Date:

20/10/2022
Daily Activities Report
Day: 6
Start : 17/10/2022
Work Package/Project no. 05/PHR/TAR/SPHR00129A/10/2022
Work package/Project Title Major Service TX-3 at 8D Substation
PIC/Lead Crew Angga Anggriawan

HES METRIC AND ISSUES


LPO: - SWA: - IHE : 1 Confine Space: - Air Quality: Clear
SIFO: 3 SSWA: - WUNPL : - GPW/WAH : 1 Rain: - hours
DAFW : - Hot Work : 0 Lifting : Hazard Hunt: 0 Man Hours : 120
Progress & Overview
Progress;
Plan Vs Actual: 16,31% VS 12,23% (Behind Schedule)
Overview;
(Work In Progress as per 20 October 2022)

1. Neutral Grounding Resistor


 Electrical test before (IR test, ohmeter test)
 Service NGR (Clean all components and brush incoming and outgoing terminal)
 After service test (IR test, ohmeter test)
2. Potential Transformer TX 3
 Electrical test After service (IR test, TTR test)
 Reconnect jumper primary & secondary
 Take down 1 unit Cooling Fan TX3

Finding / Issue Action Plan/Progress

Today Planning & Support Needed (Oct 19)

Major Activities Support Needed

 Service Potential Transformer 13.8 kv at  Waiting Ground Clamp to execute 24


8D Substation Ground spots
 Service Neutral Grounding Resistor
 Take down 1 unit cooling fan TX3

Next Day Activities & Support Needed (July 7th 2022)


Major Activities Support Needed

1. Finishing & Repaint NGR 3 8D Substation


2. Service Cooling System TX3
 None
List of crews:
1 Angga Anggriawan (PMcow) 6
2 Kurnia Ilahi
3 Zikri Pradana
4 Edyson
5 Zuldelfi
Note :

 Andris off-site (training TKPK 2)


 Rahmil (support Assembly MSU Nella S/S)
Documentation

NGR Cleaning Proccess Reconnect PT jumper Proccess


Electrical Test Result