QTAR INDUTRIAL LABORATORIES Borehole Observation

Project AL-WAKRA & AL-WUKAIR SEWAGE TREATMENT PLANT


Location Wakrah
Borehole OW-02
Client Calik Enerji Metito Elegancia JV

Sensor Temperat
Observatio Installation Sensor Channel Gauge Pressure Depth
Depth ure Remarks
Date Date SN No. Factor (Kpa) (m)
(m) °C
57087 60 3 6.4523 E-04 29 450.00 14.11
5-Oct-23 20/09/2023
27529 15 4 1.7228 E-01 30 115.33 3.24
57087 60 3 6.4523 E-04 29 450.00 14.11
12-Oct-23 20/09/2024
27529 15 4 1.7228 E-01 30 115.28 3.24
57087 60 3 6.4523 E-04 29 450.00 14.11
19-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.46 3.23
57087 60 3 6.4523 E-04 29 440.00 15.13
21-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.62 3.21
57087 60 3 6.4523 E-04 29 440.00 15.13
22-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.55 3.22
57087 60 3 6.4523 E-04 29 440.00 15.13
23-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.49 3.22
57087 60 3 6.4523 E-04 29 450.00 14.11
24-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.78 3.19
57087 60 3 6.4523 E-04 29 450.00 14.11
25-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.84 3.19
57087 60 3 6.4523 E-04 29 450.00 14.11
26-Oct-23 20/09/2025
27529 15 4 1.7228 E-01 30 115.82 3.19
57087 60 3 6.4523 E-04 30 470.00 12.07
5-Nov-23 20/09/2025
27529 15 4 1.7228 E-01 28 138.65 0.86

Qatar Industrial Laboratories Client


QTAR INDUTRIAL LABORATORIES Borehole Observation
Project AL-WAKRA & AL-WUKAIR SEWAGE TREATMENT PLANT
Location Wakrah
Borehole OW-08
Client Calik Enerji Metito Elegancia JV

Sensor Temperat
Observatio Installation Sensor Channel Gauge Pressure Depth
Depth ure Remarks
Date Date SN No. Factor (Kpa) (m)
(m) °C
56921 60 5 5.8449 E-04 29 480.00 11.05
5-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.32 5.08
56921 60 5 5.8449 E-04 29 480.00 11.05
12-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.41 5.07
56921 60 5 5.8449 E-04 29 480.00 11.05
19-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.39 5.07
56921 60 5 5.8449 E-04 29 480.00 11.05
21-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.74 5.03
56921 60 5 5.8449 E-04 29 480.00 11.05
22-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.71 5.04
56921 60 5 5.8449 E-04 29 480.00 11.05
23-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.69 5.04
56921 60 5 5.8449 E-04 29 480.00 11.05
24-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.57 5.05
56921 60 5 5.8449 E-04 29 480.00 11.05
25-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.45 5.06
56921 60 5 5.8449 E-04 29 480.00 11.05
26-Oct-23 21/09/2023
27540 15 6 1.4848 E-01 30 97.45 5.06
56921 60 5 5.8449 E-04 30 490.00 10.03
5-Nov-23 21/09/2023
27540 15 6 1.4848 E-01 29 111.71 3.61

Qatar Industrial Laboratories Client