2023SWTS_ProjectPertaminaRU2(100PM9)20Nov

As of 20 November 2023 progress is 81,9%; 1,9% behind and 2 Days behind schedule. Projected overall slippage is 0 Days

Name
100% 49,5%
­
I. KOM
­
­
90% 44,55%
A. Transport motor ke SWTS
B. Pembongkaran motor
C. Inspeksi motor 80% 39,6%
D. Inspec on report
­
A. Electrical test stator sebelum overhaul 70% 34,65%
Actual
B. Stator core test / Ring flux test
Forecast
C. Cleaning stator coil
D. Oven dan Varnish stator 60% 29,7%
E. Final Electrical test stator
F. Stator ready
­ 50% 24,75%
A. Cleaning rotor
B. Penggan an sha
C. Balancing rotor 40% 19,8%
D. Rotor ready
­
A. Rebabbit bearing
30% 14,85%
B. Fabrikasi labyrinth seal
C. Cleaning dan Repain ng frame, cooler dan ter…
D. Other parts ready
20% 9,9%
­
A. Assembly motor
B. Repain ng motor
10% 4,95%
C. Final test motor
D. Transport motor
E. Motor kembali ke plant
Period Actual % 44 38
Period Baseline 1 % 44 50 7
Month Oct Nov Dec …
Year 2023 …

Page ­ 1. Version Number: 1, issued on 20/11/2023.