LIST OF CONTENTS
Page
This method of statement shows how is the proper way of application of liquid applied
bituminous waterproofing to blinding or PCC approved drawing. To keep safe property
and equipment from waste as per the approved drawings and Client /consultant
Project specifications& (KKIA ),(WSP).
This Work Method Statement refers to various work procedures contained within project
control documents, which explains and covers the application of liquid applied
bituminous.
.
The method statement shall be briefed to all appropriate operatives to ensure that they are
aware of the sequence of activities and any Client/Consultant project specific requirements.
3.2 Revision of this document will be issued in accordance with the project procedure
andrequirement.
3
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
5.0 RESPONSIBILITY
• Project Manager
• Construction manager.
• HSE Manager.
• Technical office Engineer.
• Site Engineer
• QA/QC Engineer
• Supervisor
6.0 RFERENCES
7.0 Resources
The following equipment will be required for the execution of the liquid waterproofing,
whereby the number of equipment required will be determined upon progress and upon
schedule requirements:
7.1.1 Roller.
7.1.2 Slow speed drill machine
7.1.3 Container
7.1.4 Bruch
7.1.5 PPE: ,Respirator, Safety, Warning device.
7.2 MATERIAL
7.2.1 Approved Bituminous Waterproofing Material timbers
7.2.2 Coal tar epoxy
7.2.3 Gloves ,Safety shoes etc.
4
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
5
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
Any projections or protrusions on the blinding concrete surface would be removed to obtain a
smooth surface. The surface must be cleaned and free from dust, dirt loose materials.
Blinding concrete surface shall be primed with approved primer coating recommended by the
6
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
Then membrane to be placed in the correct torching on position then re-rolled for
about half of its length without changing its orientation.
The membrane is then un-rolled again and torched on pressing the melted area
against the substrate.
7
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
Repeat till the entire length of the membrane is bonded firmly onto the surface then
the second membrane is laid in the same way with a minimum an overlap of 100
mm at the end and side.
For vertical application, one layer of 4mm thick modified bituminous waterproofing
membrane shall be applied to all vertical surfaces after applying the primer coating.
The membrane which is fixed on the horizontal surfaces or concrete vertical wall
shall be protected from any damage due to rebar fixing, formworks, concreting of
the raft.
For the vertical surfaces, the membrane will be protected with 3 mm protection
board above the membrane sheets.
For the horizontal surfaces, 50 mm of screed concrete will be poured above the
membrane sheets to protect it from any damage that may occur to the
waterproofing
8
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
9
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
10
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
Project specific HSE Plan covering all aspects of construction safety, environmental protection and
urity protection has been submitted to the Client for approval. This plan included:
A dedicated Health and Safety team will be deployed to the site under the
supervision of a Health and Safety Engineer and Safety Officers. The project will
be controlled as per the approved health and Safety plan.
It is Metito’s policy that every employee shall be provided with a healthy and safe
environment in which to work. To this end, every effort will be made and positive
action taken at all times, by all employees, to ensure healthy and safe working
conditions at all company project work site and facilities.
The general philosophy is each person on site is responsible for safe working
practice
HSE team shall monitor, guide and train all employees’ to achieve a safe working
environment by implementing work rules to achieve these goals
Regular job safety analysis will be done
Regular awareness programs will be conducted
Special training programs
Encourage communication from work force
Encourage daily reminders by each supervisors
Weekly surveillance of all rigging equipment and tools, site manpower distribution
Fire prevention program, identify hazardous areas, material and storage, establish
Daily tool box meetings for supervisory and non-supervisory work force.
11
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT
12