To set clearly the required qualifications for staff to enter, supervise, operator or
Work in transmission substations and the necessary steps to get authorized.
To standardize the authorization procedure in order that all the staff are subjected
to the same principle kingdom wise.
3
• Authorizations for National Grid-SA staff for different business lines ;
Asset Maintenance, Operations and Control , Lines Maintenance and
other related activities executed by Contractors, Generation and
Distribution.
• Specific committees are formed to carry out necessary interviews
and issue proper required authorization.
4
• All operations - include all switching, isolation, application portable
earths for Medium voltages, proving dead and phasing-out,
operation of tap changers, resetting of relay indications,…...
5
Interviews and tests for candidates are conducted by a
permanent committee whose members are drawn from:
6
• PERMANENT COMMITTEE
- Conduct interview
7
• NETWORK OPERATOR DIVISION
Issue Authorization Card
PROJECT DIVISION
Interview applicants for Contractor Staff.
8
Flowchart
NG Staff authorization
9
Start
Control Dispatcher Complete the Two Training Programs For Generation & Transmission
Concerned Division Fill Up The Application In Full, Detailing Experience Of Applicant, etc.
Permanent Committee
Issue Final Recommendation and Send To NWO
Application for Authorization
11
12
The application for different authorization levels shall be
categorized as follows:
13
The authorization levels A1, A2, A3 and SA for the authorized
persons shall satisfy the required authorization test–A2,
authorization test–A1, and authorization site test as
specified in Templates:
15
SA
A1 A2 A3
B1 B2
C1 C2 C3
16
SA
17
A
18
C
19
• All distribution staff have a copy of the current SEC
company safety rules.
• The distribution applicants shall submit their
applications for authorization request completed in full
detailing .
• The distribution applicants shall be interviewed by the
same permanent committee.
• distribution applicants shall only obtain authorization
levels A2, C1, C2 and C3.
20
Start
Distribution Staff
Submit Application For Authorization Request
End
DISTRIBUTION STAFF AUTHORIZATION
C1: To receive STW transmission safety documents needed for distribution work
- Such as connection of new distribution panels with the existing switchgear.
C2 :To receive LOA transmission safety document needed for distribution work :
- Such as layout of distribution cables.
23
• All Contractors’ staff shall have a copy of the current SEC company safety
rules.
• The nominated applicant shall be interviewed by the concerned project
divisions at first.
• After acceptance, the contractor shall fill, sign and stamp the forms
TP-NG-8300-002-003 Request for Temporary Authorization.
and TP-NG-8300-002-004.
• after being signed by project division manager and concerned division
manager for the required work.
• The authorization request to be used is as in TP-NG-8300-002-001
Application for Authorization.
25
• Contractor’s applicants shall be interviewed and tested by the
same permanent committee.
• When succeeded to pass the interview, Contractor’s applicants
shall only obtain competent person’s authorization levels C1,
C2 and C3.
26
Start
End
Contractor Staff Authorization
29
Where:
30
31
32
33
REASONS FOR RENEWAL / CANCELLATION, WITHDRAWAL OF AUTHORIZATION
Switching error
Note: Persons who have had their authorization withdrawn for any reason must follow the full
procedure from the start the process to be re-authorized / renewal.
34
Authorization Levels
• To receive the S.T.W., S.F.T., L.O.A., P.E.A. safety document numbers from RCC
and to take local control of a section of H.V. network with the consent of the
relevant control engineer.
• “B1”; To receive the H.L.W. safety document number from RCC for O.H.L
Transmission System up to and including ………kV.
35
Authorization Levels
36
Authorization Levels
“A1”
• To carry out all operations on Transmission System
• To receive the S.T.W., P.E.A. and L.O.A. safety document numbers from RCC.
“A2”
• To carry out all operations on Transmission System
“A3”
• To receive the L.O.A. safety document number from RCC for a precisely defined
job related to contractor work as described in the authorization card.
37
Authorization Levels
“B1”;
• To receive the H.L.W. safety document number from RCC for O.H.L
Transmission System
“B2”
• To receive H.L.W. safety document to carry out the HLW on OHL
Transmission System
38
Authorization Levels
“C1”
• To receive S.T.W., S.F.T, P.E.A. and L.O.A.
“C2”
• To receive L.O.A.
“C3”
• To enter transmission substations for work purposes such as taking readings and
general inspection.
39
Color Codes
40
Senior Authorized Persons shall be in pink color
41
Authorized Persons shall be in yellow color
42
Competent Persons shall be in white color
43
REASONS FOR RENEWAL / CANCELLATION
/ WITHDRAWAL OF AUTHORIZATION
44