ENGINEERING SHEET Doc. No.

BGPMRWH-E-KTE-DW-0020
PROJECT WORKSHOP & WAREHOUSE AND GUARDHOUSE
OWNER B.GRIMM POWER (AIE-MTP) LIMITED
CONTRACTOR KREETHAI ENGINEERING CO.,LTD.
PROJECT DOC NO. BGPMRWH-E-KTE-DW-0020
TITLE ROOF LIGHTNING PROTECTION SYSTEM PLAN

Revision History
Rev. Date Revision Details Prepared Checked Reviewed Approved

2 15-Dec-2022 For Approve Chartpanya P. Chartpanya P. Chartpanya P. Nuttawut L.


1 19-Dec-2022 For Approve Chartpanya P. Chartpanya P. Chartpanya P. Nuttawut L.
0 27-Jul-2022 For Approve Chartpanya P. Chartpanya P. Chartpanya P. Nuttawut L.
Distribution Issue Purpose Issued by:
B.Grimm (Soft Copy) For Review by B.Grimm Team FR Date 15-Dec-2022
For Approve A Prepared Chartpanya P.
For Information I Checked Chartpanya P.
Final, Approved for Construction F Reviewed Chartpanya P.
As Built Drawing B Approved Nuttawut L.
Kreethai Engineering Co.,Ltd.
COMMENT RESPONSE SHEET

PROJECT NAME : BGPMR Workshop & Warehouse and Guardhouse


DRAWING / DOCUMENT NO.: BGPMRWH-E-KTE-DW-0020 Revision 2
ROOF LIGHTNING PROTECTION Issued Date: 15-Jan-23
DRAWING/DOCUMENT TITLE:
SYSTEM PLAN Page 1/1

Item Rev. Owner's Comments KTE's Response


1.) 1 BGPMR: (3-JRS) Add details for installation of down
Please add more details for installation of conductor to the Test box.
down conductor to the Test box.
2.) 1 BGPMR: (3-JRS) Add remark : PROTECTION LPL CLASS IV
Please add more explain that what is Level DESIGNED EIT STANDARD 2009 - 53
of Lightning Protection Class (LPL Class
I,II, or III) that designed.
3.) 2 BGPMR : (3-JRS) Edit Bar copper to Bare copper.
Please be confirmed that it is Bar copper or
Bare copper.

Kreethai Engineering Co.,Ltd.


RD RD
0.80

WORKSHOP & WAREHOUSE AND GUARDHOUSE

DETAIL

0.80

0.80

0.80