Professional Documents
Culture Documents
Cold Startup and Shutdown
Cold Startup and Shutdown
0 0’ Boiler pr. -Start instrument air compressor -Check that all circuits have
‘0’ kg/cm2 and check that all lines to Boiler sufficient air pressure.
(g) and and TG are charged.
ambient —Start plant air compressor and fill
temp. the air receiver tanks of SRAPH &
PRAPH
—Ensure that purge air to HEA is
open in all corners.
—Line up Air and flue gas circuits -Check dampers and gates and
for start up. register position.
—ESP ready in all respects.
—Furnace bottom ash system and
seal trough lined up.
03 100’ Boiler -Switch on automatic control -As soon as the fixed set point
pressure: interface of LP bypass. reaches 12 kg/cm2, it seizes.
5 kg/cm2. -Open main steam valves. -Automatic control interface gets
-Open HP by pass. switched off when the hot reheat
-Start third CC pump. , when boiler steam pressure reaches 13 kg/cm2
pressure reaches 9 kg/cm2. i.e. after synchronization.
-Take additional guns in CD & EF
elevation.
-Close HPBP warm up valves.
ROLLING THROUGH EHC
Ste Time Unit condition Operation Notes
p
04 150’ MS Pr: 16 kg/cm2. -Open HPSVs& IPSVs for warming -Check and ensure that TSE
MS Temp: 180- up by operating starting device to influence is switched on and
200°C. approximately 42%. available margins are greater than
HRH Pr: +30°K
8 to 12 kg/cm2. -Check and ensure that speed set
point is zero and speeder gear is 0%
position.
(it is always done through the ATRS
PROGRAMME)
05 300’ 2
MS Pr: 16 kg/cm . -Raise the starting device to about -Check and ensure opening of valves
MS Temp: 350°C. 70%. in HP/IP secondary fluid lines to
HRH Pr: 12 EHC at speed control rack. ALSO
kg/cm2. FOR EHC COIL ON
HRH Temp: 350°C. -Raise the speed set point to 360
-Turbine Ready for rpm (speed reference) and watch the -If tracking device is switched ON,
Rolling actual speed. starting device position will
-Raise the speeder gear to 100%. automatically track the EHC
position.
-Hold the speed at 360 rpm for -Ensure closure of gate valve gearing
about 35 to 40 mts. at 240 rpm.
-Monitor bearing vibrations bearing
temperatures, Shaft vibrations, TSE
margins and turbovisory readings.
Step Time Unit Operation Notes
condition
06 360 MS Pr: 50 -Raise the speed set point to 3000 -Ensure tripping of jacking oil pump at
kg/cm2. rpm. 540 rpm.
Temp. : -The rate of acceleration will be 600 to
350°C. 850 rpm2.
Turbine -Monitor bearing vibration, and
Running at temperatures, shaft vibration,
360 rpm. Turbovisory readings and TSE margins.
-Monitor and control, Seal oil
temperatures, Primary water temp,
Hydrogen gas temperature and winding
temperatures.
-Ensure tripping of AOP at 2950 rpm.
07 370 MS. Pr: 50 -Put AVR on auto, Close Field
kg/cm2 breaker,
Temp.: 350°C -Set manually generator voltage to (ALWAYS USE AUTO SYNC)
Turbine grid voltage.
speed: 3000 -Synchronise the generator with grid. -Speed set point will rise automatically
rpm. -Raise the speed set point and pick up by 8 RPM and load will be picked up to
the load to 50 MW. 20 MW.
05 300’ MS Pr: 16 kg/cm2. -Turbine speed will be raised to -Ensure closure of gate valve gearing at
MS Temp: 350°C. 360 rpm through SGC - 240 rpm.
HRH Pr: 12 Programme -Monitor bearing vibration, bearing
kg/cm2. temperature, shaft vibration, TSE
HRH Temp: 350°C. margins and turbvisory readings.
-Turbine Ready for -To achieve the programme as per the
Rolling starting curve, the main steam
temperature should be maintained
steadily till loading up to 50MW.
Step Time Unit Operation Notes
condition
06 360 MS Pr: 50 -Turbine speed will be raised up to -Ensure tripping of JOP at 540 rpm.
kg/cm2. 3000 rpm through SGC - -Ensure tripping of AOP at 2950 rpm.
Temp. : programme. -Monitor bearing temp. and vibrations,
350°C. shaft vibrations, TSE margins and
Turbine turbovisory reading seal oil, primary
Running at water, Hydrogen gas and Generator
360 rpm. winding temperatures.
07 370 MS. Pr: 50 -SGC Programme will switch ON -Ensure SGC - start up programme is
kg/cm2 field breaker, put AVR on auto, completed.
Temp.: 350°C synchronise and pick up load upto 20
Turbine speed: MW.
3000 rpm. -Raise the speed set point and pick
up the load upto 50 MW.
1 Start reducing the pulveriser coal flows -Check that load reduction is
gradually in all the mills. approx.5MW/niin.
2 Take the attemperation control in manual mode
and slightly raise the controller output to bring
down MS / HRH temperatures.
3 Reduce the AVR set point by pressing the lower
button.
4 Gradually reduce the throttle pressure set point - The ESV/Control valve temperatures
to about 130 kg/cm2 and load to 400 MW start dropping followed by mean
temperatures.
5 Turn the burner tilt down.
6 With the reduction in the coal flow, reduce the
total air flow.
7 Further drop the main steam and reheat -Check the decreasing trend on TSE 12
temperatures to cool the turbine. point recorder.
8 Stop the topmost pulveriser to reduce the firing
(after emptying the feeder).
Step Operation Notes
9 Close the extraction block valves to HP heater 6B - As the extraction block valve closes, notice the
and 5B. closure of drain control valve as there is no steam
flow to the heater.
- The boiler pressure increases momentarily and
then drops.
10 Further reduce the coal firing. - Ensure that the unit is in Turbine follow mode
with initial pressure control mode in service.
- Check the furnace pressure, drum level and PA
header pr.
11 Stop one more pulveriser to reduce the firing. - Check the furnace pressure, drum level and PA
Take blade pitch control of one PA fan into header pr.
manual and stop it after unloading. - Check the flame intensity at elevations
corresponding to running feeders.
12 Reduce the main steam temperature and hot
reheat steam temperature by raising the
attemperation flow.
13 Transfer the furnace pressure controller to manual
mode and reduce the loading on one ID fan and
load the other fan.
14 Unload one FD fan corresponding to above ID -Maintain furnace pressure and air flow.
fan which is unloaded.
15 Stop one ID fan and one FD fan by giving a stop - Ensure flame stability within furnace. If
command from UCB. necessary cut in oil support. Three feeders with
loading above 75% may not need the oil support.
Step Operation Notes
16 Check that the inlet/outlet dampers of ID fan and
discharge damper of FD fan close on auto.
19 Reduce the target load set (load reference) value - Ensure that LP Bypass controller is kept on auto
from the governing console i.e., Pr (ref) & P(lim) with fixed set point slightly below the sliding set
comes down at a rate set by the load gradient. point.
20 As the throttle pressure increases on reduction of
load the HP Bypass valves will open on auto
causing the cold reheat pressure to go up. Once
this pressure exceeds the sliding set point, LP
Bypass valves will also open.
21 Further reduce the load set point from governing - Check that the opening of HP Bypass valves
console. increases further. The
HRH temperature can be controlled by controlling
CRH temp. by HP Bypass attemperation valves.
25 Close the extraction block valves of LPH 2&3 - Check that the drain control valve closes.
once the load has come
below20%. Open the drains of extraction lines.
26 Transfer the 30% FRS to auto mode and take the Maintain hot well, deaerator and drum level
50% FRS to manual mode. during transient operation.
31 Stop the remaining two pulverisers one after -Check that all fuel air dampers close from
the other after emptying the feeders and top to bottom.
mills. Stop the second PA fan after
unloading it.
TURBINE SIDE:
- Turbine trips on Boiler trip protection.
- Ensure the closure of Turbine Stop valves/Control valves.
- Ensure that the Turbine is coasting down.AOP takes start at 2800 RPM.
- Ensure that all MAL valves open.
- Ensure that at about 540RPM, the JOP takes start and jacking oil pressure
comes to about 125 kg/cm2.
-At about 210RPM, check that the barring gear valve starts opening and
turbine speed is maintained to about 190RPM.
-Check that the seal steam pressure/temp. is maintained and condenser
vacuum satisfactory.
GENERATOR SIDE:
-Generator trips on low forward power protection.
-Ensure opening of generator breakers (2552 & 2452).
- Ensure the opening of field breaker.
Step Operation Notes
37 If Aux steam is not lined up for TDBFPs Trip
them and take MDBFP into service
42 - Increase feed water flow -Ensure that the blow down valves are closed.
- Stop the drum filling once all the ports of the
hydrastep are indicating water (green lamps on).
to top up the drum level.
43 Stop the chemical dosing pumps.