Professional Documents
Culture Documents
Surface area of precast element, Aprecast = 3.3 m2 (for adhesion force calc during
demoulding, if no adhesion put 0 )
Design Criteria
FOSdemoulding = 1.5
FOSinstallation = 1.5
Dynamic Factor for crane lifting ,at casting yard = Tower crane, portal crane, mobile crane – 1.3
at site = Tower crane, portal crane, mobile crane – 1.3
By lifting elements with a chain, there is a load increase resulting from the angle of
inclination.
Angle of lifting sling to the vertical β , at casting yard = 30º , at site = 30º
No. of lifting_points ,
Demoulding stage = 4 nos
Installation stage = 4 nos
Note:
All balanced lifting MUST use chain blocks and pulleys to provide equal distribution of
loads. The center of gravity of the the lifting hooks must also coincide with the center of gravity
of the precast elements.
Lifting mechanism
h1= 60 mm
b1= 110 mm
NOTE
ALL LIFTING POINTS TO BE SYMETRICALLY ARRANGED AROUND CENTROID OF
PRECAST ELEMENT.
Project Title : Solar Car Parking Phase - II - MAF Area
Code = CP 65 Part 1: 2009 and EC02
NOTE
ALL LIFTING POINTS TO BE SYMETRICALLY ARRANGED AROUND CENTROID OF
PRECAST ELEMENT.
φrebar =: 20 mm
nosrebar =: 1 nos
fst =: 500 N/mm2
ψm =: 1.25
βrebar =: 0.4
h1 =: 60 mm
b1= 110 mm
h1= 60 mm
--------------------------------------------------------------------------------
Pr,demould = 36.61 kN / cos(30o) = 42.27 kN
Pv,demould = 36.61 kN
Ph,demould = 42.27 kN *sin(30o)*cos(25o) = 19.15 kN
Ph,demould,25 deg = 42.27 kN *sin(30o)*sin(25o) = 8.93 kN
Trebar,demould = 36.61 kN /2 legs + 19.15 kN * 60 mm / 110 mm = 28.75 kN
Vrebar,demould = √ [(19.15 kN /2 legs)2 + (8.93 kN /2 legs)2 ] = 10.56 kN
Mrebar,demould = 8.93 kN * 60 mm / 2 legs / 1000 = 0.27 kNm
--------------------------------------------------------------------------------
checkrebar,demoulding = 28.75/136.59 + 0.27/0.39 + 10.56/89.49 = 1.02
checkrebar,installing = 30.08/136.59 + 0.28/0.39 + 11.06/89.49 = 1.06
Rebar capacity check <=1.2 for demoulding , OK
Rebar capacity check <=1.2 for installation , OK
During demoulding
NOTES
For defined balance conditions (statically determined system), the loads can be calculated exactly at
each lifting points. This is the case when using only two lifting points, three lifting points , four or
more lifting points with chain links allowing compensation seesawing movements that would align
the c.g of the lifting with the c.g of the lifting hook.
For undefined or un-balance conditions, the lifting insert loads cannot be calculated exactly. This is
the case when more than two lifting inserts are used, for wall elements with three lines installed or
four or more suspension gears without compensation to rebalanced the weight so that the c.g of the
loads and the lifting points coincides exactly.