Introduction: In this Process, the stock removal process has been divided into two steps.
1st step is to withdraw OR PICK the total quantity of material collectively from the storage type for the Multiple
Outbound deliveries and Place it into the Interim storage type of 2step Picking.

2nd step is to Distribute OR Allocate that total material according to Outbound deliveries.

This process is activated at Warehouse level and as per requirement material by material.

PANDAV Page 1
Two Steps Picking Process in SAP-WM

Configuration Steps:

 Activate two step picking for Transfer requirement:

SPRO–>Logistic Execution–>Warehouse Management–>Activities–>Transfers–>Set up 2 step picking process for


Transfer Requirement

Under Transfer requirement control, we need to make following setting.

1) Assign 2 step picking under column 2stP for given Warehouse No

2) If you check column 2-stMatl system will check that 2 Step is Material dependent or not., only those
Materials will be part of 2 steps picking where 2 step provisions is made in Material master under Warehouse
view 1

3) Movement type 850 needs to be assigned as this is movement type will be used during first TO during
collective picking to bring the materials to interim Storage Type 200

PANDAV Page 2
Two Steps Picking Process in SAP-WM

Under transfer type control tab, we need to set up 2 step picking for transfer type- Stock removal

Same configuration is required for outbound Delivery. Configuration path can be found under

 SPRO–Logistic Execution–>Warehouse Management –> Interface–>Shipping–>2 step picking

PANDAV Page 3
Two Steps Picking Process in SAP-WM

Material Master Setting

 Assigning 2 step indicator in Material Master:

We now need to set up Storage type search for 2 step picking. Here we need to assign operation 2 and give
storage type as 200 as stock will be kept at storage type 200 before final allocation.

PANDAV Page 4
Two Steps Picking Process in SAP-WM

Let’s take Example

Here for Better Understanding we are going to execute 2 Step Picking Process for STO with Delivery

S.T.O PO created: 4500024943 & 4500024944

Suppling Plant: M001 & Receiving Plant: M101

T code VL10B: Create outbound delivery (OBD)

Here we have Created OBD for both PO

OBD 80018232 FOR PO - 4500024943

OBD 80018233 FOR PO - 4500024944

PANDAV Page 5
Two Steps Picking Process in SAP-WM

T code: VL06P: Create Group with reference to outbound Delivery

Here we need to create Group of all OBD So that you need to select both OBD follow the step as marked in below
Picture.

PANDAV Page 6
Two Steps Picking Process in SAP-WM

Once the successfully Group created then line item will be green.

Here GROUP FOR OBD is 6546 Created

PANDAV Page 7
Two Steps Picking Process in SAP-WM

T CODE LT72: Activate 2 step picking for Group of OBD

T code: LT73

PANDAV Page 8
Two Steps Picking Process in SAP-WM

Create removal TO with T code LT0E & Confirm TO with LT12 & Check Whether material goes to storage type
200

T code: LT03

Select line item and click on Generate TO item Save the entries

Once you click on “Generate TO item “then the line item Gray off and TO will create in Background.

PANDAV Page 9
Two Steps Picking Process in SAP-WM

Here TO has been created

PANDAV Page 10
Two Steps Picking Process in SAP-WM

Before Confirm the TO check the Stock overview at Suppling Plant WH (Here M32)

T CODE: LS26

Here you can see that Picking Qty going to updated into Storage type : 200

Confirm TO with T code: LT12 /LT21

PANDAV Page 11
Two Steps Picking Process in SAP-WM

Stock Overview after TO 48 Confirmation, now you can see stock placed in Sto. Type 200

PANDAV Page 12
Two Steps Picking Process in SAP-WM

Evaluation of OBD group for 2 step Picking Process.


1) Here we confirm that whether To Created & confirmed or NOT
2) Create TO for Allocation (Distribution according to OBD) & Confirm the same TO

Run T CODE: LX39

Once you click on Create TO as mentioned 2nd step in above image system will take you on LT42 window for to
creation and Follow the below the step.

PANDAV Page 13
Two Steps Picking Process in SAP-WM

PANDAV Page 14
Two Steps Picking Process in SAP-WM

3) T code LX39:- Here you can see that Allocation process successfully completed

T code LS26: You can see that 20 Picking qty has been placed from storage type: 200 to 916

PANDAV Page 15
Two Steps Picking Process in SAP-WM

T code VL02N: POST GOODS ISSUE Against OBD

Document Flow of OBD after PGI Done

PANDAV Page 16
Two Steps Picking Process in SAP-WM

Here you can see that 20 qty has been issued from Plant M001/SLoc M010/ WH M32 to Plant M101

So that we need to post GR at Plant M101/SLoc M004 /WH M30 with ref to OBD

GR for PO 4500024943 –OBD IS 80018232

GR for PO 4500024944 –OBD IS 80018233

Follow the regular WM process for WAREHOUSE During receiving material (TR->TO -> Confirm TO)

PANDAV Page 17
Two Steps Picking Process in SAP-WM

Now you can see that stock has been placed at M30 warehouse TCODE: LX03

PANDAV Page 18
Two Steps Picking Process in SAP-WM

2 Step Picking Process Overview

 Reference

SAP BLOG:
https://blogs.sap.com/2014/09/24/two-steps-picking-process-in-sap-wm/

You tube Video:


https://www.youtube.com/watch?v=owcfIyX6jMw

PANDAV Page 19

You might also like