Professional Documents
Culture Documents
1. Introduction
1.1 Introduction and Purpose
1.2 Contract Data
1.3 Scope of Services and Objectives
1.3.1 Objective of Project
1.3.2 The Scope of Project Services
2. Project Description
2.1 Type of Project
2.2 Location
2.3 Project Background
3.9 Existing Power Supply and Telecommunication System
3.9.1 Electric Power System
3.9.1.1 Existing Electric Lines, Sub Stations and Transformers
3.9.1.2 Alternative Electric Power Source for Gelan Logistic Site.
3.9.1.3 Selection of Topology and Hierarchy
3.9.1.3.1 The fundamental structure of the power system configuration (topology)
3.9.1.3.2 Selection of Topology
3.9.1.3.3 Hierarchical Approaches
3.9.1.4 Distribution System and Design
3.9.1.5 The operation approach of the power supply system
3.9.1.6 The selection of equipment
3.9.1.7 Land use categories, power estimation, and power forecast
3.9.1.8 Distribution System Remote Monitoring
3.9.1.9 Road Lighting Design
3.9.2 Telecommunication Networks
3.9.2.1 Overview
3.9.2.2 An Existing Telephone line, cabinet and manholes
3.9.2.3 Preferred Telecom Infrastructure for Gelan Logistic Project
3.9.2.4 Optical Access Network
3.9.2.5 Full-Service Optical Access Network
3.9.2.5.1 Introduction
3.9.2.5.2 Optical Fiber
3.9.2.5.3 Optical Access Network Architecture
3.9.3 SWOT Analysis Major Finding and their Implications
3.9.3.1 SWOT Analysis
3.9.3.2 Summary of Major Findings/ Planning Issues & Planning Implications
3.9.3.3 Synthesis of Major Finding/planning issue and their implication
List of Figures
Figure 2.1 Location of the Project
Figure 2.2 Small Village nest to condominium
Figure 3.1 Picture Sample of transformer and High Tension
Figure 3.2 Picture for sample transformer and LV electric line
Figure 3.3 Sub-Station –Salo Gora Gelan condominium
Figure 3.4 Gelan condominium Sub-station
Figure 3.5 telecom tower electric utility
Figure 5.1 Typical radial topology
Figure 5.2 Typical Ring topology
Figure 5.3 SCADA block diagram system
Figure 5.4 Nomo solar pole Lighting
List of Tables
Table: 1.1 Project Data for Gelan Logistic site
The project is aimed at providing the high‐class basic infrastructure development that can
contribute to the regional, national, and international prospect investors creating opportunities to
participate in the diverse impact and export trades and manufacturing activities.
Since, smart city is a place where traditional networks and services are made more flexible,
efficient, and sustainable with the use of information, digital and telecommunication
technologies, to improve its operations for the benefit of its inhabitants. Smart cities are greener,
safer, faster and friendlier. The different components of a smart city include smart infrastructure,
smart logistics and transportation, smart energy, smart healthcare, and smart technology. These
components are what makes the cities smart and efficient. Information and communication
technology (ICT) are enabling keys for transforming traditional cities to smart cities.
The purpose of this report is to describe the current status of electric power, street light and
telecom infrastructure level in the area. It illustrates the overall infrastructure accessibility within
the selected site. Type of telecom system, transmission system and power supply and its
distribution mode of the community.
1.2 Contract Data
Project Name Andode Tuma Logistic -NDP
Client Shaggar City Administration
Consultant ECO
Type of Services
Project Period
The Consultancy services shall be carried following generally accepted standards of professional
practice, following recognized engineering procedures. The Consultant’s scope of work is to
Prepare Neighborhood Development Plan for different six sites, produce detailed engineering
designs for infrastructure and utilities in the NDP including roads, water supply,
sewerage, wastewater treatment plant, power, telecom, and solid waste site. The general scope of
the service covers the following major tasks.
Carry out the necessary field investigation including all field works like site visits, data
collection from the project site.
Carry out preliminary and final design works covering preparation of preliminary design
and final design.
Identifying and evaluating of the existing utilities, and preparing the existing statues and
the proposals.
2. Project Description
2.1 Type of Project
The project has proposed to launch Neighborhood Development Plan which is an action-
oriented development basis to improve the living standard inhabitants significantly.
2.2 Location
The site is located at about 8.862° latitude 38.7587° longitude.
It is quite evident that the energy sector has an important role to play and remarkably accelerates
the development effort of a country. Assured electricity supply is one of the core infrastructure
elements of a Smart City along with water supply, sanitation, robust IT connectivity, public
transport etc. The Shaggar City Administration announced a six of NDP projects. A Smart City
would include different types of land uses like residential, commercial, IT, hospitals, hotels etc.
Despite its enormous potential, however, Ethiopia has one of the lowest levels of energy
consumption per capita in the world, 28 kWh. Various sources confirm that only about 14% of
the population has access to electricity.
The use of electricity first started in Ethiopia in the late 19 th century during the reign of Menilk II
(1898). Following its introduction, when its use was confined only to the palace, new and
additional generators were installed to meet the growing demands for industrial and urban
development.
Yearly electric power production potential from all major rivers is estimated at 60 billion kWh
and unknown but enormous potential exists from geothermal energy and gas. The actual
aggregate production capacity of electricity power from hydro and geothermal electric power
plants amounts 1,665,812 MWH of which 1,217,922 is produced by Melka Wakena and Fincha
hydro plants.
The processes of industrial and urban development, together with rising standards of living,
influence the patterns of power consumption. Consumption from all power plants amounted to
1375.8 GWh in the year 2002, but in terms of national per capita consumption of power for one
year (2000) this amounted to only 22.31 kWh which is very small, even by African standards and
a major proportion of this low level of consumption is confined to major cities like Addis Ababa,
Adama, Dire Dawa, Bahir Dar, Mekele and Awassa.
Nevertheless, electric power consumption in various towns has shown a steady increase since
1995, following improvements made in the existing industrial units and the establishment of new
ones. Industrial consumption (in 2000) was 38.67%, domestic consumption 36.6%, commercial
establishment 23.95%, streetlight 0.68% etc.
Ethiopian Electric Power Corporation is currently the responsible institute to administer 501 MW
installed capacity, of which 472.6MW is hydroelectric and 28MW thermal power. The installed
generating capacity is estimated to reach 1110 MW and 1745 MW by the years 2010 and 2015
respectively. Over 98% of the total generation in the country comes from the hydropower
sources. EEPCO is responsible for power generation, transmission, distribution and sales of
electricity all over the nation. EEPCO's mission is to be a leading electricity provider through an
integrated and universal electrification scheme to meet the socio-economic development and
environmental protection needs of the public. EPPCO sources indicate that currently it provides
electricity to over 680.325 customers in approximately 479 towns, which is small coverage for a
country, with over 70 million population.
This article covers the various aspects of power distribution system design in smart cities.
Key Features. The key features of the power distribution system shall be as follows:
• Reliability-
• Uninterrupted and Quality supply
• Smart Sustainable
• Expandable.
3.9.1.1 Existing Electric Lines, Sub Stations and Transformers
The project site covers an agriculture land. There are only three rural kebels which do have
access to electricity. Medium voltage line with concrete pole is connected from the nearest sub-
station.
The detail of power distribution and nearby power sub-station are mentioned below…
The rural community that included do have access to electricity. They have
connected to electric grid from the nearest sub-station. An electric line with
concrete pole of 15KV connected from the nearest sub-station has been supplying
On the other hand, four electric tower carrying high tension of 66KV, 132kV,
Besides the power plants, high voltage transmission lines and substations are crucial to transfer
the generated power from the power plant to the national power grid as well as to provide quality
electricity nationwide.
Currently, the total stretched high voltage transmission lines has reached more than 17,000km
across the country ranging from 132kv to 500kv.This includes 500kv Hidase-Didesa-Holeta,
400kv Wolayta Soddo II-Addis Ababa, 230kv koka-Hurso-Dire Dawa, 230kv Alaba-Hosana-
Giligel GibeII-Gima-Agaro-Bedele, and 230kv Metu- Gambela transmission lines which is under
operation. The number of Substations has reached 163 substations ranging from 132kv to 500kv.
500kv Didesa and Holeta substations, 400kv Gibe III, 230kv Hurso, Gambela and Mehoni
substations are among the 163 substations currently under operation across the country. (Source
EEP)
3.9.1.2 Alternative Electric Power Source for Andode Tuma Site.
Among the below listed sub-station the two nearby sub-station to Andode Tuma project are...
Sub-station II which located near Gelan town near ganda Kore specific
area. It is 2.1km far from Andode Tuma site.
The second sub-station is Akaki-Kality substation. It is one of the largest
Sub-station, and found at Salo Gora, near Gelan condominium. This is
6.2km far from the project site.
However, it will not be sure if it has sufficient capacity that is reliable for smart city. The total
load estimation should be forecasted to decide about sub-station.
4 Gefersa-II 230KV
3) Existing Transformer…
Around Andode
village substation
Fig 3.3: two Sub-Stations found at –Salo Gora Gelan condominium and
Andode
3.9.1.3 Selection of Topology and Hierarchy
What are the magnitudes of initial loads and expected loads after 5, 10, 20
years?
What is the likely transformer capacity required? How many
transformers will be required and will it be better to put in a smaller
size and then increase ratings later, e.g. after 10 years?
Proximity to the load center keeping in view the future load growth.
The orientation of the proposed incoming lines to be terminated at the
substations.
Is there a suitable route for the 132kV/500kV supply to this site?
Can the 230kV/132kV line be routed to this site without constraints?
What site facilities and buildings will be required?
What minimum plot dimensions are needed for the substation?
Are there any sensitive installations nearby – e.g. telephone exchanges,
hospitals?
What type of switch gear will be best, outdoor 33KV, indoor 15KV, or some
other combination?
Calculation of substation fault levels and conductor ratings.
The cost of setting up a new substation
3.9.1.3.2 Selection of Topology
There are two main typologies in the power distribution system i.e. Radial and Ring and
1) Radial Topology
Fig-5.1-Typical radial topology
The simplest system configuration that can be found particularly at the low‐voltage and the
medium voltage level is the radial system. The individual feeders or lines are connected to the
primary or station feeder or station by radial feeders. The system is characterized by
Clear and simple structure
Low initial expenditure
Loading of lines during normal operation up to 100%
No reserve for loss of lines
System losses comparatively high
Flexibility for changed load conditions is comparatively small.
2) Ring Topology
The simplest kind of ring‐main system is obtained by connecting the lines ends back to
the feeding station. The system is characterized by:
Clear and simple structure
Loading of lines during normal operation is 50% of the
permissible loading, higher loading possible depending on the
load duration.
Reserve for one line outage is guaranteed.
System losses can be minimized.
Flexibility to respond to changing load conditions.
Standardization of cross‐sections.
Figure -5.2- Typical ring topology
A Ring main typology is selected for the power distribution as it is the most
reliable.
Reduced losses
Risk containment and mitigation
Will give a chance for future distributed energy resources
After the switching stations, RMUs are provided to the power the transformers at each premises.
As much as possible, a single RMU is used to feed two adjacent transformers. The number of
switching station and RMUs required for this project are estimated after quantity of (logistics,
industries, building, social service and so on) is known.
The aim of planning electrical power systems is to fully serve the interests of the consumers to
be supplied with electricity. To determine the configuration of the power system in terms of
technical, operational, and economic criteria, planning principles have to be defined and used.
The reliability of the power supply system (Power station, transmission, and distribution system,
etc.) is influenced by:
The operational mode of the power supply system
The selection of equipment
The fundamental structure of the power system configuration (topology)
Understandably, 100% security and reliability of electrical power supply cannot be achieved. In
each case, a compromise between supply reliability, the design of the system, the operation
requirements, the interest of consumers, and the expected investment cost are to be
considered. The power system in the Andode Tume site may be characterized into three different
subsystems according to its tasks.
The high voltage transmission grid – Its major task is the transportation of electrical
energy over long distances.
Distribution systems with 33KV – This serves as a network of distribution in urban
population centers. Industrial suppliers and high power demanding customers are
provided directly from the 33KV line.
LV distribution with 480/220V – This is mainly done for individual residential
customers.
The mode of operation is the first major element in the architecture of the power network. There
are mainly two modes i.e. overhead and underground. The general understanding is that the
underground cables are laid beneath the ground and the overhead cables are visible overhead.
But apart from this, there are many significant features of both the types of these cables from the
perspectives of electrical power transmission or distribution. In the changed scenario of the
power system design, particularly, the distribution system, the cables, and their characteristics
have become highly selective and the technological advancements have also made the selection
of cable for a particular application more flexible. Several factors are affecting the selection of
overhead or underground transmission
System cost‐ the underground system is more expensive than the overhead system. Safety ‐ as
the conductors are constantly exposed to the open atmosphere, there are several concerns related
to the safety of the system and also reliability. The adverse conditions like heavy rain, wind,
snowfall, humid and salty contents in the air could deteriorate the lifespan of these conductors
and raise serious electrical safety concerns. The underground system is not susceptible to such
environmental problems.
Suitability for long‐distance – Overhead installation is more suitable for long distances.
However, in our design, we provided switching stations as intermediate facilities to minimize the
distances.
Appearance – Overhead installations are traditional and are not good aesthetically. Although the
overhead installations seem a good fit, the underground cables have several advantages over the
overhead lines; they have smaller voltage drops, low chances of developing faults and have low
maintenance costs. Recent developments in cable technology make the underground cable more
relevant and popular. Our research and experiences also lead us to use underground installations
as most new settlements around the globe chose underground installation.
The selection of operation mode defines the type of conductor used in our system which is
underground cable. The next step is deciding the voltage level and hence deciding the subsequent
equipment. The voltage levels are selected based on IEC recommended system voltages as shows
in below table and EEP distribution voltage recommendations. The voltage level of the nearby
substations also influences the type of transformers at the substation.
b) Power Estimation
The power estimation is an essential task and forms the basis for the planning of the power
system. There are five methods to estimate power.
Load forecast with load increase factors – This method is based on the existing power
system load and the increase in past years and estimate the future load increase
employing exponential increase functions and trend analyses.
Load forecast with economic characteristic data – Load forecast with economic
characteristic data assumes different relations between economic growth, availability
of energy resources, energy consumption and requirement in general, and growth in
population.
Load forecast with estimated values – Matching existing settlements based on area,
population number, etc. with the new proposed area.
Load forecast with specific loads and degrees of electrification – More exact
planning is possible using development plans from planners and estimating the power
demand based on different types and number of stories.
Load forecast with standardized load curves ‐ Determination of the system load based
on annual energy consumptions of individual consumer or consumer groups, which
can be taken from the service provider.
3.9.1.8 Distribution System Remote Monitoring
The control of the substation, monitoring of the status of the switchgear, feeder loads,
and transformer loading, metering, and other parameters can be remotely monitored.
The choice of a SCADA system will impose technical requirements that will need to be
incorporated in the substation and distribution design.
A SCADA (supervisory control and data acquisition) is an automation control system that
is used in industries such as energy, oil and gas, water, power, and many more. The
system has a centralized system that monitors and controls entire sites, ranging from an
industrial plant to a complex of plants across the country. A SCADA system works by
operating with signals that communicate via channels to provide the user with remote
controls of any equipment in a given system. It also implements a distributed database, or
tag database, that contains tags or points throughout the plant. These points represent a
single input or output value that is monitored or controlled by the SCADA system in the
centralized control room. The points are stored in the distributed database as value‐
timestamp pairs. It's very common to set up the SCADA systems to also acquire
metadata, such as programmable logic controller (PLC) register paths and alarm statistics.
While these systems simplify a given infrastructure, their components are quite
complex. There are five essential parts of a SCADA system as shown in Fig 3.6.
So, SCADA system is proposed in our distribution plan as it fits the technical requirement and it is
already utilized by Ethiopian Electric Power for remote monitoring. The main control station will be at
the substations and each switching station is connected to the control room via fiber optic cables.
1) General description
The main task of road lighting is to assure proper luminous levels on the roads
to enable the good vision for all road users.
2) Standard Use
The right light levels are determined by the internationally accepted standard
Commission (CIE, International Commission on Illumination). This standard
defines the required lighting for every type of motorized road, with roads
classified according to a set of defining characteristics such as traffic volume
and composition, the number of lanes, usage, weather condition (fog, rain), and
type of road surface ( paved, unpaved, cemented, asphalt).
There may many type of roads on this project. The height and spacing between
street pole is depends on the road design, land use and final city plan layout.
Accordingly, the selection of pole height, planning and design, selection of light
fitting and analysis of parameter shall be done after the work land use and
categories with site plan is being finalized.
However, due to its many advantages, Nomo solar pole lighting is proposed
for this project. It has combines remote centralized control and management of
street lights through solar photovoltaic applications and ZigBee wireless
communication technology, 4G communication, cloud computing, Internet of
Things and mobile Internet technologies, with brightness adjustment, active
fault alarm, Lamp cable anti-theft, visual remote control, and other sensor
extension applications. Smart solar street lights can greatly improve the level of
public lighting management, save power resources, reduce operation and
maintenance costs, and increase additional revenue.
Urban street lights serve as the densest urban infrastructure for information
gathering and dissemination. Smart lighting is an important part of the smart
city and the best entrance. Smart solar street lights are an effective support for
the city. Low-power smart solar street light is the perfect embodiment of smart
city new energy application.
Nomo intelligent outdoor lighting solution for Smart City comes with an
upgrade option to become a public streetlight Wi-Fi hotspot. Nomo in
partnership with one of the most advanced routers and wireless ISP systems
manufacturer is able to provide an easily installable wireless device which is
carrying out the public internet hotspot function for the street lighting poles.
Besides it support usb charger (charged service)
1. LED charger indicator light
2. Non slip pad surface
3. 10w transmitter coil
4. Fanless design for quiet operation
5. .Wireless charging chipset control the current flow
6. Thermal protection sensor can dial back power for safer operation
7. Foreign object detection circuit to prevent conductive materials
from receiving the power from the charger.
3.9.2.1 Overview
Telecommunication systems play a very important role in the infrastructure of smart cities. An
excess of networked devices interact to provide safe, convenient and environmentally conscious
new services. Residents in smart cities can enjoy their lives using these services, seamlessly and
without being aware of the existence of the networks.
In cities, transportation, distribution, finance, and energy services are connected to networks and
interact to provide more reliable, convenient, and environmentally conscious new services.
Residents in smart cities will have seamless access to these services without needing to know
about the networks on which they are based.
Recognizing the crucial role of telecommunication sector in the entire economic activities and
impact on growth and developments governors in different regime in the last century have been
attempting to expand this service for citizens, though at different scale. A structurally different
communication institution had and has been established all along in telecommunication history
of the country. In our country, recently the responsible institution to render this service is the
Ethiopian Telecommunication Corporation (ETC). This sector structure has stretched down from
national level up to sub areas.
ETC has been monopolistically providing nationwide telecommunications services since 1996.
These are including consisting of:
Telephone Service is calls which including voice, voicemail and conference and data calls, and
supplementary services that including call forwarding and call transfer. It is also messaging and
multi-media services.
The provision of nationwide telephone service to fulfill the waiting demand is current core
activity for ETC and has been accelerated recent years. From a viewpoint of accessibility to the
telephone service, most of the regions except certain areas (including rural areas) have been
covered to some extent by the telephone network.
A service available to the public for originating and receiving national and international calls and
access to emergency services through a telephone number or numbers in a national or
international telephone
ETC is providing public payphones in a nationwide basis. Since the start of the public payphone
service, ETC established 935 coin telephones as of 2001, and starting card phone system in early
2002. However, the number of public telephones is insufficient compare with other telecom
communication.
A mobile phone or cellphone is a portable telephone that can make and receive calls over a radio
frequency link while the user is moving within a telephone service area, as opposed to a fixed-
location phone landline phone. The radio frequency link establishes a connection to the
switching systems of a mobile phone operator, which provides access to the public switched
telephone network PSTN. Modern mobile telephone services use a cellular network architecture
and therefore mobile telephones are called cellphones cell phones in North America. In addition
to telephony, digital mobile phones support a variety of other services, such as text
messaging, multimedia messaging, email, Internet access (via LTE, 5G or Wi-Fi), short-range
wireless communications (infrared, Bluetooth), satellite access (navigation, messaging
connectivity), business applications, video games and digital photography. Mobile phones
offering only basic capabilities are known as feature phones; mobile phones which offer greatly
advanced computing capabilities are referred to as smartphones.
In 1999 ETC entered into Mobile-phone Service. In 2001, the service covers urban and suburb
areas of Addis Ababa and metropolitan. Nowadays, compare to other countries, Ethiopia is
massively lagging behind in the development of telecommunications. Under the country code
+251, there were a total of 65.39 million connections in 2021. Among them were 64.50 million
mobile phones, which corresponds to an average of 0.54 per person.
Gigaband Solution – Gigabit broadband is an internet connection that offers a speed of 1 gigabit
per second (1Gbps/1GB) or more. The proposed design can accommodate this and has the
following characteristics.
Smart mixed City ‐ A smart city is a municipality that uses information and communication
technologies (ICT) to increase operational efficiency, share information with the public
and improve both the quality of government services and citizen welfare. The following can
be included in this platform.
Smart Transportation
Smart Energy and Water
E – Healthcare
Smart Logistics
Smart Garbage Disposal
Smart Agriculture
Smart Lighting, Smart Parking, Smart Transit, Smart Waste Management, Video Surveill
ance, robotic network, etc.
Digital Transformation – This is the result of the gigabit solution. With such an infrastructure
in place, the following things can be achieved.
Broadband
Main Data Centers, Backup data center, Satellite backup
Cloud Network
Big Data
Internet of things (IoT), SCADA, Robotic network
4K / VR / Game online
Backbone network
• No existing fiber route in the site that cross the Andode Tuma area
• Permanent new fiber route, pipe, and manhole facility design
A suitable choice of fiber and splicing technology should be made. Single ‐mode fiber, normally
compliant with [ITU‐T G.652] and [ITU‐T G.657], is the most appropriate for a wide range of
telecommunication services in the local distribution network since this fiber benefits from
economy of scale and has long‐term potential utility for future services. With the current usage
of single‐mode fiber, splicing techniques will allow typical splice losses of less than 0.5 dB to be
achieved.
As per ITU-T recommendation, only ITU-T G.657 category a fibers are compatible with ITU-T
with G.652 fibers. Using other fiber types will increase the uncertainty regarding the splice value
and compatibility issue.
b) Planning Assumption
Peak power demand for Andode Tuma is known after loads estimation will be done. To
do this, the function of land should be categorized.
The power source for site shall be connected to either two sub-stations or needs new (its
own) sub-station. This is depend on the peak power demand we will get during power
estimation and power forecasting of the project.
Since the electric utility should be Uninterrupted and Quality supply, Smart, Sustainable
and expandable for the supposed NDP project, it shall have a minimum of one power
sub-station, even if it is not sure to estimate the number of sub-station. The load
estimation needs the project plan that indicates the land use categories and function,
estimated and planed number of residences, commercial and business, social service and
so on should be identified first.
The core of smart city implementation is the Internet of Things (IoT). The smart cities
need to have three key features: intelligence, interconnection, and instrumentation which
the IoT can provide. It can be said that the use of the IoT can make the smart cities
feasible. A large variety of sensors including RFID, IR, and GPS, connect the buildings,
infrastructure, transport, networks and utilities through ICT.
In a big picture, a city is a system of systems with a unique history and set in a specific
social and environmental context. For a city to prosper, all the key city systems need to
work together, by utilizing all of their resources to overcome the challenges the city
faces. The “smartness” of a city describes its ability to bring together all its resources, to
effectively operate with maximum possible efficiency to fulfil the purposes it has set
itself.
Therefore, to fulfil our requirements, the Andode Tuma site should have its own telecom
core center/switching center.
The transmission for network access shall be optical fiber from central office to
customers, point-to-multipoint architecture is the better one for its many advantage.
3.9.3.3 Synthesis of Major Finding/planning issue and their implication
One new transmission sub-station is required for Gelan Logistic project
One new telecom central office/core is required(should be installed)
Underground installed optical fiber for telecom transmission system is required from
the nearest switching center.