Project X Risk Register

Positive Risk Response Options Exploit Share


Negative Risk Response Options Avoid Transfer
Alternate Response Options Contingency

Risk ID Description Risk Owner Risk Trigger

How you know the risk is


Name of person becoming an issue or has
who monitors the reached a point that
Description of the risk risk requires action.

If the expected work


remaining will cost more
There is a chance that the project than $9,000 over budget
cost will exceed the amount that we will need to seek
the company has budged for the additional funding from
EXAMPLE work. Joe Agileguy management.
Enhance Accept Risk
Mitigate Accept Issue
No longer active

Risk Category Probability (1-3) Impact (1-3) PI Score

Group sourced rough estimate


Group defines the types of Group sourced rough of how significant the impact of Probability
risks (technology, estimate of how likely this this risk will be if/when it multiplied by
financial, staffing, etc.) is to occur becomes an issue Impact

Financial 2 3 6
Something which has not happened, but might
Something which has already happened
o longer active

Expected Result, No
Action Risk Response Type Response Trigger

What will happen if the risk Decision made by group How do you know it is
becomes an issue and no on how to respond to this time to put the response
action is taken risk (see above in blue) into play

We will not be able to


secure funding necessary
to complete the project.
Work may stop before When estimated cost for
MVP has been achieved. MVP is within 5K of
Product may never get to approved project total we
market and be deemed a will begin seeking
total failure. Mitigate additional funding.
Response Owner Response Description Expected Impact of Response

Who is responsible for What do you expect will result from the
initiating the response What is the response response

Meet with key stakeholders


to review finished product, Given that our team has a mostly stable
total spend to date, work velocity, a proven ability to meet
remaining and expected commitments and deliver value, we
total spend. Ask for expect the answer to be yes provided
additional funding to the total amount requests is less than
Jimmy Kanban complete work. $25K.