Depressurizedﺧﻂ ﻟﻮﻟﻪ ﺍﻃﻤﻴﻨﺎﻥ
ﺣﺎﺻﻞ ﮔﺮﺩﺩ .
ﺑﺮﺍﻱ ﺍﻳﻦ ﻣﻨﻈﻮﺭ ﻣﻲ ﺗﻮﺍﻥ ﻧﺰﺩﻳﻜﺘﺮﻳﻦ ﻓﺸﺎﺭ ﺳﻨﺞ ﺑﻪ ﻣﺤﻞ ﺗﻌﻤﻴﺮﻱ ﺧﻂ ﻟﻮﻟﻪ ﺭﺍ ﺭﻭﻳﺖ ﻭ ﻗﺮﺍﺋﺖ ﻧﻤﻮﺩ .ﻫﻤﭽﻨﻴﻦ
ﺑﺮﺍﻱ ﺍﻃﻤﻴﻨﺎﻥ ﺑﻴﺸﺘﺮ ﻣﻲ ﺗﻮﺍﻥ ﺑﺮﺍﺳﺎﺱ ﺗﻮﺻﻴﻪ ﻫﺎﻱ ﺍﻳﻤﻨﻲ ﺍﺗﺼﺎﻝ ﻭ ﺷﻴﺮ ﻭ ﻓﺸﺎﺭ ﺳﻨﺞ ﺩﺭ ﻣﺤﻞ ﺗﻌﻤﻴﺮﻱ ﻧﺼﺐ
ﻧﻤﻮﺩ ﻭ ﭘﺲ ﺍﺯ ﻋﻤﻠﻴﺎﺕ ﺳﻮﺭﺍﺧﻜﺎﺭﻱ ﺩﺳﺘﻲ ) (Hot Tapﻣﻴﺰﺍﻥ ﻓﺸﺎﺭ ﺧﻂ ﻟﻮﻟﻪ ﺭﺍ ﺳﻨﺠﺪ ﻭ ﻳﺎ ﻓﺸﺎﺭ ﺍﺿﺎﻓﻲ ﺭﺍ ﺑﻪ
ﺭﻋﺎﻳﺖ ﺍﻳﻤﻨﻲ ﺗﺨﻠﻴﻪ ﻧﻤﻮﺩ .ﺩﺭ ﺍﻳﻦ ﻣﻮﺭﺩ ﺑﺮﺍﻱ ﺍﻃﻼﻋﺎﺕ ﺑﻴﺸﺘﺮ ﺑﻪ ﺻﻔﺤﻪ 7ﺑﺨﺶ ﺍﻭﻝ ﻣﺮﺍﺟﻌﻪ ﻓﺮﻣﺎﺋﻴﺪ .
-10ﭘﺲ ﺍﺯ ﺍﻃﻤﻴﻨﺎﻥ ﺍﺯ ﻧﺒﻮﺩ ﻓﺸﺎﺭ ﺩﺭ ﺧﻂ ﻟﻮﻟﻪ ،ﺑﺪﻭﻥ ﺗﻮﺟﻪ ﺑﺎ ﺍﻳﻨﻜﻪ ﺧﻂ ﻟﻮﻟﻪ ﻧﻮ ﺑﻮﺩﻩ ﻭﻳﺎ ﺧﺎﺭﺝ ﺍﺯ ﺳﺮﻭﻳﺲ
ﺍﺳﺖ )ﺩﺭ ﺻﻮﺭﺗﻲ ﻛﻪ ﺑﻪ ﺳﺎﻣﺎﻧﻪ ﻟﻮﻟﻪ ﻛﺸﻲ ﻣﺘﺼﻞ ﺍﺳﺖ ( ﺣﺘﻤﺎ ﺳﺮ ﺍﻭﻝ ﺑﺮﺷﻜﺎﺭﻱ ﺑﻪ ﺭﻭﺵ ﺳﺮﺩ )(Cold Cut
،ﺑﺮﺷﻜﺎﺭﻱ ﮔﺮﺩﺩ .
-11ﭼﻨﺎﻧﭽﻪ ﻧﺰﺩﻳﻜﺘﺮﻳﻦ ﻣﺤﻞ ﻫﺎ ﺑﻪ ﻃﺮﻓﻴﻦ ﺑﺎﻻ ﺩﺳﺖ ﻭ ﭘﺎﺋﻴﻦ ﺩﺳﺖ ﺧﻂ ﻟﻮﻟﻪ (Up Stream and Down
) Streamﺑﺎﺯ ﻭ ﺩﺭﻭﻥ ﺧﻂ ﻟﻮﻟﻪ ﻗﺎﺑﻞ ﺭﻭﻳﺖ ﻭ ﻳﺎ ﻗﺎﺑﻞ ﺳﻨﺠﺶ ﮔﺎﺯ ) (Gas Testﺑﺎﺷﺪ ﻭ ﻭﺟﻮﺩ ﻫﻴﭽﮕﻮﻧﻪ
ﮔﺎﺯﻱ ﻣﺸﺎﻫﺪﻩ ﻧﮕﺮﺩﺩ ؛ ﻣﻲ ﺗﻮﺍﻥ ﺑﺮﺷﻜﺎﺭﻳﻬﺎ ﺭﺍ ﺑﻪ ﺻﻮﺭﺕ ﮔﺮﻡ ﺍﻧﺠﺎﻡ ﺩﺍﺩ .
-12ﭘﺲ ﺍﺯ ﺑﺮﺷﻜﺎﺭﻱ ﺩﺭﻭﻥ ﺧﻂ ﻟﻮﻟﻪ ﺟﻬﺖ ﺍﻳﻤﻦ ﺑﻮﺩﻥ ﺧﻂ ﻟﻮﻟﻪ ﺑﺮﺍﻱ ﻧﺒﻮﺩ ﮔﺎﺯ ) (Gas Testﺍﺭﺯﻳﺎﺑﻲ ﺷﻮﺩ .
-13ﺩﺭﻭﻥ ﺧﻂ ﻟﻮﻟﻪ ﺑﺮﺍﻱ ﺍﺭﺯﻳﺎﺑﻲ ﺳﻼﻣﺖ ﺩﺍﺧﻠﻲ ﺑﺎﺯﺭﺳﻲ ﭼﺸﻤﻲ ﻭ ﺩﺭ ﺻﻮﺭﺕ ﺳﻼﻣﺖ ﻟﻮﻟﻪ ،ﺍﺟﺎﺯﻩ ﺟﻮﺷﻜﺎﺭﻱ
ﺩﺍﺩﻩ ﺷﻮﺩ .
-14ﻟﺒﻪ ﻫﺎﻱ ﻟﻮﻟﻪ ﭘﺦ ﺳﺎﺯﻱ ) (Bevelﻭ ﭘﺲ ﺍﺯ ﺟﻔﺖ ﻧﻤﻮﺩﻥ ﺷﺎﺧﻪ ﻟﻮﻟﻪ ﺳﺎﻟﻢ ﺩﺭ ﻣﺤﻞ ﺗﻌﻤﻴﺮﻱ ﻭ ﻣﻬﺎﺭ ﺁﻥ
ﺗﻮﺳﻂ ﻛﻠﻤﺲ ﺧﺎﺭﺟﻲ ؛ ﺧﻂ ﻟﻮﻟﻪ ﺟﻮﺷﻜﺎﺭﻱ ﮔﺮﺩﺩ .
-15ﻣﺘﻨﺎﺳﺐ ﺑﺎ ﻗﻄﺮ ﻭ ﻓﺸﺎﺭ ﺧﻂ ﻟﻮﻟﻪ ﺁﺯﻣﺎﻳﺸﺎﺕ ﻏﻴﺮ ﻣﺨﺮﺏ ﻗﺒﻞ ﻭ ﺩﺭ ﺿﻤﻦ ﻭ ﺑﻌﺪ ﺍﺯ ﺟﻮﺷﻜﺎﺭﻱ ﺑﺮﺍﻱ ﻗﺴﻤﺖ
ﺗﻌﻤﻴﺮﻱ ﺻﻮﺭﺕ ﮔﻴﺮﺩ .