You are on page 1of 6

KONTRAKTOR BARU CATATANConcrete

NAMA PROJEK MUKA


UTAMA of work
SURAT
PERUBAHAN
SYIFA BINA SDN BHD MENAIKTARAF RUMAH KANAK-KANAK TAMAN 1 H/SBSB/07_Rev0
BAKTI,KEPALA BATAS,PULAU PINANG.
DISEDIAKAN KHATIJAH/SHO
TARIKH :
OLEH
15/1/2023
DISEMAK EN AHMAD TARMIZI
NAMA PENGURUS / PENGARAH PROJEK
OLEH
EN AHMAD TARMIZI / EN MOHD SUHAIMI
DILULUSKAN EN MOHD SUHAIMI
LOKASI PROSES
OLEH
PENGENALAN HAZAD ANALISIS RISIKO KAWALAN RISIKO DAN STATUS
TURUTAN KAWALAN
KERJA SEMASA KEBARANG- TAHAP
HAZAD KESAN KETERUKAN TINDAKAN STATUS PERUNDANGAN
KALIAN RISIKO
a. Formwork fabrication .Expose to Potential 1.To barricade off 4 2 8
moving/ cut/entangle by the fabricating
moving part of area
dangerous part of machinery and
machinery cause body injury.

2.Excessive 2.Potential to 1.To maximize 3 3 9


manual handling sustain body injury usage of
machinery aid to
minimize manual
handling

2.To organized
work rotation

3.Conduct Tool
Box Talk on
manual handling
hazard and
control prior to
formwork
fabrication
4.Wear
appropriate PPE

b. Excavation work for 1.Poor shoring 1.Excavation wall 2.To provide 3 3 9


pile cap preparation collapse standing
supervision by
designated
person

2.Expose to hit 2.Potential to 1.To barricade 3 3 9


by moving arm of excavated area
excavator
be hit by
moving arm/ 2.To provide
standing
body injury supervision by
designated
person

3.Work must be
carried out by
trained personnel

4.Conduct Tool
Box Talk on
excavation safety
prior to
excavation work

5.Wear
appropriate PPE

c. Pile cap re-bar 1.Expose to 1.Potential to Work must be


installation sharp object cause leg and carried out by 3 3 9
hand injury trained personnel

2.Conduct Tool
Box Talk on cut
hazard and
control prior to
pile cap re-bar
installation

3.Wear
appropriate PPE

2.Excessive 2.Potential to
1.To organized 3 3 9
manual handling sustain body injury
work rotation
2.Work must be
carried out by
trained personnel
3.Never lift heavy
load alone, seek
assistance from
other
4.Conduct Tool
Box Talk on
manual handling
work and control
prior to manual
handling work
5.Wear
appropriate PPE
j. Manual pile cap 1.Expose to 1.Potential to 1.Work must be
concrete work contact with wet cause leg injury carried out by 4 2 8
cement mixture trained personnel

2.Conduct Tool
Box Talk on
concreting safety
prior to concrete
work

3.Wear
appropriate PPE
2.Excessive 2.Potential to 1.To organized
work rotation 3 3 9
manual sustain body
handling injury 2.Work must be
carried out by
trained personnel

3.Never lift heavy


load alone, seek
assistance from
other

4.Conduct Tool
Box Talk on
manual handling
work and control
prior to manual
handling work

5.Wear
appropriate PPE

k. Pile cap back Expose to hit Potential to 1.To barricade 3 3 9


filling by moving cause physical excavated area
arm of injury
2.To provide
excavator
standing
supervision by
designated
person
3.Work must
be carried out
by trained
personnel
4.Conduct
Tool Box Talk
on back filling
safety prior to
back filling
work
5.Wear
appropriate
PPE