You are on page 1of 18

`

Project: UNIQUE MEGHNAGHAT 588.31 MW CCPP,


at Sonargaon, Narayanganj, Bangladesh.
Owner:
UNIQUE MEGHNAGHAT POWER LIMITED.

Owner’s Engineer:
TRACTEBEL ENGINEERING PVT. LTD.

Contractor:
GE GLOBAL PARTS AND PRODUCTS GmbH
GENERAL ELECTRIC GLOBAL SERVICE GmbH

Revision History
Rev. RevisionDate Created by Checked by Approved by Brief Description
A 2022-11-16 Jiang Hongda Yu Lingmin Ji Jinguo 1nd Submission 提交

Description current Revision


Rev.A
Cross checked
Department Name Date Signature

Replaces Derived From Project Document Code

UNQ/00/E/A----EP60/EQ/001
Responsible Created by Checked by Approved by Format
Jiang Hongda Yu Lingmin Ji Jinguo DIN A4
Dept. QC

Originator Document Type Document Status


Quality Draft
NEPC
Document Title Identification number

UNQ/00/E/A----EP60/EQ/001
HV Switch-yard Package Rev. Date Lang. Sheet
Installation ITPL A
2022-11-16 en 1/18

Non-Public
© COPYRIGHT 2022 General Electric Company
All rights reserved. The information herein is Proprietary and Technically Exclusive content that is solely owned by General Electric Company
and/or its affiliates. Thus, it is being provided with the explicit expectation of restricted and privileged use. All recipients of this information
shall be deemed to have agreed not to make duplications, reproductions of any nature by any means, modifications, disclosures, or use any
portion of this material; except as preis expressly authorized in writing by the General Electric Company, and/or its legitimate affiliates.
TABLE OF CONTENTS:
SAFETY SYMBOLS ............................................................................................................................................ 2
GENERAL ........................................................................................................................................................... 3
CHECKS BEFORE ERECTION ...........................................................................................................................3
CHECKS AFTER ERECTION ..............................................................................................................................4
FINAL INSPECTION ..........................................................................................................................................16
INSTALLATION COMPLETION ........................................................................................................................ 17
ATTACHMENT ..................................................................................................................................................18

SAFETY SYMBOLS

The user must understand the following symbols used within this document:

CAUTION

Caution indicates a potentially hazardous situation that if not avoided,


may result in minor or moderate injury.
It may also be used to alert against unsafe practices.

Note
Note indicates an important instruction or the best practices
It may also be used to alert against mechanical damage to the equipment

The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to
ensure that the requirements stipulated in drawings and specifications are fulfilled for the product concerned.

GE Document Code Rev. Date Lang. Sheet

UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 2/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

1.00 GENERAL
1.01 Each person's signature / initials in this Document must be Partner Procedure to be Name- / Signature register L B Y R
confirmed with the personal Q-stamp. Followed
Q-Management to maintain name / signature register.

1.02 Ensure that the EHS Requirements, Notification periods, Partner Procedure to be - L - - -
handling of the inspection and test documentation is being Followed
followed

1.03 Ensure that procedures for the correct handling and storage - - L - - -
of the equipment is being followed

1.04 Ensure Civil Work Completion before placing the equipment. Partner Procedure to be Date / Signature in this ITPL L - - -
Followed

2.00 CHECKS BEFORE ERECTION


Before starting erection, make sure that manufacturer safety
2.01 - - L B - -
instructions are available and fully understood.

UNQ/00/E/A----- - L B - -
Before starting erection, make sure that manufacturer
2.02
erection instructions are available and fully understood EP60/EI/001

Verify that the fixation of the support structure on the


2.03 - - L B - -
foundation is carried out according to layout drawings.

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 3/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

Note: Manufacturer specific recommendations must be observed during positioning and erection.

3.00 CHECKS AFTER ERECTION


UNQ/00/E/A----- GAS/00/E/A----- L B Y Q
EP60/EI/001 EP60/TQ/060
SWITCHYARD:
UNQ/90/E/A-----
- Check civil work / foundations are in accordance with
EP60/GA/101
drawing.
UNQ/00/E/A-----
- Check structure position & orientation.
EP60/EA/012
- Check structure level & alignment.
UNQ/00/E/A-----
3.01 - Check that bolts are torqued to the required value.
EP60/EA/019
- Visual check of connection to the indoor earthing &
UNQ/00/E/A-----
verify the earthing resistance..
EP60/EA/030
- Check labelling.
UNQ/00/E/A-----
- Check quality & welding.
EP60/EA/015

And relevant manufacture


instructions /drawings

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 4/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

STRUCTURE ERECTION: UNQ/00/E/A----- GAS/00/E/A----- L B Y Q


- Ensure foundation clearance available from civil EP60/EI/001 EP60/TQ/060
group for structure assembly. UNQ/00/E/A-----

- Check for assembly and orientation of structure as EP60/EA/012

per approved drawing. UNQ/00/E/A-----


EP60/EA/019
- Check that all joints have been properly made with
UNQ/00/E/A-----
proper size of bolts and nuts, cover plates and filler
EP60/EA/030 to 38
washer.
3.02 And relevant manufacture
- Verify all bolts and nuts have been properly tightened
instructions /drawings
as per required torque.

- Check that step bolts have been fixed and tighten


properly.

- Check for the alignment of the equipment structure.

- Check for any bending / sagging of beams /


columns.

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 5/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

CIRCUIT BREAKERS: UNQ/00/E/A----- GAS/00/E/A----- L B Y Q


EP60/EI/001 EP60/TQ/060
- Before erection check for any damage and ensure
that SF6 gas is available in all poles as per And relevant manufacture
instruction manual.
instructions /drawings
- Ensure that breaker is erected with proper handling
equipment, preferably with mobile crane with
appropriate boom. Check slings.

- Ensure erection has been done as per approved


drawing and manual.

- Check for individual pole and CB alignment with


3.03
respect to drive.

- Check for the tightness of pole base bolt with


structure

- Check erection of air receiver.

- Ensure proper flushing of air pipe before filling air in


to air tank.

- Check for the air leakage at pipe joints, valves,


gauge, density monitor, pole to pipe connection

- Check for the filling of SF6 gas as per defined


pressure / temperature curve.

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 6/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

- Check for gas leakage at pipejoints, valves, gauge,


density monitor, pole to pipe connection.

- Check for the checknut tightness of tie rod. ( if


applicable )

- Ensure erection switch cubicle.

- Drain valve in the switch cubical should be properly


closed to avoid leakages.

- Check for nut bolt tightness of cable and pipe


clamps.

- Check for cable termination, ferrules and cable tags


are provided as per cable schedule.

- Lubricate all the moving parts of the CB.

- Refer erection manual of the supplier to erect the CB


correctly.

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 7/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

DISCONNECTOR/EARTH SWITCHES: L B Y Q
- Check mechanical setup of both open & close GAS/00/E/A-----

position of isolator as per manufacturer’s EP60/TQ/060


UNQ/00/E/A-----
specification. EP60/EI/001
- Check operation of mechanism electrically proving And relevant manufacture
both open & close positions as per manufacturer’s instructions /drawings
instructions.

- Check position feedback in each case.

- Check operation of earth switch with disconnector


3.04 open (if applicable).

- Measure joint resistance of closed isolator, Phase A,


B, C.

- Measure joint resistance of closed earth switch,


Phase A, B, C.

- Measure earth continuity of earth switch connection

- Check remote operation of isolator (if mimic control


system available).

- Check the polarity of DC and phase sequence of AC


sources

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 8/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

VOLTAGE TRANSFORMER / CAPACITOR VOLTAGE L B Y Q


TRANSFORMER: GAS/00/E/A-----
UNQ/00/E/A----- EP60/TQ/060
- Ensure no damage and oil leakage before erection.
EP60/EI/001
- Check that name plate is matching single line drawing
And relevant manufacture
reference.
instructions /drawings
- Check that equipment is erected correctly in
accordance with drawing take note for polarity.

- Check that level & alignment are correct.

- Check that porcelain insulators are secured & not


damaged.
3.05
- Check that voltage transformer base is earthed.

- Check correct rating & function of links & fuses.

- Check that secondary signal is connected (if not it


should be open with one terminal earthed see
connection diagram).

- Check oil level up to define level mark.

- Ensure removal of shorting wire between primary


terminal and tank. (for CVT only)

- Check HF bushing terminal earthed properly (if not


used for PLCC)

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 9/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

CURRENT TRANSFORMER: L B Y Q
- Check that name plate is matching single line drawing UNQ/00/E/A----- GAS/00/E/A-----

reference. EP60/TQ/060
EP60/EI/001
- Ensure no damage and oil leakage before erection. And relevant manufacture
- Check that equipment is erected correctly in instructions /drawings
accordance with drawing, take note for the polarity.

- Check that level & alignment are correct.

- Check that porcelain insulators are secured & not


damaged.
3.06 - Check for oil marks, oil level/leakage, damage or any
other defect of primary and secondary terminals and
CT

- Check that current transformer base is earthed.

- Check correct rating & function of links & fuses.

- Check that secondary signal is connected to a closed


circuit (if not, terminals need to be short circuited &
earthed see connection diagram).

- Check oil level up to define level mark.

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 10/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

SURGE ARRESTOR: L B Y Q
UNQ/00/E/A-----
- Check all fixing bolts for tightness. GAS/00/E/A-----
EP60/EI/001
EP60/TQ/060
- Check that the vent ports are clear.
And relevant manufacture
- Check that assembly has been done correctly & instructions /drawings
record serial number of each part.
3.07 - Check that the bushing surfaces are clean & free of
damage.

- Check that leakage current indicators / impulse


counters are erected correctly (if applicable).

- Check earthing connection

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 11/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

CONDUCTOR / TUBE: L B Y Q
UNQ/00/E/A-----
- Check that the installation is in accordance with EP60/EI/001 GAS/00/E/A-----

drawing. EP60/TQ/060
And relevant manufacture
- Check that insulators are assembled correctly & are instructions /drawings
not damaged.

- Check that insulators locking pins are installed


correctly.

- Check that conductors are the correct size.

- Check visually that conductors have no defects


(twists, etc…).
3.08
- Check that conductors are correctly clamped / bolted
/ welded.

- Check that bolts are torqued to the required values.

- Check clearances between conductors are correct.

- Check clearances between conductors & structures


are correct.

- Check that conductor sag has been set to the


manufacture tolerances & is correct.

- Check after putting the switchyard in service that


each connection is not over heating (infrared heat

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 12/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

measurement)

Note : strike off whichever is not applicable .

STRINGING OF MAIN BUS BARS L B Y Q


- Ensure use of correct size of disc insulator and GAS/00/E/A-----
UNQ/00/E/A-----
conductor. EP60/TQ/060
EP60/EI/001
- Check the sag or tension of the bus.
And relevant manufacture
- Check clamping of conductor, tightness of clamp, instructions /drawings
orientation and looping without loss of tension.

- Check for the tightness of carona clamp. (if


3.09
applicable)

- Check for proper spacing and tightness of line


spacers.( if applicable )

- Check the earth/ground clearance.

- Check claming of conductor, tightness of clamp,


orientation and looping without loss of tension.

WAVE TRAP UNQ/00/E/A----- L B Y Q


3.10 GAS/00/E/A-----
- Ensure no damage before erection EP60/EI/001
EP60/TQ/060

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 13/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

- Ensure lifting of WT using lifting lugs only And relevant manufacture

- Check for the tightness of equipment base bolts with instructions /drawings
structure

- Check provision of earthing and tightness of earth


connection

- Check for the clearence between live part to earth


and ground

- Check overall allignment of WT

- Refer erection manual of the supplier for more details


of field activity

PLCC UNQ/00/E/A----- L B Y Q
GAS/00/E/A-----
- Ensure no damage before erection EP60/EI/001
EP60/TQ/060
- Ensure lifting of PLCC using lifting lugs only And relevant manufacture
instructions /drawings
- Check for the tightness of equipment base bolts with
3.11
structure

- Check provision of earthing and tightness of earth


connection

- Check the cable tags and ferrules are provided as per

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 14/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

cable schedule.

- Refer erection manual of the supplier for more


details of field activity

CUBICLES, PANELS & LOCAL BOXES ETC., L B Y Q


GAS/00/E/143b---
- Ensure no damage before erection
002/TQ/015
- Verify that the installed panels or compartments are
assembled according to detail drawings.

- Check and verify that the ground bus links are


UNQ/00/E/A-----
installed between the panels or compartments
EP60/EI/001
according to detail drawings and earthing layout
And relevant manufacture
3.12 - Where applicable, check the tightness of bolts and
instructions /drawings
nuts on the main bus bar links. Make 100 % check by
using a torque wrench and applicable torque limits
according to manufacturer instructions.

- Where applicable, verify that all terminals are tight


and solid on CT / VT circuits for power protection
and measurement.

- Check and verify that all interconnection wirings are


installed and terminated according to manufacturer

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 15/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

instructions and drawings.

- Check and verify the marking and labeling with


correct numbers according to KKS or plant coding
system.

- Check and verify that all transport protections and


supports are removed properly and disposed of.

- Make sure that loose supplied material such as


breakers(if applicable), instruments, etc… are
installed and connected according to assembly and
layout drawings and wiring diagrams.

- Refer erection manual of the supplier for more


details of field activity

4.00 FINAL INSPECTION


As per manufacturer specification, make sure that all required
L B - -
inspections are performed and that results are recorded on
4.01 - -
relevant test sheets.

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 16/18


System Name 1) Performed by B = GE or GE’s representative unit 3) Inspection Type H = Hold point
2) Acceptance by L = Erection Company / Installer M = Witness point
HV Switch yard Package U = Material/Hardware/Equipment Supplier Y = Internal test
K = Customer or his representative 4) Q-Record Q = Q record copy to K
Inspection and Test Plan S = Official acceptance authority Handling R = Internal Record

Step Description Procedure Record Q Activities Remarks Step Completed


No.
1) 2 3 4 Date / Signature

Make sure that labeling is performed with correct numbers


4.02 - - L B - -
according to KKS or plant coding system.

4.03 Make sure that safety signs are fitted where required. - - L B - -
Before handing over the system, make sure that area are clear
4.04 - - L B - -
and clean (tools, debris, etc…)

5.00 INSTALLATION COMPLETION


The Sub-Contractors Quality Manager confirms that:
- All steps of the inspection and test plan are completed and
marked with date and initials (including Q-Stamp)
- All test certificates indicated in the ITPL and other
supportive documents are available, completed and signed L B - R
5.01 - -

___________________________________________________
Name (Print), Date, Signature

HV Switch-yard Package Installation GE Document Code Rev. Date Lang. Sheet

ITPL UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 17/18


`

ATTACHMENT

GE Document Code Rev. Date Lang. Sheet

UNQ/00/E/A-----EP60/EQ/001 A 2022-11-16 en 18/18