Client / Project : Academy of Defence Industries (ADI) Site Location Al Dirab, Riyadh
Inspection Date: 2-Dec-23 Inspection Carried out By: HSE Officer Muhammad Noman Qamar
Risk Level and Observations Closure Time: Extreme Risk /Red- Immediately or within One Week; High Risk /Peel- within Two Weeks, Moderate Risk/Yellow - within Three Weeks Low/Green - within One Month.
Note:- This report to be discussed, agreed with the Operation Team and communicated to the relevant parties. Follow-up and verification to be done until closure accordingly. Record to be maintained in the site Safety Folder.
Multi-Purpose
Statutory
1 ADI Hall. Improper Storage of Materials. HIGH Removal of Materials Requires. SFCL Team ASAP OPEN
Required.
Building B01
Statutory
2 ADI Parking Area. Improper Storage of Materials. HIGH Removal of materials requires. SFCL Team ASAP OPEN
Required.
Multi Purpose
Statutory
3 ADI Hall. Poor-Housekeeping. HIGH Removal of Wastage Requires. SFCL Team ASAP OPEN