Professional Documents
Culture Documents
Standard Detail
3. TOP OF PAD TO BE SMOOTH, LEVEL AND CLEARED OF ALL
FRAMING MATERIAL AFTER CONCRETE SETS.
EDGE TO CL OF #6, EQUALLY SPACED, MIN. 4. NO WALLS SHALL BE BUILT AROUND GENERATOR, NOR
LENGTH OF THE PAD SPACING @ 7-1/2" CENTER CANOPIES ABOVE GENERATOR.
18"
TO CENTER
5. ALL CONDUIT ENTERING SLAB TO BE VERTICAL AND AT A
GROUND ROD, SEE NOTE 12 90° ANGLE WITH TOP OF SLAB. STUB ALL CONDUITS 1"
ABOVE TOP OF CONCRETE PAD. PROVIDE ALL SPARE
12"
#6, EQUALLY SPACED,
(W) + 24" MIN. SPACING @ 14-5/8" CONDUITS WITH PULLSTRINGS AND PLASTIC CAPS.
12" CENTER TO CENTER
6. COORDINATE WITH UNL UTILITIES TO ALLOW ANY AND ALL
INSPECTIONS BEFORE, DURING AND AFTER
CONDUIT STUB UP AREA. CONSTRUCTION OF PAD.
VERIFY EXACT SIZE AND
12" LOCATION WITH GENSET. 7. PROPER REBAR SPACERS SHOULD BE USED TO KEEP THE
(L) + 24" REBAR AT PLACE. USE OF CONCRETE BRICKS AS
#4 CIRCULAR REBAR
SUBSTITUTE OF SPACERS IS NOT PERMITTED.
PLAN VIEW 8. ALL REBAR SHOULD AT LEAST HAVE 3" COVER FROM THE
SCALE: NO SCALE
SIDES OTHERWISE NOTED.
April 2021
N.T.S.
33 70 00 - 07
11. A 48 HOUR INSPECTION NOTICE SHALL BE GIVEN BEFORE
#4 REBAR EQUALLY SCHEDULED POUR WHICH INCLUDES EMAILING THE
#6 REBAR, LOCATED
SPACED AT 3" UNIVERSITY INSPECTOR, ELECTRICAL ENGINEER, AND
AT CENTER OF
CIVIL ENGINEER.
5'-0" MIN.
#6 REBAR,
4 NOS. 12. BOND GROUNDING ROD TO REBAR IN SLAB AND TO
(1) 5/8" DIA. X 10' LONG CU
Detail No.:
GENERATOR FRAME. STUB ROD UP 6" ABOVE TOP OF
GROUND ROD. BOND TO
Scale:
Date:
CONCRETE PAD. SIZE BOND PER NEC 250-66
PAD REBAR WITH UL
REQUIREMENTS BASED ON PHASE CONDUCTOR SIZE.
SECTION VIEW LISTED CONNECTOR.
PROVIDE BRAIDED, BARE CU BOND CABLE FROM GROUND
SCALE: NO SCALE
BAR TO PAD REINFORCING AND TO FRAME. LEAVE
SUFFICIENT LACK ABOVE PAD TO TIE TO GENSET FRAME,
GENERATOR PAD DETAIL
Detail Title: