METHODOLOGY:

MANUAL METHOD ARE CARRIED OUT TO DOWN,PROCEEDING IN GENERAL ,


FROM ROOF TO GROUND

THE SEQUENCE OF DEMOLITION VARY ON:

1.39
1. OUTLINE THE DEMOLITION METHODS,EQUIPMENT NEEDED ,DEBRIS AND
MATERIALS CLEAN UP FOR THE SAFETY SECURE OF REMAINING STRUCTURE.

3.00 2. TEMPORARY SUPPORT AND/OR PLATFORM SHALL BE PROVIDED UNDERNEATH


(SEE ELEVATION)
8.55

SIGNAGE
3. EXISTING COLUMN AND RC BEAM REMAIN.
3.95

4. DIRECTION OF CONCRETE DEMOLITION (SEE ELEVATION).

5. GROUND FLOOR WALL THE REINFORCEMENT BARS SHOULD CUT AFTER BREAKING
0.22

AWAY THE CONCRETE WALL.

6. ADVISE SITE WORKERS OF HAZARD,SECURE/BLOCK OFF AREAS. ALONG THE


RETAINED STRUCTURE
1 FRONT ELEVATION
A 3 SCALE 1:100M

SCOPE OF WORK TO DEMOLISHED

SAFETY NOTES:
1. DEMOLITION SHOULD BE UNDERTAKEN BY
SUITABLYQUALIFY PEOPLE.
2. WORKER UNDERSTANDING OF DANGERS
&PROCESSES IS CRITICAL TO SAFETY3. ALL
WORK MUST BE OVERSEEN BY AN ENGINEER.
4. DEMOLITION SHOULD BE PROPERLY PLANNED BEFORE
COMMENCEMENT.
5. SELECT APPROPRIATE TOOLS & TECHNIQUES FOR THE
WORK.
6. MONITORING OF STRUCTURES BEFORE &
DURINGDEMOLITION IS IMPORTANT.
7. MAINTAIN AN EXCLUSION ZONE AROUND
DEMOLITIONWORK.
8. CONSIDER WHERE THE DEBRIS WILL BE REMOVE TO&
RECYCLE MUCH AS POSSIBLE.

2 RIGHT SIDE ELEVATION 3 LEFT SIDE ELEVATION


A 3 SCALE 1:100M A 3 SCALE 1:100M

A1
PROPOSED DEMOLITION OF
DEMOLITION PLAN 747 LUMBER & CONSTRUCTION SUPPLY BLDG.
EDGARDO CRUZ
747 LUMBER CMPD. CARUNCHO AVE. SAN NICOLAS, PASIG CITY PM/ Owner