You are on page 1of 12

lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:

Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

Method statement of Waterproofing


lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

LIST OF CONTENTS
Page

1.0 PURPOSE ................................................................................................................ 3


2.0 SCOPE......................................................................................................................3
3.0 Document control:..................................................................................................3
4.0 DEFINITIONS, TERMS AND ABBREVIATIONS...........................................................3
5.0 RESPONSIBILITY ......................................................................................................4
6.0 REFERENCES ............................................................................................................4
7.0 Resources................................................................................................................4
7.1 EQUIPMENT And Tools ...........................................................................................4
7.2 MATERIAL .....................................................................................................................4
7.3 WORK EXECUTION/PROCEDURE waterproofing .........................................................6
7.4 WORK INSPECTION FOR Waterproofing ...................................................................11
8.0 SAFETY AND HAZARD PLAN ........................................................................................11
9.0 job safe practice analysis ...........................................................................................12
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

1.0 MOS PURPOSE

This method of statement shows how is the proper way of application of liquid applied
bituminous waterproofing to blinding or PCC approved drawing. To keep safe property
and equipment from waste as per the approved drawings and Client /consultant
Project specifications& (KKIA ),(WSP).

2.0 MOS SCOPE

This Work Method Statement refers to various work procedures contained within project
control documents, which explains and covers the application of liquid applied
bituminous.
.

The method statement shall be briefed to all appropriate operatives to ensure that they are
aware of the sequence of activities and any Client/Consultant project specific requirements.

A constant monitoring and supervision duty shall be undertaken by contractor to ensure


work activities are carried out in accordance with the method statement. Any irregularities
shall be immediately actioned.

3.0 DOCUMENT CONTROL

3.1 This project procedure is a controlled document as required by the Project


Policyand issued in accordance with the contractual requirements.

3.2 Revision of this document will be issued in accordance with the project procedure
andrequirement.

4.0 DEFINITIONS, TERMS AND ABBREVIATIONS

4.1 RMP: Requirement Management Plan

4.2 QMP: Quality Management Plan

4.3 HSE: Health, Safety and Environment

4.4 HSERA: Health, Safety and Environment Risk Assessment

4.5 GIS: Geographic Information System

3
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

5.0 RESPONSIBILITY
• Project Manager
• Construction manager.
• HSE Manager.
• Technical office Engineer.
• Site Engineer
• QA/QC Engineer
• Supervisor
6.0 RFERENCES

• Contract & KKIA Specification. ( REF NO: DIV-03 ).


• Contract as built structure Drawings.
• Approved design Drawing.
• Pouring concrete method statement.
• Rebar method statement
• General site layout ( REF NO: MSL-1718-T-DDR-CV-0001-00 ).
• HSE Plan (REF NO.: MSL-1718-Q-HSP-HS-0001-01).
• Geotechnical report ( REF NO: MSL-1718-Q-MSP-SU-0002 ).
• Project quality plan ( REF NO: MSL-1718-Q-PQP-GN-0001-00 ).
• American concrete institute ACI
• American society for testing and material ASTM.

7.0 Resources

7.1 EQUIPMENT And Tools

The following equipment will be required for the execution of the liquid waterproofing,
whereby the number of equipment required will be determined upon progress and upon
schedule requirements:

7.1.1 Roller.
7.1.2 Slow speed drill machine
7.1.3 Container
7.1.4 Bruch
7.1.5 PPE: ,Respirator, Safety, Warning device.

7.2 MATERIAL
7.2.1 Approved Bituminous Waterproofing Material timbers
7.2.2 Coal tar epoxy
7.2.3 Gloves ,Safety shoes etc.

4
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

5
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

7.3 WORK PROCEDURE OF Waterproofing :

7.3.1 Delivery and Storage


 material shall be delivered to site by truck or any proprietary
vehicle that material shall reached on site undamaged
 Make sure that material is sealed with labels indicating the
manufacturer name, trademark, date of manufacture, and expiry
 Material shall be stored in safe material storage with shade
and or at the area out of direct sunlight.
7.3.2 Work and surface preparation:

Any projections or protrusions on the blinding concrete surface would be removed to obtain a
smooth surface. The surface must be cleaned and free from dust, dirt loose materials.

7.3.2 Primer Application:

Blinding concrete surface shall be primed with approved primer coating recommended by the

manufacturer of the membrane prior to placing the membrane.

Coating will be done using a normal painting roller or brush.

6
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

7.3.3 Membrane Application

 Waterproofing membrane application, one layer of 4mm thick modified bituminous


membrane shall be laid on blinding concrete with a minimum of 100 mm end and
side overlaps.

 Waterproofing membrane installation shall be performed using cylinder fed


propane gas torch, trowel to seal the membrane sheets and a small knife for cutting
the extra edges.

 Then membrane to be placed in the correct torching on position then re-rolled for
about half of its length without changing its orientation.

 The membrane is then un-rolled again and torched on pressing the melted area
against the substrate.

7
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

 Repeat till the entire length of the membrane is bonded firmly onto the surface then
the second membrane is laid in the same way with a minimum an overlap of 100
mm at the end and side.

 An extra length of minimum 200mm of the horizontal membrane shall be left to


carry up the vertical surface to maintain continuity of the membrane and be
protected as above.

 For vertical application, one layer of 4mm thick modified bituminous waterproofing
membrane shall be applied to all vertical surfaces after applying the primer coating.

 The membrane on the exposed external vertical surfaces shall be carried up to a


minimum of 150 mm above the finished ground level.

 The membrane which is fixed on the horizontal surfaces or concrete vertical wall
shall be protected from any damage due to rebar fixing, formworks, concreting of
the raft.

 For the vertical surfaces, the membrane will be protected with 3 mm protection
board above the membrane sheets.

 For the horizontal surfaces, 50 mm of screed concrete will be poured above the
membrane sheets to protect it from any damage that may occur to the
waterproofing

8
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

9
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

10
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

7.4 WORK INSPECTION FOR Waterproofing WORK

7.4.1 The inspection requests shall be in accordance with the ITP.

8.0 SAFETY AND HAZARD PLAN

Project specific HSE Plan covering all aspects of construction safety, environmental protection and
urity protection has been submitted to the Client for approval. This plan included:

 A dedicated Health and Safety team will be deployed to the site under the
supervision of a Health and Safety Engineer and Safety Officers. The project will
be controlled as per the approved health and Safety plan.
 It is Metito’s policy that every employee shall be provided with a healthy and safe
environment in which to work. To this end, every effort will be made and positive
action taken at all times, by all employees, to ensure healthy and safe working
conditions at all company project work site and facilities.
 The general philosophy is each person on site is responsible for safe working
practice
 HSE team shall monitor, guide and train all employees’ to achieve a safe working
environment by implementing work rules to achieve these goals
 Regular job safety analysis will be done
 Regular awareness programs will be conducted
 Special training programs
 Encourage communication from work force
 Encourage daily reminders by each supervisors
 Weekly surveillance of all rigging equipment and tools, site manpower distribution
 Fire prevention program, identify hazardous areas, material and storage, establish
 Daily tool box meetings for supervisory and non-supervisory work force.

11
lient: UPGRADE AND EXPANSION OF WASTEWATER Contractor:
Project Name: TREATMENT PLANT

Project No.: 225211300


Consultant:
MS FOR Waterproofing
Document Title:
Document No.: MSL-1718-E-MST-CV-0000-00

9.0Job Safe Practice Analysis:

12

You might also like