Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1000 PIPE.PROJECT START Mobilization 30


P1010 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 1 60
P1020 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 2 60
P1030 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 3 60
P1040 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 4 60
P1050 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 5 60
P1060 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 6 60
P1070 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 7 60
P1080 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 8 60
P1090 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 9 60
P1100 PIPE.PIPELINE.PDP Pipe Delivery Kilo no. 10 60
P1110 PIPE.PIPELINE.EXC Excavation Kilo no. 1 30
P1120 PIPE.PIPELINE.EXC Excavation Kilo no. 2 30
P1130 PIPE.PIPELINE.EXC Excavation Kilo no. 3 30
P1140 PIPE.PIPELINE.EXC Excavation Kilo no. 4 30

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 1


Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1150 PIPE.PIPELINE.EXC Excavation Kilo no. 5 30


P1160 PIPE.PIPELINE.EXC Excavation Kilo no. 6 30
P1170 PIPE.PIPELINE.EXC Excavation Kilo no. 7 30
P1180 PIPE.PIPELINE.EXC Excavation Kilo no. 8 30
P1190 PIPE.PIPELINE.EXC Excavation Kilo no. 9 30
P1200 PIPE.PIPELINE.EXC Excavation Kilo no.10 30
P1210 PIPE.PIPELINE.PIP Pipe Install Kilo no. 1 80
P1220 PIPE.PIPELINE.PIP Pipe Install Kilo no. 2 80
P1230 PIPE.PIPELINE.PIP Pipe Install Kilo no. 3 80
P1240 PIPE.PIPELINE.PIP Pipe Install Kilo no. 4 80
P1250 PIPE.PIPELINE.PIP Pipe Install Kilo no. 5 80
P1260 PIPE.PIPELINE.PIP Pipe Install Kilo no. 6 80
P1270 PIPE.PIPELINE.PIP Pipe Install Kilo no. 7 80
P1280 PIPE.PIPELINE.PIP Pipe Install Kilo no. 8 80
P1290 PIPE.PIPELINE.PIP Pipe Install Kilo no. 9 80

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 2


Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1300 PIPE.PIPELINE.PIP Pipe Install Kilo no. 10 80


P1310 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 1 3
P1320 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 2 3
P1330 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 3 3
P1340 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 4 3
P1350 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 5 3
P1360 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 6 3
P1370 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 7 3
P1380 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 8 3
P1390 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no.9 3
P1400 PIPE.PIPELINE.BF1 Backfilling 1 Kilo no. 10 3
P1410 PIPE.PIPELINE.TST Testing Kilo no. 1 10
P1420 PIPE.PIPELINE.TST Testing Kilo no. 2 10
P1430 PIPE.PIPELINE.TST Testing Kilo no. 3 10
P1440 PIPE.PIPELINE.TST Testing Kilo no. 4 10

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 3


Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1450 PIPE.PIPELINE.TST Testing Kilo no. 5 10


P1460 PIPE.PIPELINE.TST Testing Kilo no. 6 10
P1470 PIPE.PIPELINE.TST Testing Kilo no. 7 10
P1480 PIPE.PIPELINE.TST Testing Kilo no. 8 10
P1490 PIPE.PIPELINE.TST Testing Kilo no. 9 10
P1500 PIPE.PIPELINE.TST Testing Kilo no. 10 10
P1510 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 1 7
P1520 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 2 7
P1530 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 3 7
P1540 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 4 7
P1550 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 5 7
P1560 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 6 7
P1570 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 7 7
P1580 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 8 7
P1590 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 9 7

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 4


Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1600 PIPE.PIPELINE.BF2 Backfilling 2 Kilo no. 10 7


P1610 PIPE.BUILD.GN.SUB Excavation (Gen. Build.) 20
P1620 PIPE.BUILD.GN.SUB Backfilling (Gen. Build.) 3
P1630 PIPE.BUILD.GN.SUPER P.C for Foundation (Gen. Build.) 4
P1640 PIPE.BUILD.GN.SUPER R.C for Foundation (Gen. Build.) 10
P1650 PIPE.BUILD.GN.SUPER Damp Proofing (Gen. Build.) 5
P1660 PIPE.BUILD.GN.SUPER P.C for Flooring (Gen. Build.) 7
P1670 PIPE.BUILD.GN.SUPER R.C for Skeleton (Gen. Build.) 15
P1680 PIPE.BUILD.GN.SUPER R.C for Slab (Gen. Build.) 21
P1690 PIPE.BUILD.GN.SUPER Brick Work (Gen. Build.) 14
P1700 PIPE.BUILD.GN.FINISH Indoor Plaster (Gen. Build.) 14
P1710 PIPE.BUILD.GN.FINISH Outdoor Plaster (Gen. Build.) 14
P1720 PIPE.BUILD.GN.FINISH Electric Work (Gen. Build.) 7
P1730 PIPE.BUILD.GN.FINISH Sanitary Work (Gen. Build.) 7
P1740 PIPE.BUILD.GN.FINISH Carpentry Work (Gen. Build.) 7

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 5


Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1750 PIPE.BUILD.GN.FINISH Flooring (Gen. Build.) 14


P1760 PIPE.BUILD.GN.FINISH Painting (Gen. Build.) 21
P1770 PIPE.BUILD.PM.SUB Excavation (Pump. Build.) 14
P1780 PIPE.BUILD.PM.SUB Backfilling (Pump. Build.) 3
P1790 PIPE.BUILD.PM.SUPER P.C for Foundation (Pump. Build.) 3
P1800 PIPE.BUILD.PM.SUPER R.C for Foundation (Pump. Build.) 7
P1810 PIPE.BUILD.PM.SUPER Damp Proofing (Pump. Build.) 3
P1820 PIPE.BUILD.PM.SUPER P.C for Flooring (Pump. Build.) 5
P1830 PIPE.BUILD.PM.SUPER R.C for Skeleton (Pump. Build.) 15
P1840 PIPE.BUILD.PM.SUPER R.C for Slab (Pump. Build.) 21
P1850 PIPE.BUILD.PM.SUPER Brick Work (Pump. Build.) 14
P1860 PIPE.BUILD.PM.FINISH Indoor Plaster (Pump. Build.) 12
P1870 PIPE.BUILD.PM.FINISH Outdoor Plaster (Pump. Build.) 14
P1880 PIPE.BUILD.PM.FINISH Electric Work (Pump. Build.) 6
P1890 PIPE.BUILD.PM.FINISH Sanitary Work (Pump. Build.) 6

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 6


Workshop 3 : Adding Project Activities

Activity ID WBS Code Activity Name Original Duration

P1900 PIPE.BUILD.PM.FINISH Carpentry Work (Pump. Build.) 6


P1910 PIPE.BUILD.PM.FINISH Flooring (Pump. Build.) 10
P1920 PIPE.BUILD.PM.FINISH Painting (Pump. Build.) 15
P1930 PIPE.BUILD.RS.SUB Excavation (Ground Reservoir) 60
P1940 PIPE.BUILD.RS.SUPER P.C for Foundation (Ground Reservoir) 14
P1950 PIPE.BUILD.RS.SUPER R.C for Foundation (Ground Reservoir) 60
P1960 PIPE.BUILD.RS.SUPER R.C for wall (Ground Reservoir) 30
P1970 PIPE.BUILD.RS.SUPER R.C for Slab (Ground Reservoir) 30
P1980 PIPE.BUILD.RS.FINISH Indoor Plaster (Ground Reservoir) 30
P1990 PIPE.BUILD.RS.FINISH Ceretal Work (Ground Reservoir) 14
P2000 PIPE.PROJECT END Commissioning 5

Eng. Magda El Talawy, MD,PMP, PSP, CCE Page 7