METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE COMPOUND–
FOR WAREHOUSE
At FM office Compound–
For Warehouse
Page 1 of 13
Contractor: Sub-Contractor: Client:
Coastal
Contracting The Red Sea Development
Company Company
Project:
FM Compound Offices Construction Of Steel Structure Warehouse
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
TABLE OF CONTENT
Contents
PURPOSE..........................................................................................................................3
SCOPE OF WORK...........................................................................................................3
RESOURCES....................................................................................................................3
DEFINITIONS....................................................................................................................4
METHODOLOGY............................................................................................................10
DOCUMENTATION:......................................................................................................12
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
PURPOSE
To ensure that the blinding for foundation are executed safely and in accordance with the
contract requirements and that all quality assurance/ control activities are conducted in a
systematic manner, works are inspected and conformance is verified and documented.
SCOPE OF WORK
This procedure applies to pouring the PCC which is being carried out for the following
Works.
Construction of steel structure warehouse
PCC is an important component of a building which is laid on the soil surface to avoid direct
contact of reinforcement of concrete with soil and water.This method statement describes
the working procedures for blinding concrete and all related activities. This will include
surface preparation, application, and testing.
RESOURCES
Equipment’s
Spirit level
Measuring tape
Hammer
Hand planer
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Carpenter chisel
Plastic trowel
Steel trowel
Gum boots
Wire Nails
Generator
Air compressor
Electric saw
Personal Protective Equipment (PPE)
Concrete Pump
Thermometer
Materials
Polyethylene plastic sheet
Mix Design C20
Water for curing of PCC.
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
DEFINITIONS
Contractor RAFA Gulf contracting Company
Client/consultant The Red Sea Development Company
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Drivers will have valid licenses accepted in the Kingdom of Saudi Arabia.
Vehicles & Equipment will be inspected daily and prior to the beginning of
work to safeguard good working conditions.
A traffic control plan will be effectuated. Trucks leaving the work area to any road in
service will be covered to prevent falling material which could damage other
vehicles.
Ample welfare facilities including cool drinking water, shaded rest areas and toilets
will be provided in close proximity to the workers.
Entrances and exits to/from the work area as well as haul roads will be approved
prior to commencing any earthwork.
Dust control by watering will be performed to minimize dust generation from
demolition operation.
Heavy equipment operators will be trained and adept.
Solid barricades will be installed where the possibility for traffic entering an
excavation exists.
Mobile phones will not be used during the operation of vehicles or equipment and
by worker’s close proximity to it.
Mobile phones will not be used by flagmen while directing the traffic.
Third-party inspection services must be approved by the client.
Sufficient lighting at the worksite will be provided during nighttime shifts or overtime
work.
At all-time signal men will be present to all heavy equipment during operation.
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Safety Helmet
Safety Shoes
High Visibility Safety Vest
Safety Goggles
Safety Gloves
Ear Plugs
Pre-task Safety Tool Box Talk
Mask
Emergency Procedure
Emergency procedure will be adopted according to approved Health & Safety Plan.
First aid kits will be provided on site for light injuries as well as First Aid Station.
In the event of an emergency all workers will be asked to evacuate and assemble at
the designated assembly area and wait for further instruction from supervisors.
Environmental Issues
Contractor does not envisage any major environmental impact as a result of
excavation activities. No perilous material or the like will be used in the construction
and consequently no perilous chemicals will be stored or used on site.
Assessment of the risk to the environment that may be caused by the works, such
as oil spillage, soil contamination or any other events that may have an adverse
effect on the environment has been made.
The Job Hazard Analysis provides the action and/or procedure taken to minimize
the identified risks.
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Vehicles and equipment will be monitored and inspected for the leakage of fuel, oil,
anti-freeze/coolant as, etc.
Dust control by watering will be performed to minimize dust generation from
earthwork operations.
In order to achieve effective dust prevention, the preventive measures include a
speed limitation on-site at 20km/h, additionally by dampening the source before
particles can become airborne, usually with hand-held hoses or movable sprinklers
available in water tankers.
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
matters.
Assesses the implementation of the Quality Plan and Quality Control Plans on the
site.
Allocates Quality Control personnel to the various areas of site activity.
Supervises inspections, reports, and the documentation issued by inspectors and
collect and file the required Quality Records.
Report directly to Project Manager for site instructions.
Direct and continuous supervision he has the authority to give instruction to workers
under his responsibility and to ensure the safety of his people and equipment.
Reporting to Project Manager and will be responsible for continuously monitoring
the works to ensure implementation and compliance in accordance with this method
statement and compliance with its relevant specifications.
He is responsible for assuring the use of acceptable quality materials, processes,
and workmanship in the Project work and is responsible for conducting inspections
with the consultant.
He is also responsible for conducting the test at the site with an approved third-party
laboratory and consultant.
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Working with and training all employees to manage, monitor, and improve the
health and safety standards in the workplace
Being responsible for all safety inspections in the workplace (for example,
monitoring noise levels in a warehouse)
Assisting with the creation and management of health and safety monitoring
systems and policies in the workplace.
Managing emergency procedures (such as fire alarm drills) and organizing
emergency teams such as fire marshals and first aiders.
Reporting to Project Manager and will be responsible for the following.
Preparing and implementation of site application safety plan.
Ensuring all-time safety at the site.
Organize the safety system at site.
Safety record, sign board, training will be performed regularly at site.
Safety checks and monitoring to ensure safety at all the times.
Surveyor
The Surveyor is fully responsible for all survey works for the location of elements of
construction co-ordinates.
Inspection by clients for W.I.R for survey works.
Foreman
Report directly to the Site engineer for site instructions with direct and continuous
supervision, he has the authority to give instruction to workers under his
responsibility and look for the safety of his people and equipment.
METHODOLOGY
No part of this document or the information it contains may be reproduced or
transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system,
without permission in writing from RSG and RGC
Contractor: Sub-Contractor: Client:
Coastal
Contracting The Red Sea Development
Company Company
Project:
FM Compound Offices Construction Of Steel Structure Warehouse
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Surveyor will validate the level based on the approved drawing and marking around
the blinding perimeter will be provided.
All extra soil and loose material shall be removed from the excavated area where
blinding is to be done.
Anti-termite treatment shall be applied if based on the project specification required.
Separate method of statement will be submitted for the application of anti-termite.
Plastic protection (polythene sheet) will be provided as per approved material
submitter.
The top level of the reference point indicates the designed blinding finish level.
Side shutter shall be fixed as per approved drawing and marking was provided by
the Surveyor.
Finishing level should be marked on the side shutter.
The concrete shall be in accordance to approved mixed design from approved
concrete supplier with the required compressive strength of C20 cube strength at 28
days.
Casting will take place using mobile pump or concrete bucket depending on casting
quantity and as per site condition.
Blinding levels shall be determined via level mark.
Curing will be done as per project specification. No activity will take place without
completing the required curing period as per specification.
Testing
Compressive strength (cylinder/cubes) C20 as per project specification.
Curing
Document:
METHOD STATEMENT FOR BLINDING CONCRETE AT FM OFFICE
COMPOUND–
FOR WAREHOUSE
Curing of concrete will proceed and curing will be of same quality as that specified
for mixing concrete.
DOCUMENTATION: