Executive Summary………………………………………………………………………………………...3
1 FINANCIAL REPORT ............................................................................................................... 4
1.1 INVOICE PAYMENT STATUS MARCH 2023 ............................................................................. 4
1.2 SPARE PARTS ..................................................................................................................... 5
1.3 ADDITIONAL INFORMATION ................................................................................................... 6
2 PERFORMANCE ASSESSMENT ...................................................................................................... 9
2.1 OVERALL SERVICE MONITORING .......................................................................................... 9
2.1.1 TRAM OPERATION STATISTICS .......................................................................................... 9
2.1.2 KPI REPORTING ............................................................................................................. 9
2.1.3 OTHERS KPI’S .............................................................................................................. 10
2.1.4 OPERATIONS AND MAINTENANCE ................................................................................... 23
2.1.5 HEALTH AND SAFETY .................................................................................................... 23
2.1.6 INCIDENT REPORTING ................................................................................................... 26
2.1.7 DEPOT CONSTRUCTION AND TRAM PROJECT PROGRESS ................................................ 26
2.1.8 AUDIT REPORTS ........................................................................................................... 27
2.1.9 TRAINING OF THE TRAM TEAM ....................................................................................... 28
2.1.10 STAFFING ..................................................................................................................... 28
2.1.11 NON-CONFORMANCE .................................................................................................... 28
3 OPEN ISSUES ............................................................................................................................ 28
3.1 REACTIVE MAINTENANCE ................................................................................................... 28
4 CHANGE M ANAGEMENT ............................................................................................................. 31
5 INNOVATION .............................................................................................................................. 31
6 APRIL 2023 LOOK AHEAD AND UPCOMING ACTIVITIES ................................................................ 32
7 APPENDICES ............................................................................................................................. 32
P a g e |2
Tram Monthly Report March 2023
Executive Summary
MDD tram transported 37,491 passengers during reporting month, representing an increase of 20.43% in
respect of previous month, compared with March 2022 (22,404 passengers), there was an increase of
67.34%.
Tram passenger service was suspended on thirteen (13) separated occasions for a total of 16:24 hours,
reduction mainly attributed to passenger service suspension instructed by MP for VIP tram tours and
filming sessions.
Starting on March 23rd and until further notice, it has been implemented the Tram passenger service
operating hours for Ramadan, from 18:30 to 24:00, All weekdays same timing.
We are not receiving spare parts from Trams OEM (TIG/m) in a timely manner. There are materials ordered
to TIG/m since January 2021 that are pending to be delivered by them. See section 1.2 Spare Parts.
A log is being kept of observations in relation to the systems that were retrofitted by TIG/m (trams OEM)
during their 2022 technical visit. This log is being communicated to TIG/m and MP when occurrences
happen. See appendix B.
P a g e |3
Tram Monthly Report March 2023
1 FINANCIAL REPORT
P a g e |4
Tram Monthly Report March 2023
Pending: We are not receiving spare parts from Trams OEM in a timely manner. There are materials
ordered to TIG/m since January 2021 that are pending to be delivered by them. See detail in the
following table.
P a g e |5
Tram Monthly Report March 2023
Assets
P a g e |6
Tram Monthly Report March 2023
On March 03rd, SNC tram team performed practical exercise of tram towed by another tram
inside the tram depot, this as part of the preparation for drill to be conducted on the same
matter. The date of the drill pending to be confirmed by MOI.
On March 06th, SNC tram staff participated of three VIP Tram Tours, for KSA Delegation VIP visit,
Saudi Chamber and Saudi Minister of Municipality and Delegates.
On March 08th, SNC tram staff participated of VIP Tram Tours for Earthna Summit.
On March 09th, SNC tram staff participated of VIP Tram Tours for Earthna Summit.
On March 13th, SNC tram staff participated of VIP Tram Tours for Smart -Score.
On March 19th, SNC tram staff participated of VIP Tram Tours.
On March 28th, 29th and 30th Tram #2 was branded with a new design. See following picture.
P a g e |7
Tram Monthly Report March 2023
On March 30th, SNC tram staff participated of tram filming session for Garangao video.
P a g e |8
Tram Monthly Report March 2023
2 Performance Assessment
P a g e |9
Tram Monthly Report March 2023
P a g e | 10
Tram Monthly Report March 2023
1) The number of drug and alcohol tests conducted by the railway operator and/or by its service
provider/s.
187 assessments completed during reporting month. All assessed individuals found fit for work.
As a precaution for Covid, breathalyzer device will not be use in the MDDTTS.
0 accident since we have completed 61323 loops from December 30th, 2019, to March 31st, 2023.
0 accident since we have started the trial runs for 62993 loops completed.
4) The number of health/medical assessments conducted including the number of rail safety workers who
have undergone health/medical assessments.
5) The length, in kilometres, of track over which the certificate holder has effective management and
control.
P a g e | 12
Tram Monthly Report March 2023
Km: from Dec 30th, 2019, to March 31st, 2023: 104801 kilometres.
8) The number of employees of the railway operator and its service providers engaged in provision of
railway services.
9) The number of rolling stock, with details of type of rolling stock, available for railway operations: 3
10) Any SMS audit reports (if audit conducted within the reporting months).
11) List of notifiable occurrences that occurred in the reporting period (Category A. B & C).
Category A: None
Category B: None
Category C: None
12) Investigation reports: - if an investigation report has already been provided then a report reference
number must be provided along with the information from sub-item 11 above.
13) List and details of improvement/prohibition notices issued by either MOTC or other authority having
jurisdiction.
14) Number of trams operated per day and per week (planned vs actual). 100%
Planned and Actual Deployed Tram
Date Planned Weekly Actual Weekly Remarks
1-Mar-2023 2 2 0
2-Mar-2023 2 2 0
3-Mar-2023 2 2 0
4-Mar-2023 2 2 0
5-Mar-2023 2 2 0
6-Mar-2023 2 2 0
P a g e | 13
Tram Monthly Report March 2023
P a g e | 14
Tram Monthly Report March 2023
15) Total number of Loops completed & passengers carried during the reporting period
(Including numbers on daily basis).
Sum of Loops / Passengers per Month Remarks
Total
# Of Tram Passenger
Year Date 1 2 3 Loops
Deployed Count
per Day
1-Mar 29 48 19 96 2 1075
2-Mar 48 0 48 96 2 1639
58 Loops: passenger service, (-) 1 Loop:
late arrival of security at the time of tram
exit, (-) 4 Loops: as instructed by Turgay, to
3-Mar 27 0 31 58 2 1353
operate only one tram for passenger
service due to heavy traffic, (-) 1 Loop: due
to heavy traffic
4-Mar 48 48 0 96 2 1917
5-Mar 48 21 27 96 2 2458
72 Loops: passenger service, (+) 2 Loop:
without passenger preparation for VIP
tour, (+) 2 loops: Tour with VIP KSA
Delegation & Saudi Chamber and Saudi
Minister of Municipality and Delegates, (-)
6-Mar 0 39 37 76 2 2255 19 loops: waiting time for KSA Delegation
& Saudi Chamber and Saudi Minister of
Municipality and Delegates, (-) 1 loop: due
to longer time for trams to complete loop
due to stations are crowded with potential
passengers
2023 84 Loops: passenger service, (-) 12 loops:
Work in progress at Al Kahraba St. for
7-Mar 0 46 38 84 2 2242
replacing the banners of FIFA World Cup
design for a new design
72 Loops: passenger service, (+) 1 loop:
MDD Tour for Earthna Summit tour, (-) 12
loops: waiting time for MDD Tour for
Earthna Summit, (-) 1 loop: late arrival of
8-Mar 33 0 40 73 2 2060 security, (-) 1 loop: due to longer time for
trams to complete loop due to stations are
crowded with potential passengers
(-) 9 loops: Tram 1 technical issue (all
DAMS buttons were not resetting DAMS)
82 Loops: passenger service, (+) 1 loop:
MDD Tour for Earthna Summit, (-) 11
loops: waiting time for MDD Tour for
9-Mar 18 23 42 83 2 2377
Earthna Summit, (-) 2 loops: longer time
for trams to complete loop due to stations
are crowded with potential passengers
63 Loops: passenger service, (-) 1 loop: due
10-Mar 18 32 13 63 2 1957
to RHS door malfunction for Tram 1
11-Mar 31 17 48 96 2 1529
P a g e | 15
Tram Monthly Report March 2023
12-Mar 48 48 0 96 2 1219
P a g e | 16
Tram Monthly Report March 2023
Below are the details of the timetable change as per MP’s request.
Starting March 23rd and until further notice, it was implemented the Tram passenger service operating
hours for Ramadan as follows:
18) Number and extent of service interruptions/ disturbances/ re-routing (if any).
P a g e | 17
Tram Monthly Report March 2023
Re-routing
Re-routing Re-routing
Re-routing Re-routing Duration of Re-
Item Reason of Re-routing Starting Ending
date Ending date routing (hh:mm)
Time Time
Requested by MP to use stage 1
1 as stage 2 is used for filming 30-Mar-23 19:00 30-Mar-23 0:00 5:00
session
Total 5:00
P a g e | 18
Tram Monthly Report March 2023
2022 2023
Classification APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR
Violation 0.04 0.06 0.05 0.07 0.07 0.04 0.07 0.04 0.04 0.04 0.05 0.06
Vehicle obstruction 0.03 0.02 0.02 0.01 0.01 0.00 0.01 0.02 0.01 0.01 0.02 0.02
No streetlights 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
No Lights at the station 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Obstruction on the tracks 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
No Security guard on duty 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
General observation 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Traffic signalization issue 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
P a g e | 19
Tram Monthly Report March 2023
The following 3 charts provide the detail of the 3 hazards with highest grand total numbers registered.
0.05
0.00
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR
Violation
Vehicle obstruction
No street lights
P a g e | 20
Tram Monthly Report March 2023
In the following table it is provided the detail of traffic violations registered per location during the
reporting month, sorted by count of Traffic Violation:
Year 2023
Month Name March
Count of traffic
Locations Remarks
violations
Junction 5 47
Junction 4 22
Junction 2 14
Station 6 11
Junction 14 9
Junction 13 7
Junction 7 4
Junction 1 3
Junction 10 2
Junction 6 2
Junction 11 2
Station 9 1
Junction 9 1
Station 08 1
Qasr Suhaim Street 1
FGL Entrance 1
Junction 15A 1
Station 7 1
Q03 Parking Entrance 1
Grand Total 131
P a g e | 21
Tram Monthly Report March 2023
In the following picture are marked the location of 3 junctions with highest numbers of traffic violations
in the reporting month.
As observed in the previous table and picture, Junction 5, 4 and 2 respectively, presented the highest
numbers of traffic violations.
23) Variation observed on the tram system (driving rules, SOP’s, protocols)
0 during the reporting Month.
P a g e | 22
Tram Monthly Report March 2023
NOTICES
0 notices were posted during this reporting Month.
SRP Meetings:
COVID-19
Since beginning of COVID-19 pandemic and up to reporting date, 11 cases have been registered in the
tram staff.
In the following table are provided details of tram staff COVID-19 vaccination status.
Recovered
Vaccinated from COVID
Eligible for 3rd
Sr No Name Fully/Partia Positive 1ST Dose 2nd Dose 3rd Booster Dose
Dose
lly/No Earlier
Yes/No
1 Juan David Fernandez Fully No 29-Apr-21 20-May-21 14-Jan-22
2 Glenberth Madrona Fully No 23-Apr-21 14-May-21 23-Nov-21
3 Glenn Velasco Fully No 27-Jan-21 17-Feb-21 26-Oct-21
4 Fabeena Faisal Fully Yes 26-Apr-21 17-May-21 27-Dec-21
5 Mahendra Kumar Fully No 5-May-21 27-May-21 03-Feb-2022
6 Reginald Ortiz Fully Yes 6-May-21 27-May-21 13-Feb-2022
7 Anish Samkutty Fully Yes 27-Jan-21 17-Feb-21 25-Sep-21
8 Ibrahim Ismael Fully Yes 27-Apr-21 18-May-21 Not Registered for 3rd dose Yes
9 Sabri Harriga Fully Yes 20-May-21 10-Jun-21 Not interested in 3rd Dose Yes
Ahmad Sadik Amin
10 Fully No 27-Jan-21 17-Feb-21 25-Oct-21
Mohamed
11 John Renz Retiro Fully Yes 26-May-21 17-Jun-21 Not Registered for 3rd dose Yes
Not interested in 3rd Dose
12 Nesredin Musa Ibrahim Fully No 26-Apr-21 29-Jun-21 (also recovered from Yes
COVID-19)
13 Mohammadseid Hijay Fully No 26-May-21 29-Jun-21 Not interested in 3rd Dose Yes
Mohammad Hassan
14 Fully Yes 22-Sep-21 24-Oct-21 Not Registered for 3rd dose Yes
Chakeri
rd
15 Mohamedseid Abdu Fully Yes 13-Jan-22 10-Feb-22 Not Registered for 3 dose Yes
16 Mary Rose Yap Fully Yes 10-May-21 3-May-21 12-Dec-21
17 RajiniKumar Boini Fully No 26-Jun-21 26-Oct-21 20-Jul-22
Rahul Vaderiyattil
18 Fully No 24-Sep-21 05-Oct-21 Not Registered for 3rd dose Yes
Mohandas
HSE REPORT:
P a g e | 23
Tram Monthly Report March 2023
Leading Indicators:
MAR 369 1 12 2
P a g e | 24
Tram Monthly Report March 2023
Lagging Indicators:
0 0 22
P a g e | 25
Tram Monthly Report March 2023
Date Temperature (° C) Dew Point (° C) Humidity (%) Wind Speed (mph) Condition
Max Avg Min Max Avg Min Max Avg Min Max Avg Min
As part of open investigation of incident number 14: Tram #1 Right passenger door opened
unintentionally, which was registered on 18th January 2023, the passenger door Electronic Control Unit
(ECU) removed after the incident from Tram #1 right side passenger door, has been shipped to TIG/m
(Trams OEM) on March 4th, 2023, for TIG/m to investigate on the root cause of the incident. The door
ECU was received by TIG/m on March 8th, 2023. It is pending for TIG/m to provide result of test
undertaken on the door ECU. There have been no further occurrences since the door ECU was replaced
with a spare unit on 18th January, 2023.
Following are listed activities pending to be completed by MP on stage 2, tram station #1 and station #9:
To get Station #1 screens connected to Scala software for content management.
P a g e | 26
Tram Monthly Report March 2023
In case it is requested to operate station #4 at some point, there aren’t videos for normal timing operation
available to be displayed at station #4 kiosk and the other stations, showing that station #4 is being
serviced. These applies for stage 1 and stage 2 operations. Videos for Station #4 for Ramadan timing are
available.
Stage 2 Tram Alignment Safety Assessment: At the end of reporting month, there are still open issues from
safety assessment submitted to MP on 15th February 2022. Refer to appendix D.
All our daily ops documents are under document control and in IAuditor (software).
The following table provides number and type of audit completed this reporting period:
Audits March 2023
Maintenance-to-Driver Turnover Checklist 91
TRAM-Tram Driver Shift Report 76
Daily/Overnight Inspection-Maintenance Checklist 70
TRAM - Depot opening/closing checklist 62
Inspection before tram operation on passengers’ alignment 31
7-Day Inspection and Maintenance Checklist 14
14-Day Inspection and Maintenance Checklist 8
TMV inspection points before run 6
30-Day Inspection and Maintenance Checklist 3
90-Day Inspection and Maintenance Checklist 3
60-Day Inspection and Maintenance Checklist 2
TMV Sweeper Weekly Service. V.0 1
TRAM - Turnout switch box cleaning 1
TMV Sweeper Engine Monthly Maintenance Checklist 1
Total 369
P a g e | 27
Tram Monthly Report March 2023
Staffing
Month Hired Termination Resignation Transfer Total SNC Service Provider Employees
March 2023 0 0 0 0 18
Total 0 0 0 0 18
3 Open Issues
Previous balance: Qty. of reactive maintenance work orders with open status at end of
previous reporting month =02
Qty. of reactive maintenance work orders opened during reporting month =12.
Qty. of reactive maintenance work orders closed during reporting month =13.
Current balance: Qty. of reactive maintenance work orders with open status at end of
reporting month =01.
Qty. of reactive maintenance work orders with open status over 30 days =01
Work STATUS
Reported Equipment
No Situation description Order CLOSED
date /Category
No. / OPEN
Generator not working and VSCF phase error fault
1 6-Dec-22 TRAM-02 796991 Open
showing in led display
P a g e | 28
Tram Monthly Report March 2023
TIG/m tickets:
Qty. of TIG/m tickets with open status at end of reporting month =09.
Qty. of TIG/m tickets opened during reporting month =00.
Qty. of TIG/m tickets closed during reporting month =00
P a g e | 29
Tram Monthly Report March 2023
When the spare bogie was delivered to the Tram Depot, it was delivered without Lubricator Bar Housing
Assemblies (8 pcs). This issue was reported to TIG/m in 2021, TIG/m stated by email that these
lubricators assemblies were being manufactured back in September 2021, when asked again by email in
February 2023, TIG/m stated it is still pending to manufacture and deliver them. In the interim, TIG/m
have instructed SNC to exchange lubricators from working bogies when necessary to use the spare bogie.
Here below the snags related to Tram Depot facility with open status at the end of reporting period:
Q03 – TRAM DEPOT SNAG REPORT
Description Location Reporting date Status SR Number
(dd/mm/yyyy)
No exit signage in dispatcher room, Management, 11-Jul-2018 Open 92113
administration room and break Administration &
room Break room.
No Hot water in all pipes Break room and Toilet 31-Jan-2018 Open 92114
No extraction or air conditioning Offices Ground Floor Male 30-Apr-2018 Open 92115
inside both restrooms Toilet
Air Compressor issue not connected Tram Depot Compressor 13-Dec-2021 Open 97796
to the pipe room
Cracked flooring Tram Depot Workshop 10-Apr-2022 Open 174631
Here below the service request related to Tram alignment and tram stations with open status at the end
of reporting period:
P a g e | 30
Tram Monthly Report March 2023
4 Change Management
No changes registered during the reporting month.
5 Innovation
Source: https://www.startus-insights.com/innovators-guide/top-10-rail-industry-trends-innovations-
2021-beyond/
The US-based startup Hoeller Electrolyzer provides polymer electrolyte membrane (PEM) electrolysis
stacks for the manufacturers of green hydrogen systems. The startup offers its Prometheus Electrolysis-
Stacks to optimize hydrogen fuel cell storage capabilities in electric and hybrid locomotives. This
optimization increases the maximal output of PEM electrolysis and also lowers the costs of storing green
hydrogen.
P a g e | 31
Tram Monthly Report March 2023
The setting of tram kiosk screens of station 1 and 9 to be completed to be able to manage content
with Scala software.
7 Appendices
Appendix A: Abbreviations and Definitions
Appendix B: Log of observations in relation to the systems that were modified by TIG/m during 2022
technical visit.
Appendix C: Received copy of SRP MOM 044, March 2023
Appendix D: Stage 2 Tram Alignment Safety Assessment Tracker 22 Dec 2022
P a g e | 32
Tram Monthly Report March 2023
A/C Air-Conditioning
CCTV Closed Circuit Television
DCU Door Control Unit
ERP Enterprise Resource Planning
FRACAS Failure Reporting Analysis and Corrective Action Strategy
HSE Health, Safety and Environment
LPG Liquefied Petroleum Gas
LTI Lost Time Injury
MDD Msheireb Downtown Doha
MDDTTS Msheireb Downtown Doha tramway Transportation System
MOM Minutes Of the Meeting
MOTC Ministry of Transport and Communications
MOI Ministry of Interior
MP Msheireb Properties
NVA Next Vehicle Arrival
NVR Network Video Recorder
OEM Original Equipment Manufacturer
O&M Operations and Maintenance
OSC Operations Safety Certificate
QCD Qatar Civil Defence
SID System Information Display
SOP Standard Operating Procedure
SMS Safety Management System
SNC SNC Lavalin ProFac Gulf Management
SRP Safety Review Panel
TIG/m Transportation Innovations Group / manufacturing
TMV Track Maintenance Vehicle
TOC Tram Operations Center (Depot)
TTG Traffic Tech Gulf, MP’s subcontractor for traffic signalization / pre-emption system
VCU Vehicle Control Unit
VIP Very Important Person
P a g e | 33
Tram Monthly Report March 2023
Appendix B: Log of observations in relation to the systems that were retrofitted by TIG/m during 2022
technical visit. (Only showing issues registered in March 2023)
P a g e | 34
Tram Monthly Report March 2023
P a g e | 35
Tram Monthly Report March 2023
- END OF MINUTES -
P a g e | 37
Tram Monthly Report January 2023
P a g e | 38
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A&B 2A
P a g e | 39
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
At junction 09,
It was trimmed. It Open
The trees all planted in a row
Msheireb should be checked (regularly monitored)
4 could create a visual
Properties regularly.
obstruction of the traffic
(Mr. Jaipal) Branches found trimmed
signals for the tram drivers.
(Southwest side)
P a g e | 40
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A B&C
5A 5A
Msheireb
Refer to MP comment 18 Aug
Properties
It has been cleaned 2022
At junction 09,
P a g e | 41
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
At junction 09, A B 6A.
Sign not positioned higher to
A. “No entry” sign to be Msheireb be in the line of sight for
rotated 90 degrees and Properties motorists
positioned higher to be in
the line of sight for Open
motorists.
6B 6B
B. At same location “No Msheireb
Open
entry” sign is missing on the Properties
We will consider this
6 left side of tram track.
P a g e | 42
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A&B
7A
At junction 09,
Msheireb 7A
No entry sign installed
A. “No left turn” sign. Properties We will consider this
7 Closed
B. “Directional arrow”
marking not present (on
the road)
Msheireb 7B
Properties Closed
P a g e | 43
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A, B & C 9A
Handrail must be
Msheireb 9A
installed. It is design
Properties Open.
issue. We will consider
At station 1, this.
9B
A. When the tram departs Yellow lines painted around
station 1, a risk of 9B
the station platform. But
entrapment could occur if Msheireb It must be done. We
white lines and Mind the gap
anyone stands in the Properties will put warning sign
information not available.
open space between the soon.
edge of the platform and Open.
the tram.
B. Risk of trip and fall could
occur as no lights are
9 present on the
edges/side of the station
platform steps.
Warning stickers and signage
C. No handrail installed on 9C (Green and black
ramp area. Msheireb There must be a combination) sticked on
Properties warning sign. We will floor, it seems to remove
D. Yellow and white lines put warning sign soon due to weather conditions.
are not painted at the Open
edge of the platform, nor
"Mind the gap" markings.
P a g e | 44
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
9D
9D
Yellow lines painted around
Msheireb the station platform. No
There must be a
Properties warning signs available.
warning sign. We will
put warning sign soon
Open
P a g e | 45
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A B
P a g e | 46
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A
Msheireb 10A
10 Properties Open
We will consider this.
P a g e | 47
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A. “Tram look Left” sign is
not present to warn
cyclists or pedestrians
approaching from the
Metro station.
B
Msheireb 10B
B. From Al Mariah Street a Properties Open
We will consider this.
bicycle lane arrow/sign
points towards the stage
2 tramway and “Tram
look Right” sign is not
present to warn cyclists.
P a g e | 48
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
P a g e | 49
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
P a g e | 50
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
P a g e | 51
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
P a g e | 52
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
P a g e | 53
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
At junction 10, A B A
Msheireb 11A
A. “Do not turn left” and Properties Open
We will consider this.
“Do not turn right” signs
are not present. B
Msheireb 11B
B. “Tram look Left” sign is Properties Open
We will consider this.
not present on the left
11
side north direction at Al
Ghaffat Street.
(Southwest corner)
Msheireb C 11C
C. “No entry” sign is not Properties We will consider this. Open
present on the right-side
south direction at Al
Ghaffat Street.
P a g e | 54
Tram Monthly Report January 2023
Sr MPs comment as of
Inspection Findings Photos Action By Status as of 22 Dec 2022
No 18 Aug 2022
A B
At junction 11,
12A
A Tram sign re positioned to
A. Tram sign needs to be re- Msheireb
the right side of the road
positioned to the right of Properties
We will consider this.
the road (heading north
Closed
side of Al
Jeewan street)
12 Msheireb B 12B
C
Properties We will consider this. Open
B. “No entry” sign is not
present.
(East side).
P a g e | 55