JSA (Job Safety Analysis) Sheet

Activity Name:-Diesel Generator operation Ref-

Location:- Date :

Sr.No. Sub-Activity Name Type Of Hazard Risk(s) Involved Risk Control measures
Only inducted worker shall be deputed at the work place.
Untrained worker,lack of
1 Manpower Mobilization Personal injury
skill awareness Given Tool Box Talk to all workers.
Diesel filling in DG shall only be done using tray.
Slip of person/hazardous
2 Filling of Diesel. Spillage of diesel
envoirnment (prone to fire) Ensure DG is stopped before filling fuel.

Ensure fire extinguisher at place

Cordoning of periphery of DG
3 DG operation Fire during operation Burns/loss of property
Disply safety instructions/checklinst. Provide rubber mat around the
DG.
Ensure proper illumination during dark hours.
Darkness, fall of person, Personal injury,damage to Electrical cable should lead min 2 m height. No exposed electrical
4 Work during dark hours
fall of machinery property wire.Earthing.
Route shall be illuminated.

Name & Signature of Site Engineer / Supervisor :___________ Name & Signature of Site In-charge :___________

Name & Signature of Project In-charge :__________ Name & Signature of HSE Officer : ______