BK91-1310-CPF-000-PMT-MAN-0001
MANAGEMENT Revision A
Page 1 of 8
MANAGEMENT Revision A
Page 2 of 8
MANAGEMENT Revision A
Page 3 of 8
Contents
1.0 Scope .................................................................................................................................4
2.0 Objectives ..........................................................................................................................4
3.0 Abbreviations/definitions .................................................................................................4
4.0 References .........................................................................................................................5
5.0 Contents of Manual ...........................................................................................................6
5.1. Engineering .......................................................................................................................6
5.2. Procurement ......................................................................................................................6
5.3. Construction ......................................................................................................................7
5.4. Commissioning .................................................................................................................7
5.5. Project Control ..................................................................................................................7
5.6. Quality Management System ............................................................................................8
5.7. HSE system .......................................................................................................................8
MANAGEMENT Revision A
Page 4 of 8
1.0 Scope
This document provides the references and links of the Project management system and
associated documents to be applied to execution of EPCC of CPF-Oil Treatment System
and Auxiliary System Project.
2.0 Objectives
This PMM is intended to line out the required provisions for all key activities of engineering,
procurement, construction, commissioning, project control, quality management,
occupational health and safety etc.
3.0 Abbreviations/definitions
Term Definition
COMPANY Kuwait Energy Basra Limited (KEBL)
China Huanqiu Contracting & Engineering Corporation
PMC
Co.,Ltd.(HQC)
Consortium of China CAMC Engineering Co.,Ltd and CNOOC
CONTRACTOR
Petrochemical Engineering Co.,Ltd (CNOOCPEC)
HSE Health Safety & Environment
QA/QC Quality Assurance/Quality Control
DCC Document Control Centre
HAZID Hazard l Impact Identification
HAZOP Hazard & Operability Study
QRA Quantitative Risk Assessment
SIL Safety Integrity Level Study
PEP Project Execution Plan
PMM Project management manual
QMS Quality Management System
Add ITB
MANAGEMENT Revision A
Page 5 of 8
4.0 References
MANAGEMENT Revision A
Page 6 of 8
To ensure the successful implementation of this Project, complete the project within the
approved schedule, constraint lay out in the Contract and achieve a quality that meets the
requirements of COMPANY, the PMM consists of the following subsections:
• Engineering
• Procurement
• Construction
• Commissioning
• Project control
• Quality Management Program
• HSE system
etc.
5.1. Engineering
CONTRACTOR shall apply the basic engineering design, ITB requirement, standards and
COMPANY’s policy and procedure etc., and BK91-1310-CPF-000-PMT-PLN-0001 Project
execution Plan, BK91-1310-CPF-000-PMT-PCD-0011 Design variation procedure,
BK91-1310-CPF-000-QAC-PLN-1001 Detailed Design Quality Control Plan
5.2. Procurement
The overall project execution plan for guiding the procurement activities to go smoothly set
in BK91-1310-CPF-000-PUR-PLN-0001 Procurement plan, BK91-1310-CPF-000-PUR-PLN-
0002 Vendor management plan, BK91-1310-CPF-000-PUR-GDL-0002 Technical and
commercial evaluation guideline BK91-1310-CPF-000-PUR-PCD-0009 etc.
MANAGEMENT Revision A
Page 7 of 8
5.3. Construction
The CONTRACTOR shall organize logically and reasonably to ensure smooth progress of
all activities for achieving satisfactory mechanical completion, commissioning and start-up
on schedule and with high quality.
5.4. Commissioning
There are many risk factors associated with commissioning activities, the commissioning
team must comply with both commissioning and HSE requirements: Details refer to
In order to assure that the project implementation be carried out in a professional and
efficient manner, CONTRACTOR shall formulate and implement a total project control
system. This involves in closely with COMPANY at an on-going basis, to review engineering,
procurement and construction, and to incorporate with any additional/changes of work to
meet COMPANY’s requirements. The contractor shall apply BK91-1310-CPF-000-PRC-
PCD-0001 Project progress measurement procedure, BK91-1310-CPF-000-PRC-PLN-0001
Project schedule development and control plan, BK91-1310-CPF-000-PRC-SCH-0001
Project Baseline Schedule, BK91-1310-CPF-000-PRC-SCH-0002 Project Forecast /
Recovery Schedule.
capital letter
MANAGEMENT Revision A
Page 8 of 8
CONTRACTOR is an ISO 9001 QMS Certified organization. CAMCE will develop all
necessary Project Quality Management System plan & procedures suitable for managing the
quality of engineering, procurement, construction, commissioning and warranty of the
system and effectively implement throughout the project. The systems shall as a minimum,
meet the requirements of International Standard Organization ISO 9000 series and
contractual requirements: BK91-1310-CPF-000-QAC-PLN-0001 Project Quality Plan, BK91-
1310-CPF-000-QAC-PLN-0002 Project Audit Plan etc.
CONTRACTOR shall establish the HSE system to cover the outlines of the Site Safety,
Health and Environment management system and HSE programs to be applied to Execution
of EPCC of CPF-Oil Treatment System and Auxiliary System Project. The HSSE system
refer to: BK91-1310-CPF-000-HSE-PLN-0001 HSSE Plan, BK91-1310-CPF-000-HSE-PLN-
0006 Environment Protection plan, BK91-1310-CPF-000-HSE-PLN-0003 HSE Training Plan,
BK91-1310-CPF-000-HSE-PCD-0010 COVID 19 Procedure, BK91-1310-CPF-000-HSE-
GDL-0002 HSE performance improvement guideline, BK91-1310-CPF-000-SEC-PLN-0002
Security and Emergency Preparedness and Response (EP&R) Plans etc.